E.I. Du Pont De Nemours & Co. v. United States

37 Cont. Cas. Fed. 76,242, 24 Cl. Ct. 635, 1991 U.S. Claims LEXIS 577, 1991 WL 260783
CourtUnited States Court of Claims
DecidedDecember 5, 1991
DocketNo. 311-89 C
StatusPublished
Cited by5 cases

This text of 37 Cont. Cas. Fed. 76,242 (E.I. Du Pont De Nemours & Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
E.I. Du Pont De Nemours & Co. v. United States, 37 Cont. Cas. Fed. 76,242, 24 Cl. Ct. 635, 1991 U.S. Claims LEXIS 577, 1991 WL 260783 (cc 1991).

Opinion

OPINION

HODGES, Judge.

The President of the United States asked E.I. Du Pont De Nemours and Company (DuPont) to perform a vital service in 1950: [636]*636to design, construct, and operate a facility for nuclear production for the nation’s defense program. DuPont’s response was the Savannah River Plant near Aiken, South Carolina.

For various reasons, plaintiff did not want to make a profit from the Savannah River project, but it did not want to bear any losses either. The result was an unusual contract whereby the United States agreed to indemnify DuPont from virtually all costs and expenses of the project, specifically including “all welfare and employee relations plans, policies and practices of the Contractor.”

Plaintiff had a severance payment policy which paid DuPont employees generously when they were terminated for lack of work. Plaintiff interpreted the term “lack of work” to mean “lack of work with DuPont.” Defendant repeatedly urged plaintiff to discard the policy as applied to successor contractors. That is, if the project were taken over by another contractor, and the contractor agreed to hire all DuPont employees, there would be no loss of work and no reason for severance pay.

Plaintiff and defendant apparently agreed to disagree over the years, and did not resolve the issue until 1985. Thereafter, Westinghouse assumed responsibility for the Savannah River Project. Westinghouse retained most of DuPont’s employees, as it had promised the federal government. Defendant notified plaintiff that severance payments to its employees under the circumstances would not be appropriate, and in fact would not be reimbursed by the government. DuPont made approximately $64 million in payments to its employees anyway, and defendant refused to reimburse these payments.

The issue is whether severance payments made in accordance with plaintiff’s severance policy are reimbursable costs under the terms of the contract between plaintiff and defendant. Both parties filed motions for summary judgment. For the reasons stated herein, and during oral argument on June 4, 1991, plaintiff’s cross-motion for summary judgment is GRANTED; defendant’s motion for summary judgment is DENIED.

FACTS

1. Background

In 1950, plaintiff E.I. Du Pont De Nemours and Company (DuPont) embarked on a project at the request of President Harry S. Truman. The task was to produce nuclear materials for the nation’s defense program; the project was the design, construction, and operation of nuclear production facilities which became known as the Savannah River Project. The President felt that it was a task plaintiff was “uniquely qualified” to perform.

DuPont had supplied the Army with plutonium for the Manhattan Project during World War II. Partly as a result of its experience with that contract, plaintiff did not want to make a profit from the Savannah River Project. The result was a contract by which the United States paid plaintiff a nominal fee of $1.00 and agreed to reimburse DuPont for all costs and expenses incurred under the agreement. While DuPont did not want a profit on the project, it did not want to bear any of the costs of its services. Therefore, the contract was unusual in the breadth of its indemnity clause. By Article XXXIV, defendant indemnified plaintiff from all costs and expenses excepting only willful or bad faith misconduct by corporate officers, and costs specifically listed as non-reimbursable in the contract.

Article XV of the contract provided for the reimbursement of any “costs and expenses incurred ... with respect to all welfare and employee relations plans, policies and practices of the Contractor.” Reimbursement under this article was not conditioned upon prior approval from the government so long as the costs were incurred pursuant to policies that were not implemented specifically for the Savannah River Project.

DuPont’s employee relations policy was an important issue from the beginning of negotiations between plaintiff and defendant in 1950. Plaintiff added a severance [637]*637plan in 1956 which admittedly was very generous. However, defendant knew about this plan and discussed it repeatedly ’ with plaintiff until 1984, when the matter finally was resolved.

Plaintiff testified before a Joint Congressional Committee on August 4, 1950 that it intended to treat the employees transferred to Savannah River in the same manner as those on its commercial side. Plaintiff warned the Committee of the unusually generous nature of DuPont’s benefit policy as compared to the industry standard. Plaintiff explained to the Committee that it wanted the government to know of this progressive attitude toward its benefit plans up front, for fear that they might be a potential source of contention regarding the government’s obligation to reimburse.

Another feature of this contract made it unusual. President Truman exempted the agreement between DuPont and the Atomic Energy Commission from those provisions of law relating to contracts which could raise any question as to the validity or enforceability of the agreement. This order was issued by President Truman on September 27, 1950, pursuant to section 12(b) of the Atomic Energy Act of 1946 (now codified at 42 U.S.C. § 2202 (1988)), upon his finding that “such, action is in the interest of the common defense and security....”

2. Severance Pay

In 1956, plaintiff informed the government of its new employee termination plan, “Treatment To Be Accorded Employees Terminated on Account of Lack of Work.” A terminated employee would receive one week’s salary for each year’s service with DuPont. Conditions of payment were (1) involuntary termination from the permanent employment roll of the company, and (2) termination caused by lack of work. The severance plan formalized DuPont’s long-standing practice, but it was more liberal. It superseded the layoff-notice policy which provided for either a notice period or a week's pay when termination was attributed to lack of work.

Plaintiff informed the government that it considered these payments to be a reimbursable cost because this was a corporate policy applicable to all permanent employees. No distinction would be made between plant shutdowns and other types of termination for lack of work. The government withheld formal concurrence because the plan could apply to a successor contractor. In such a situation plaintiff’s employees likely would be retained by the successor, and therefore a “lack of work” would not exist.

Plaintiff confirmed that it intended to apply the plan even in a successor contractor situation. Plaintiff’s position stemmed from the company’s belief that its employees had developed expectations of continuing career employment with DuPont. If such opportunities were lost, the employees should be compensated.

The parties’ views on the severance pay issue were at odds during subsequent extensions of the contract. In 1959, the government modified its own severance pay policy by prohibiting the reimbursement of severance payments made under such circumstances. During negotiations for contract renewals, the government repeatedly asked plaintiff to make the severance payment plan at Savannah River consistent with the government’s. Plaintiff refused.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Linda Newman Construction Co. v. United States
48 Fed. Cl. 231 (Federal Claims, 2000)
Northrop Grumman Corp. v. United States
47 Fed. Cl. 20 (Federal Claims, 2000)
Huna Totem Corp. v. United States
40 Cont. Cas. Fed. 76,937 (Federal Claims, 1996)
Conoco Inc. v. United States
35 Fed. Cl. 309 (Federal Claims, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
37 Cont. Cas. Fed. 76,242, 24 Cl. Ct. 635, 1991 U.S. Claims LEXIS 577, 1991 WL 260783, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ei-du-pont-de-nemours-co-v-united-states-cc-1991.