Santa Fe Engineers, Inc. v. The United States

801 F.2d 379, 33 Cont. Cas. Fed. 74,377, 1986 U.S. App. LEXIS 20055
CourtCourt of Appeals for the Federal Circuit
DecidedApril 18, 1986
DocketAppeal 85-2682
StatusPublished
Cited by20 cases

This text of 801 F.2d 379 (Santa Fe Engineers, Inc. v. The United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Santa Fe Engineers, Inc. v. The United States, 801 F.2d 379, 33 Cont. Cas. Fed. 74,377, 1986 U.S. App. LEXIS 20055 (Fed. Cir. 1986).

Opinion

DAVIS, Circuit Judge.

This appeal from the Veterans Administration Board of Contract Appeals (VAB-CA) presents the legal question of the correct interpretation of a contract provision used by the Veterans Administration (VA) in its construction contracts. The VABCA upheld the Government’s understanding of the reach and validity of that clause, and rejected those of appellant contractor. VABCA No. 1832, 85-2 B.C.A. (CCH) ¶ 18,008 (1985). We affirm.

I.

In 1979 Santa Fe Engineers, Inc. (contractor) entered into an agreement with the VA for the construction of an outpatient clinic addition and research and education addition at the VA Medical Center, Nashville, Tennessee. In the course of that work, the VA issued a change order substituting gypsum board ceilings in lieu of acoustical tile ceilings in one part of the addition. The parties partially agreed upon an equitable adjustment for that change, increasing the contract price by $38,826.11 and granting a 14-calendar-day time extension. There was no dispute as to the amount to be allowed for the direct costs of the change, but there was a dispute as to delay overhead. The contract contained clauses limiting the amount allowable for overhead and profit (on the changes). The VA insisted that those limits covered all claims for overhead, including overhead claims with respect to the 14-day delay authorized by the change order. The contractor countered that those overhead limits related only to overhead connected with direct costs, not to overhead incurred in connection with the two-week delay. In accepting the change order, the contractor specifically reserved the right to submit a claim for the delay overhead costs.

Such a claim was submitted but was denied by the contracting officer. On appeal to the VABCA, that tribunal held that the contract clause (relating to the limits on overhead) covered delay overhead as well as direct-costs overhead, and the contractor (which did not contest the calculation of the overhead limits if they applied here) had therefore been properly compensated.

II.

The VA contract clause on overhead which grounds the dispute is G-10, CONTRACT CHANGES, providing in pertinent part:

A. Clause 3, Changes and Clause 4, Differing Site Conditions of General Provisions (Construction Contract) are supplemented as follows:
******
4. Allowances not to exceed 10 percent each for overhead and profit for the party performing the work will be based upon the value of labor, material and use of construction equipment required to accomplish the change. As the value of *381 the change increases, a declining scale will be used in negotiating the percentage of overhead and profit. Allowable percentage on changes will not exceed the following: 10% overhead and 10% profit on first $20,000; 7V2% overhead and 7V2 profit on next $30,000; 5% overhead and 5% profit on balance over $50,-000.
* # * * * *
9. Overhead and Contractor’s fee percentage shall be considered to include insurance other than mentioned herein, field and office supervisors and assistants, watchman, use of small tools, incidental job burdens, and general home office expenses, and no separate allowance will be made therefore. 1

Appellant’s position, as we have said, is that this provision does not impose any limit on overhead connected with delay resulting from the change. In principal support of that contention, the contractor first points out that (a) the contractual Changes clause (Clause 3) is uniform throughout the Government and mandatory; (b) this Changes clause was specifically amended in 1967 to cover delay expense due to a change, 2 and (c) the Changes clause as so amended sets no limit to the recovery of delay overhead costs actually and reasonably incurred. It is thus contended that (i) the terms of G-10 need not be read to cover delay overhead, and should not be so interpreted because in effect that would deprive the contractor of reimbursement for its delay overhead; (ii) if nevertheless G-10 is so read (as the VABCA did), that provision conflicts with the amended Changes clause by eliminating a large part (if not all) of delay overhead, in contravention of the broad reach of the amended Changes clause; (iii) in case of such a conflict, the mandatory Change clause prevails; and (iv) adoption of the VABCA’s interpretation would be unfair and inequitable to the contractor which is likely to recover very little or none of its overhead connected with a conceded delay due to the Change order.

This is not an unsubstantial or unreasonable argument, but we think that in the end it cannot prevail. We note, at the outset, that the literal words of G-10 blanket delay overhead as well as overhead on the direct costs incurred by the contractor. There is nothing in the language of G-10 differentiating delay overhead in any way from direct costs overhead. Appellant thus gets no help from the bare language of G-10, but must rely (as it does) on various canons of contract construction.

One of these is the general principle of contra 'proferentem where the contractor’s reading of an ambiguous contract provision is reasonable in itself. The difficulty with applying that canon in this case is that G-10 is drawn directly from a procurement regulation adopted by the VA, 41 C.F.R. § 8-7.650-21 (1982). Our predecessor court has held that agency regulations are not governed by the contra proferentem principle but rather by deference to the reasonable and consistent administrative interpretation. Honeywell, Inc. v. United States, 661 F.2d 182, 186, 228 Ct.Cl. 591 (1981). This same rule of proper deference has continued to be applied to procurement regulations. Paul E. Lehman, Inc. v. United States, 673 F.2d 352, 355, 230 Ct.Cl. 11 (1982). The showing here is that the VA has consistently interpreted G-10 in the way the VABCA did in this instance. See Colton Construction Co., VABCA No. 1574, 83-1 BCA 1116,220 (1982); West Land Builders, VABCA, No. 1664, 83-1 BCA ¶ 16,235 (1983), aff'd, 732 F.2d 166 (Fed.Cir.1984); Jack Cooper Construction Co., Inc., VABCA No. 1663, 84-3 BCA 1117, 703 *382 (1984). And in view of the clause’s own wording, that construction cannot be said to be unreasonable. The administrative interpretation is therefore a decided plus for the Government (even though the contractor’s reading may likewise be reasonable).

Another of appellant’s points is that G-10 conflicts with the uniform and mandatory Changes clause, as amended to cover delay damages. The VA regulation, however, declares that it is “supplementing” the Changes clause, thus indicating that the provision is a part of the Changes clause for VA contracts (not a deviation from that clause, nor a separate or conflicting provision). 41 C.F.R. § 8-1.108(a) (1982).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

SWR, Inc.
Armed Services Board of Contract Appeals, 2014
Sec. Of Energy v. The Boeing Co.
497 F. App'x 978 (Federal Circuit, 2012)
Raytheon Co. v. United States
105 Fed. Cl. 236 (Federal Claims, 2012)
Commonwealth Edison Co. v. United States
56 Fed. Cl. 652 (Federal Claims, 2003)
Navcom Defense Electronics, Inc. v. England
53 F. App'x 897 (Federal Circuit, 2002)
M.J. Paquet, Inc. v. New Jersey Department of Transportation
794 A.2d 141 (Supreme Court of New Jersey, 2002)
MJ Paquet, Inc. v. Dept. of Transp.
761 A.2d 122 (New Jersey Superior Court App Division, 2000)
Linda Newman Construction Co. v. United States
48 Fed. Cl. 231 (Federal Claims, 2000)
Park Village Apartments v. United States
32 Fed. Cl. 441 (Federal Claims, 1994)
City of Tacoma v. United States
38 Cont. Cas. Fed. 76,532 (Federal Claims, 1993)
Reliance Insurance v. United States
36 Cont. Cas. Fed. 75,892 (Court of Claims, 1990)
CCM Corp. v. United States
36 Cont. Cas. Fed. 75,876 (Court of Claims, 1990)
Underground Construction Co. v. United States
35 Cont. Cas. Fed. 75,604 (Court of Claims, 1988)
United States v. Turner Construction Co.
819 F.2d 283 (Federal Circuit, 1987)
The United States v. The Boeing Company
802 F.2d 1390 (Federal Circuit, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
801 F.2d 379, 33 Cont. Cas. Fed. 74,377, 1986 U.S. App. LEXIS 20055, Counsel Stack Legal Research, https://law.counselstack.com/opinion/santa-fe-engineers-inc-v-the-united-states-cafc-1986.