General Builders Supply Co., Inc., on Behalf of Itself and for the Benefit of Hupp, Inc. v. The United States

409 F.2d 246, 187 Ct. Cl. 477, 1969 U.S. Ct. Cl. LEXIS 145
CourtUnited States Court of Claims
DecidedApril 11, 1969
Docket188-68
StatusPublished
Cited by39 cases

This text of 409 F.2d 246 (General Builders Supply Co., Inc., on Behalf of Itself and for the Benefit of Hupp, Inc. v. The United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
General Builders Supply Co., Inc., on Behalf of Itself and for the Benefit of Hupp, Inc. v. The United States, 409 F.2d 246, 187 Ct. Cl. 477, 1969 U.S. Ct. Cl. LEXIS 145 (cc 1969).

Opinion

ON PLAINTIFF’S MOTION AND DEFENDANT’S CROSS-MOTION FOR SUMMARY JUDGMENT

DAVIS, Judge.

General Builders Supply Co., Inc., the plaintiff, made a contract in 1964 with the General Services Administration to furnish 7,859 refrigerators, for use in Germany, at $119 each. General Builders then subcontracted to purchase these articles from the Gibson Refrigerator Division of the Hupp Corporation, at $116. Hupp built pre-production models and submitted them for inspection to the Government, which rejected them three times. The contract was then terminated for default on the ground that the preproduction models failed to meet the specifications. No production refrigerators were made or delivered.

On appeal, the Board of Contract Appeals of the General Services Administration determined that the work had been improperly terminated for default. 1 'The case was returned to the contracting officer for calculation of the recovery for *248 the erroneous termination. General Builders made claim, not only for the costs actually incurred before termination, but also for the anticipated profits said to have been lost by plaintiff and by Hupp. These amounted, plaintiff said, to more than $23,500 for itself and slightly over $102,400 for the subcontractor. The contracting officer allowed recovery of $6,491.77, for the costs, 2 but denied the demand for unearned but anticipated profits. Plaintiff was satisfied with the cost computation but appealed the rejection of the profit. The Board of Contract Appeals affirmed, holding that the default clause in the contract did not permit the award of anticipatory gain. The suit in this court attacks that conclusion. Both parties have moved for summary judgment and there is no factual controversy bearing on the legal question of the Government’s liability for such profits.

The contract’s default article embodied a then new provision (paragraph 3(e)) which was first promulgated in 1962:

If, after notice of termination of this contract under the provisions of this clause, it is determined for any reason that the Contractor was not in default under the provisions of this clause, or that the default was excusable under the provisions of this clause, the rights and obligations of the parties shall, if the contract contains a clause providing for termination for convenience of the Government, be the same as if the notice of termination had been issued pursuant to such clause. If, after notice of termination of this contract under the provisions of this clause it is determined for any reason that the Contractor was not in default under the provisions of this clause, and if this contract does not contain a clause providing for termination for convenience of the Government, the contract shall be equitably adjusted to compensate for such termination and the contract modified accordingly; failure to agree to any such adjustment shall be a dispute concerning a question of fact within the meaning of the clause of this contract entitled “Disputes.” (NOTE: This contract does not contain a termination for convenience clause. Accordingly, the first sentence of above paragraph (e) is inapplicable.)

The application of that provision is the over-all question, and, since plaintiff’s agreement did not contain a convenience-termination article, the narrower issue is whether the phrase “the contract shall be equitably adjusted to compensate for such termination and the contract modified accordingly” precludes the award of unearned profits. 3

It is plain as a pikestaff that this provision was deliberately formulated by the Government in order to by-pass this court’s holding in Klein v. United States, 285 F.2d 778, 152 Ct.Cl. 8 (1961), that, under the older version of the standard default clause, a contractor could recover anticipatory profits if he was defaulted when he was not truly in default. So *249 much is said expressly in General Services Administration’s FPR [Federal Procurement Regulations] Circular No. 25, dated July 25, 1962 (transmitting the revision of the Federal Procurement Regulations which incorporated the new clause). The circular stated (under the rubric of “Explanation of Changes”):

The revision of the default clauses in Standard Forms 32 and 23A is intended to preclude further decisions adverse to the Government similar to the decision in the Court of Claims case of Klein v. United States (285 F.2d 778, Jan. 18, 1961). * * * The revised clauses provide specifically, where the Government has issued a notice of termination for default and such notice subsequently is found to have been issued erroneously, (1) that such termination will become a termination for convenience of the Government if the contract contains a “convenience” termination clause, and (2) that an equitable adjustment will be made to compensate the contractor for the erroneous termination if the contract does not contain such a “convenience” clause. Thus, administrative settlement procedures and related measures of compensation are provided in the contract whenever a termination for default is later determined to be erroneous” (emphasis added).

With this explicit statement, there can be no doubt of the Government’s purpose to cut off the recovery of unearned gain. The reference to the “measures of compensation” “related” to “administrative settlement procedures” makes it absolutely clear that the GSA intended that substantive result.

The only open question is whether this subjective intent was effectively carried into that part of the new clause dealing with those contracts without any provision for a convenience-termination. Plaintiff argues that the normal contractor would not be put on notice by the critical words of the clause — “equitably adjusted to compensate for such termination” — that anticipated profits could not be paid on an erroneous default termination. It is also stressed that, in contrast, the convenience-termination article spells out just that result in its formula for compensation, but that this contractor was told that its agreement was not to be controlled by the convenience-termination formula.

The concept of an “equitable adjustment” has had a long history in federal procurement, going back for about fifty years. See United States v. Callahan Walker Constr. Co., 317 U.S. 56, 63 S.Ct. 113, 87 L.Ed. 49 (1942); United States v. Rice, 317 U.S. 61, 63 S.Ct. 120, 87 L.Ed. 53 (1942); Ribakoff, Equitable Adjustments Under Government Contracts, in Government Contracts Program, The George Washington University, Changes and Changed Conditions 26, 27 (Gov’t Contracts Monograph No. 3,1962). First used in the standard “changes” and “changed conditions” articles, the term has been taken over for other clauses, such as the “suspension of work” and “government-furnished property” provisions. See J. Paul, United States Government Contracts and Subcontracts 430 (1964).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kellogg Brown & Root Services, Inc.
Armed Services Board of Contract Appeals, 2018
Sweetwater, A Wilderness Lodge LLC v. United States
72 Fed. Cl. 208 (Federal Claims, 2006)
General Dynamics Corp. v. United States
69 Fed. Cl. 180 (Federal Claims, 2005)
McDonnell Douglas Corp. v. United States
41 Cont. Cas. Fed. 77,035 (Federal Claims, 1996)
Genstar Stone Paving Products Co. v. State Highway Administration
618 A.2d 256 (Court of Special Appeals of Maryland, 1993)
Delco Electronics Corp. v. United States
35 Cont. Cas. Fed. 75,679 (Court of Claims, 1989)
Salsbury Industries v. United States
35 Cont. Cas. Fed. 75,661 (Court of Claims, 1989)
J.F. Shea Co. v. United States
33 Cont. Cas. Fed. 74,561 (Court of Claims, 1986)
Santa Fe Engineers, Inc. v. The United States
801 F.2d 379 (Federal Circuit, 1986)
Descon System Ltd. v. United States
32 Cont. Cas. Fed. 72,989 (Court of Claims, 1984)
South Louisiana Grain Services, Inc. v. United States
30 Cont. Cas. Fed. 70,493 (Court of Claims, 1982)
Maryland Port Administration v. C. J. Langenfelder & Son, Inc.
438 A.2d 1374 (Court of Special Appeals of Maryland, 1982)
SCM Corp. v. United States
645 F.2d 893 (Court of Claims, 1981)
Fairfield Scientific Corp. v. United States
611 F.2d 854 (Court of Claims, 1979)
Kisco Co. v. United States
610 F.2d 742 (Court of Claims, 1979)
DeMatteo Construction Co. v. United States
600 F.2d 1384 (Court of Claims, 1979)

Cite This Page — Counsel Stack

Bluebook (online)
409 F.2d 246, 187 Ct. Cl. 477, 1969 U.S. Ct. Cl. LEXIS 145, Counsel Stack Legal Research, https://law.counselstack.com/opinion/general-builders-supply-co-inc-on-behalf-of-itself-and-for-the-benefit-cc-1969.