John C. Kohler Co. v. United States

498 F.2d 1360, 20 Cont. Cas. Fed. 83,156, 204 Ct. Cl. 777, 14 U.C.C. Rep. Serv. (West) 1159, 1974 U.S. Ct. Cl. LEXIS 239
CourtUnited States Court of Claims
DecidedJune 19, 1974
DocketNo. 4-73
StatusPublished
Cited by12 cases

This text of 498 F.2d 1360 (John C. Kohler Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
John C. Kohler Co. v. United States, 498 F.2d 1360, 20 Cont. Cas. Fed. 83,156, 204 Ct. Cl. 777, 14 U.C.C. Rep. Serv. (West) 1159, 1974 U.S. Ct. Cl. LEXIS 239 (cc 1974).

Opinion

Per Cueiam :

This case comes before the court on defendant’s request, filed January 3, 1974, for review by the court of the recommended decision, filed October 18,1973, by Trial Judge Hal D. Cooper pursuant to Rule 166 (c) on plaintiff’s motion and defendant’s cross-motion for summary judgment. The court has considered the case on the briefs and oral argument of counsel. Since the court agrees with the said decision, as hereinafter set forth, it hereby affirms and adopts the same as the basis for its judgment in this case. Therefore, plaintiff’s motion for summary judgment is granted, defendant’s cross-motion for summary judgment is denied and the case is remanded pursuant to Pub. L. 92-415, 28 U.S.C. § 1491, and General Order No. 3 of 1972, to the Department of Agriculture Board of Contract Appeals for a determination of the amount plaintiff is entitled to receive for restoring the boiler to an operable condition. Plaintiff’s counsel is designated to advise the court, by letter to the clerk, of the status of the remand proceedings as provided for in paragraph 9(a) of the General Order, with said advice to be given at intervals of 90 days or less, commencing from the date of this opinion.

OPINION OP TRIAL JUDGE

Cooper, Trial Judge:

Plaintiff contracted to install a boiler for defendant. After plaintiff had installed and tested the boiler, but before final payment to plaintiff had been made, defendant took custody of the boiler and operated it [781]*781from mid-April to July 18, 1967. On July 18, while the paperwork necessary to conclude the contract was being processed, the boiler exploded. The question presented in this Wunderlich Act review is as to which of the parties should bear the cost of repairing the boiler.

Although plaintiff contended the explosion was caused by the negligence of defendant’s operator, the contracting officer assigned the cause of the explosion to defective equipment and required plaintiff, at plaintiff’s expense, to make the repairs necessary to restore the boiler to operating condition. Plaintiff timely appealed the decision of the contracting officer to the Department of Agriculture Board of Contract Appeals (Board). After a full hearing with oral testimony and documentary evidence, the Board concluded that the cause of the explosion could not be determined with reasonable certainty; however, it sustained the decision of the contracting officer, finding that defendant had never accepted the boiler and that plaintiff had failed to discharge its burden of showing that it was not responsible for the explosion.1

The matter is before this court on the parties’ cross-motions for summary judgment. Prom a review of the administrative record, and upon consideration of the motions and arguments in support thereof, it is concluded, for the reasons hereinafter stated, that plaintiff’s motion should be granted and defendant’s cross-motion denied.

I.

Under contract No. 12-14-100-8968(73), plaintiff undertook to perform all work required to remove an existing boiler and install a new “package boiler” in one of defendant’s buildings. By mid-April 1967, the old boiler had been removed and plaintiff had completed installation and testing of the new boiler. On or about April 15, 1967, defendant assumed custody of the boiler and began regular operation of it with its own personnel. From the commencement of its operation, the boiler functioned without mishap until July 17, 1967, when difficulty was experienced in getting the boiler started. It was the next day, July 18, as defendant’s operator commenced the first of the approximately 60 steps necessary to start the boiler, that it exploded.

[782]*782ii.

The first issue presented, in this review is as to the cause of the explosion. The Board found that the explosion could have been caused either by operator negligence or defective equipment 'but concluded that it was not possible to determine with reasonable certainty which of the two actually caused the explosion. This conclusion by the Board, plaintiff asserts, is not supported by substantial evidence.

The controversy as to the cause of the explosion revolves around a steam atomizing switch that is a part of the boiler controls. During start-up of the boiler, it is necessary to use both a light oil gun and a heavy oil gun. The start-up procedures call for the steam atomizing switch to be placed in a “mechanical” position when the light oil gun is in use. Upon removal of the light oil gun and replacement by the heavy oil gun, the operator must turn the steam atomizing switch from the “mechanical” position to the “steam” position. According to defendant’s operator, the explosion occurred within a brief period — 10 to 15 seconds — after the light oil gun had been replaced by the heavy oil gun.

Two facts regarding the atomizing switch are not in substantial dispute. The first is that a Mr. White, an employee of plaintiff’s subcontractor, investigated the explosion on the morning it occurred and found the atomizing switch in the “mechanical” position rather than in the “steam” position. The other fact is that, during defendant’s investigation, it was found that the steam atomizing switch had been wired backwards.

Based on his observation of the atomizing switch, Mr. 'White’s testimony supported the theory that the explosion was caused by the failure of the operator to change the atomizing switch from a “mechanical” to a “steam” position when the light oil gun was replaced by the heavy oil gun. Defendant’s expert theorized that the explosion was caused either by operator negligence in failing to turn the atomizing switch or by improper wiring of the atomizing switch.2

[783]*783The operator denied that he had failed to change the steam atomizing switch from the “mechanical” to the “steam” position. His explanation for the switch being in the “mechanical” position was that he turned it back to that position when he was securing the boiler after the explosion had occurred. However, plaintiff introduced evidence that would tend to show that there was no reason to alter the position of the steam atomizing switch after the explosion since this would have no significant effect on the operation of the boiler. This evidence also indicated that it was more desirable to leave the steam atomizing switch in a “steam” position which would have introduced steam to the boiler to smother any fire that may have resulted from the explosion.

The experts for both parties expressed opinions on whether failure to turn the atomizing switch could cause an explosion and whether improper wiring of the switch could result in an explosion. There is testimony supporting the conclusion that, under at least some circumstances, both of the alleged causes could result in an explosion.

From this brief summary of the record, it is apparent that plaintiff is correct in its contention that there is substantial evidence, although largely opinion testimony, that the cause of the explosion was due to operator error. However, there is substantial opinion testimony to the contrary. The difficulty is simply that few measurable, objective facts bearing on the cause of the explosion were available and it was necessary for the witnesses on both sides to theorize as to the cause of the explosion.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Paragon Defense Solutions, Inc.
Armed Services Board of Contract Appeals, 2025
In Re Qimonda Richmond, LLC
435 B.R. 215 (D. Delaware, 2010)
Enron Federal Solutions, Inc. v. United States
80 Fed. Cl. 382 (Federal Claims, 2008)
Ow-Taylor v. Overseas Private Investment Corp.
8 F. App'x 957 (Federal Circuit, 2001)
Thorne v. Department of Health & Human Services
4 F. App'x 943 (Federal Circuit, 2001)
E.I. Du Pont De Nemours & Co. v. United States
37 Cont. Cas. Fed. 76,242 (Court of Claims, 1991)
Beta Systems, Div. of Velcon Filters, Inc. v. United States
35 Cont. Cas. Fed. 75,613 (Court of Claims, 1989)
Marine Midland Bank v. United States
687 F.2d 395 (Court of Claims, 1982)
CRF v. United States
624 F.2d 1054 (Court of Claims, 1980)
Tennessee Valley Authority v. Westinghouse Electric Corp.
429 F. Supp. 940 (E.D. Virginia, 1977)
ITT Arctic Services, Inc. v. United States
524 F.2d 680 (Court of Claims, 1975)

Cite This Page — Counsel Stack

Bluebook (online)
498 F.2d 1360, 20 Cont. Cas. Fed. 83,156, 204 Ct. Cl. 777, 14 U.C.C. Rep. Serv. (West) 1159, 1974 U.S. Ct. Cl. LEXIS 239, Counsel Stack Legal Research, https://law.counselstack.com/opinion/john-c-kohler-co-v-united-states-cc-1974.