Klein v. United States

285 F.2d 778, 152 Ct. Cl. 8
United States Court of Claims·Decided January 18, 1961·No. No. 20-56·Published·Cited by 38 cases

Opinions

MaddeN, Judge,

delivered the opinion of the court:

This is a suit for damages for the alleged wrongful termination by the Government of a contract between the Government and the plaintiff’s assignor, Beam Radionics Corporation, hereinafter called Beam. The plaintiff is the assignee for the benefit of creditors of Beam. The Government’s original answer denied liability, alleged that the plaintiff had failed to exhaust his administrative remedies, and counterclaimed for alleged overpayments to Beam. By amendment to its answer, filed by leave of court, the Government pleaded fraud on the part of Beam, and added two counterclaims for statutory penalties for fraud, one counterclaim relating to the contract in suit and the other relating to another contract which Beam had with the Government.

On June 27, 1951, Beam entered into a negotiated contract with the Army Corps of Engineers for the furnishing of 1,000 electric lighting sets at prescribed prices per set [11]*11and wit'll prescribed dates for beginning and completing deliveries. The total contract price was $1,675,000. This contract was known as contract 955. Before entering into contract 955 the Government had made an investigation of Beam’s ability to perform. Beam had before that time undertaken and completed a dozen or more other military supply contracts.

Beam made subcontracts for the acquisition of the parts for the electric lighting sets. It planned to itself assemble, test, package and ship the completed sets. The rubber-insulated cable which was to be a part of each set had to meet rigid contract specifications for use at very low temperatures. The Government was to test the cable at its engineering and development laboratory at Fort Belvoir, Virginia. At the time contract 955 was made, no cable meeting the contract requirements had been produced, and the Government was aware of that fact. The United States Rubber Company had been conducting research in the development of rubber-insulated cables, including cables of the type needed for contract 955. The Government’s officials had informed Beam that United States Rubber’s cable came closest to meeting the contract specifications.

Before contract 955 was made, Beam had made another contract, No. 7939, with the Army Corps of Engineers for the furnishing of floodlighting sets which required a somewhat similar cable. For both contracts, Beam had subcontracted the production of the cable assemblies to Brad Harrison Co., and that company had subcontracted the production of the cable itself to United States Rubber. United States Rubber submitted samples of cables to the Corps of Engineers’ testing laboratory at Fort Belvoir in August and October 1951. These samples were rejected by the laboratory. Although delivery of the lighting sets was to have commenced on November 20, 1951, and although by that date not even a sample of cable meeting the contract specifications had been produced, the Government on December 4, 1951, and thereafter until the latter part of February 1952 continued to issue change orders, to make plans for inspection of finished parts, and in other ways to show that it still expected and desired performance of the contract.

[12]*12A new cable sample was prepared for testing in early February 1952. Just before it was submitted, Beam officials bad a conference with Mr. Krauss, a representative of the Government’s contracting officer. The purpose of the conference was the discussion of Beam’s other contract, No. 7939, but Krauss also said he was considering terminating contract 955, or deleting the cable from the contract. Beam’s representative said Beam would be happy to be relieved of the troublesome cable problem.

A cable sample had been submitted on February 9. It passed the test for contract 7939 but not the more rigorous test for contract 955. On February 26, a new sample was submitted. Krauss was aware of this submission. The tests were made, but Krauss made no effort to learn how the tests were progressing. The official laboratory report was not issued until the middle of May.

On April 1, 1952, the contracting officer notified Beam of the termination of contract 955

pursuant to General Provision 11, Default. The reason for this action is your failure to make delivery of the sets as you were obligated to do under the terms of your contract.

The letter also said that it constituted findings of fact from which the contractor could appeal. Beam appealed on April 10, saying it was ready to proceed with the manufacture as soon as the cable submitted for testing had been approved.

On May 21 the contracting officer sent Beam another “Findings of Fact” which said, among other things:

Contractor has failed to supply satisfactory cable within time when delivery schedule could possibly be met. No definite subcontracts were entered into for cable.

These findings further said that Beam’s available space was inadequate for the timely assembling of the lighting sets, and that Beam’s financing was not sufficient for the performance of the contract.

On June 4, 1952, Beam appealed the contracting officer’s decision. The Armed Services Board of Contract Appeals held a hearing in May 1953 and on October 1 decided that the Government had no right to terminate contract 955 for default. The Board held that the Government had, by its [13]*13conduct, waived compliance with, tbe delivery dates prescribed in tbe contract; tbat tbe Government did not prove tbat Beam did not bave sufficient space for tbe timely assembly of tbe lighting sets; and tbat Beam’s financial position was not different at the time of cancellation than it bad been when it was investigated before the award of the contract. The Board found that the cable sample submitted on February 26 complied with tbe specifications of tbe contract.

In tbe course of its discussion the Board said:

Under tbe circumstances of this case, we are of tbe opinion tbat tbe proper remedy was tbat of termination for the convenience of tbe Government, if termination was desired.

On November 27, 1953, tbe contracting officer wrote Beam, referring to the decision of tbe Armed Services Board of Contract Appeals, and saying:

In view of said decision tbe Government deems tbe above notice of default to have been issued pursuant to Clause 21 of the contract entitled, “Termination for tbe Convenience of the Government”, for the complete termination thereof, which became effective as of 3 April 1952, tbe date of the receipt of such notice by the contractor.

The contracting officer thereby sought, a year and a half after tbe event, to convert the April 1,1952, termination for default into an April 1, 1952, termination “in the best interests of tbe Government,” commonly called “termination for tbe convenience of the Government.” If tbat was effectively done, it would mean tbat tbe Government’s action was not wrongful, because tbe contract expressly granted tbe Government tbe right to so terminate under certain conditions. And it would mean tbat tbe Government’s contractual liability to Beam would be limited to tbe items of compensation named in tbat provision of the contract (see finding 2, contract article 21 (e) and (f)), and the liability would, in this and in most cases, be small.

Free access — add to your briefcase to read the full text and ask questions with AI

Klein v. United States, 285 F.2d 778, 152 Ct. Cl. 8 (cc 1961).

285 F.2d 778 (Klein v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

United States v. Hercules, Inc.
929 F. Supp. 1418 (D. Utah, 1996)
Rogerson Aircraft Corp. v. Fairchild Industries, Inc.
632 F. Supp. 1494 (C.D. California, 1986)
Descon System Ltd. v. United States
32 Cont. Cas. Fed. 72,989 (Court of Claims, 1984)
Department of Natural Resources & Conservation v. United States
30 Cont. Cas. Fed. 70,906 (Court of Claims, 1983)
Hageny v. United States
570 F.2d 924 (Court of Claims, 1978)
Brown v. United States
524 F.2d 693 (Court of Claims, 1975)
United States v. Hangar One, Inc.
406 F. Supp. 60 (N.D. Alabama, 1975)
Universal Ecsco Corporation v. The United States
385 F.2d 421 (Court of Claims, 1967)
Warren Brothers Roads Company v. The United States
355 F.2d 612 (Court of Claims, 1965)
Coastal Cargo Company, Inc. v. The United States
351 F.2d 1004 (Court of Claims, 1965)
Coastal Cargo Co. v. United States
351 F.2d 1004 (Court of Claims, 1965)
Acme Process Equipment Co. v. United States
171 Ct. Cl. 324 (Court of Claims, 1965)
C. J. Langenfelder & Son, Inc. v. The United States
341 F.2d 600 (Court of Claims, 1965)