Linda Newman Construction Co. v. United States

48 Fed. Cl. 231, 2000 WL 1704485
CourtUnited States Court of Federal Claims
DecidedNovember 13, 2000
DocketNo. 00-317 C
StatusPublished
Cited by5 cases

This text of 48 Fed. Cl. 231 (Linda Newman Construction Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Linda Newman Construction Co. v. United States, 48 Fed. Cl. 231, 2000 WL 1704485 (uscfc 2000).

Opinion

OPINION AND ORDER

HEWITT, Judge.

This is a suit by a government contractor for an equitable adjustment for costs arising out of changes to a contract for the construetion of an addition to a Veterans Administration (VA) hospital. Plaintiff contends that a reservation clause in the change order entitles plaintiff to additional compensation for the costs associated with the delay in the completion of the contract. Defendant argues that the adjustment plaintiff requests is for additional overhead costs, and that another clause in the change order, read together with the original contract, precludes compensation for the additional overhead costs sought. The action is before this court on Defendant’s Motion for Summary Judgment (Def.’s Mot.). Because plaintiff has not shown that the reservation clause can fairly be interpreted as covering the delay costs that it seeks, Defendant’s Motion is GRANTED.

1. Background

Unless otherwise noted, the following facts are taken from plaintiffs Complaint.

Plaintiff entered into a contract with the VA on July 1, 1996, for the construction of the Ambulatory Care Addition to the Veterans Affairs Medical Center in Gainesville, Florida. The VA agreed to pay plaintiff $19,858,000.00 for its work. Over the course of construction, the VA issued 244 change orders, nineteen of which extended the completion date of the contract by a total of 199 days;1 pursuant to each of those nineteen orders, the parties executed Field Supplemental Agreements (FSAs), which modified the original contract. DPFUF H 3.2 Each FSA calculated the direct cost of the change and provided that plaintiff was entitled to compensation for overhead for up to ten percent of the direct cost of the change, along with a ten percent profit. Id. H 4. Each FSA also reserved to plaintiff the right to seek an equitable adjustment for costs arising from the impact of the change orders on unchanged work. Id. 115.

[233]*233The contract was completed in October 1999. Plaintiff sought an equitable adjustment in the amount of $321,156.77 by a claim dated December 6, 1999. DPFUF App. at 57-58. The claim encompassed certain costs claimed to have been incurred by plaintiff and by its subcontractors as a result of the change orders. Appendix to Defendant’s Proposed Findings of Uncontroverted Fact (DPFUF App.) at 57-58. The VA rejected plaintiffs claim on April 25, 2000, on grounds that the claimed expenses were overhead costs and were therefore already included in the price of the contract change. DPFUF H 7. Plaintiff brought suit in this court under the Contract Disputes Act, 41 U.S.C. § 609(a)(3), on May 30, 2000, claiming $321,156.77 in damages.

II. Summary Judgment

Summary judgment is appropriate when “there is no genuine issue of material fact and ... the moving party is entitled to judgment as a matter of law.” Rule of the Court of Federal Claims (RCFC) 56(c); Southfork Sys., Inc. v. United States, 141 F.3d 1124, 1131 (Fed.Cir.1998). A fact that may affect the outcome of the suit is material. Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248, 106 S.Ct. 2505, 91 L.Ed.2d 202 (1986). The court must construe all facts in the light most favorable to the nonmovant. Id. at 255,106 S.Ct. 2505. The movant bears the initial burden of showing that there is no genuine issue of material fact; if the movant satisfies that standard, the burden shifts to the nonmovant to show, for each issue on which it will bear the burden of proof at trial, that there is a “genuine issue for trial.” Cel-otex Corp. v. Catrett, 477 U.S. 317, 323-24, 106 S.Ct. 2548, 91 L.Ed.2d 265 (1986). Contract interpretation is a question of law appropriately resolved on summary judgment. Gov’t Sys. Advisors, Inc. v. United States, 847 F.2d 811, 812 (Fed.Cir.1988).

III. Discussion

A. Contract Interpretation

The contract between the parties was a firm-fixed-price contract as defined in the Federal Acquisition Regulations, since the cost of the contract was not subject to adjustment based on established prices, actual costs, or cost indexes. FAR § 16.203-1. A firm-fixed-price contract “places upon the contractor maximum risk and full responsibility for all costs and resulting profit or loss.” Id. § 16.202-1. Plaintiff assumed the risk, in submitting a bid for and signing a firm-fixed-price contract, that it would be forced to bear costs that it would not be able to recover. Id. Accordingly, unless the parties explicitly agreed otherwise, plaintiff is not entitled to recover its costs arising from delay. See, e.g., ITT Fed. Servs. Corp. v. Widnall, 132 F.3d 1448, 1451 (Fed.Cir.1997); Dalton v. Cessna Aircraft Co., 98 F.3d 1298, 1304 (Fed.Cir.1996). Whether the parties did, in fact, explicitly agree otherwise is the question before the court.

The dispute centers on the effect of a reservation clause in the change orders on the original contract’s limitation on recovery of overhead resulting from change orders. The original contract contemplated possible changes; sections 1.47 and 1.48 set out the procedures governing change orders and specified the costs arising from change orders that the contractor may recover. DPFUF App. at 41-44. Section 1.48, which covered changes costing $500,000 or less,3 provided for overhead recovery, defined as a percentage of the cost of the change, with the percentage declining as the cost of the change increased:

Allowances not to exceed 10 percent each for overhead and profit for the party performing the work will be based on the value of labor, material and use of construction equipment required to accomplish the change. As the value of the change increases, a declining scale will be used in negotiating the percentage of overhead and profit. Allowable percentages on changes will not exceed the following: 10 percent overhead and 10 percent profit on the first $20,000; 7-1/2 percent overhead and 7-1/2 percent profit on the next $30,-[234]*234000; 5 percent overhead and 5 percent profit on balance over $50,000.

DPFUF 112; DPFUF App. at 43. The reservation clause in dispute here both incorporates the overhead recovery limitation in the original contract and reserves to plaintiff the right to seek compensation for “impact” costs, as follows:

This change represents full and complete compensation for all direct costs and time required to perform the work set forth herein, plus the overhead and profit as provided for in the Changes clause in this contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Chevron U.S.A., Inc. v. United States
110 Fed. Cl. 747 (Federal Claims, 2013)
System Planning Corp. v. United States
107 Fed. Cl. 710 (Federal Claims, 2012)
Osage Tribe of Indians v. United States
72 Fed. Cl. 629 (Federal Claims, 2006)
M.J. Paquet, Inc. v. New Jersey Department of Transportation
794 A.2d 141 (Supreme Court of New Jersey, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
48 Fed. Cl. 231, 2000 WL 1704485, Counsel Stack Legal Research, https://law.counselstack.com/opinion/linda-newman-construction-co-v-united-states-uscfc-2000.