Coastal Cargo Co. v. United States

351 F.2d 1004, 173 Ct. Cl. 259
CourtUnited States Court of Claims
DecidedOctober 15, 1965
DocketNo. 467-59
StatusPublished
Cited by12 cases

This text of 351 F.2d 1004 (Coastal Cargo Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Coastal Cargo Co. v. United States, 351 F.2d 1004, 173 Ct. Cl. 259 (cc 1965).

Opinion

Collins, Judge,

delivered the opinion of the court:

The Department of the Air Force, in September 1958, awarded to plaintiff a contract for the transportation of passengers between Charleston, South Carolina, and Nouas-seur, Morocco. 'Subsequently, after plaintiff had been performing for more than 2 months, the Air Force canceled the contract on the ground that the award to plaintiff had been invalid. In this action, plaintiff charges that the cancellation constituted a breach of contract; plaintiff seeks to recover its unreimbursed expenses and, in addition, anticipated profits.

The pertinent facts can be summarized as follows: On August 13,1958, the Military Air Transport Service (hereinafter “MATS”) issued invitations for bids regarding 13 items of airlift service. One of these items, No. 7, is involved in the present suit. Only “small business firms” were permitted to bid with regard to item 7. Finding 6, infra. The bid opening was held on September 4, 1958. Three firms submitted bids which were lower than plaintiff’s. Before the contracting officer could make an award, he was required to obtain from the MATS Capability Survey Committee a recommendation as to the qualifications of the low bidders.

On September 11th, the committee issued a negative report as to each.of the three lowest bidders. The contracting officer accepted the committee’s recommendation that the three [261]*261low bids be rejected. Moreover, the contracting officer stated that he had decided to (1) find that a condition of urgency existed, (2) issue a certificate to that effect, and (3) proceed with the procurement without referring the rejected bids to the Small Business Administration.1 Thereafter, it was determined that plaintiff was capable of providing the needed transportation. On September 18, 1958, the contracting officer notified plaintiff, by telegram, that it would be awarded the contract.

As a result of protests by the companies whose bids had been rejected, investigations were commenced by the Air Force and by the General Accounting Office (hereinafter the “GAO”). One alleged irregularity related to the preparation of the certificate of urgency. The investigations disclosed that the contracting officer had not executed the certificate until September 25, 1958, although he had dated it September 14,1958.

On October 24, 1958, the GAO issued an opinion to the effect that (1) since the certificate of urgency was issued subsequent to the award of the contract to plaintiff, such certificate was invalid and (2) therefore, the low bidders were entitled to have their capacity judged by the Small Business Administration (hereinafter the “SBA”). On December 9, 1958, after the SBA had determined that Los Angeles Air Service, Inc. (hereinafter “Los Angeles”), the second lowest bidder, was qualified to perform, the GAO [262]*262ruled that the rejection of the bid of Los Angeles had been erroneous. The GAO directed the cancellation of the award to plaintiff and this was accomplished on December 18,1958. On the same date, the contract was awarded to Los Angeles,2

Upon receipt of the notice of cancellation, plaintiff ceased performance of the contract. Subsequently, plaintiff submitted a claim to the GAO. After the denial of its claim, plaintiff instituted the present suit.

The initial question is whether the award to plaintiff was invalid. Defendant contends that the contracting officer violated the applicable regulations when he failed to refer to the SBA the matter of the competency of Los Angeles and of the other low bidders. Therefore, according to defendant, the subsequent award of the contract to plaintiff was illegal. We do not agree with the assertions of defendant.

First, it must be noted that referral to the SBA was not required' in every instance when the bid of a small business concern was rejected for lack of capacity or credit. The pertinent regulation, ASPE. § 1-705.6, provided, in part, as follows:

* * * this procedure [z.e., submission to the SBA] is mandatory except where the contracting officer certifies in writing that award must be made without delay and inserts in the contract file a statement signed by the contracting officer justifying the certificate; (Emphasis supplied.)

Here, the contracting officer, acting in good faith, sought to come within the terms of this exception.3

Defendant argues that, at the time of the award, there was no need to proceed without delay. Thus, defendant asks us to declare that the contracting officer erred when he deter[263]*263mined that a condition of -urgency existed.4 We can assume that, under appropriate circumstances, a court could overturn the decision of a contracting officer that an award must be made without delay. However, this is not a case where interference with the discretion of .the contracting officer would be proper.

The rejection of the low bidders took place at the meeting held on September 10-11, 1958. Finding. 12,- m/m'. Thus, at that point, it became necessary for the contracting officer to determine whether to submit the matter to the SBA. In light of the existing conditions, we cannot say that the decision reached by the contracting officer was either unreasonable or improper.5 For example, the Air Force desired the airlift service to begin by October 1, 1958, and this left a relatively short time for completing award of the contract and commencing performance. Therefore, we conclude that the contracting officer did comply with the regulations and that award of the contract to plaintiff was proper and valid. Cf. John Reiner & Co. v. United States, 163 Ct. Cl. 381, 387, 325 F. 2d 438 (1963), cert. denied, 377 U.S. 931 (1964). It follows that plaintiff is entitled to recover.

As to the proper theory of recovery, our decision in Reiner, supra, is relevant. In Reiner, as in the present case, the plaintiff’s contract was canceled as the result of a GAO ruling that the award was improper. We held that the award to Reiner was not void, but was lawful. 'Slip. op. p. 4. However, Reiner’s recovery was limited to that provided for .in the termination-for-convenience clause. Thus, there was no entitlement to such items as unearned anticipated profits. This court stated, p. 392, the following;

* * * The contracting officer on plaintiff’s contract probably thought that he was cancelling the agreement for illegality. That excuse was not a valid justification [264]*264as we now know, but just as in College Point Boat Corp. [267 U.S. 12 (1925)] a good ground did exist.in the far-reaching right to terminate under the termination-article. That justifiable cause controls the case and. “operate[s] to curtail the damages recoverable” * * *.

The majority opinion went on to point out, p. 393, that:

Just as the failure to invoke the termination article leaves untouched the defendant’s right to rely on the damage limitation of that clause, so the failure to follow the termination procedures of the Armed Services Procurement Regulations (ASPR) is ineffective to broaden plaintiff’s rights of recovery.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Salsbury Industries v. United States
35 Cont. Cas. Fed. 75,661 (Court of Claims, 1989)
Torncello v. United States
681 F.2d 756 (Court of Claims, 1982)
Trilon Educational Corp. v. United States
578 F.2d 1356 (Court of Claims, 1978)
Albano Cleaners, Inc. v. United States
455 F.2d 556 (Court of Claims, 1972)
G. C. Casebolt Co. v. United States
421 F.2d 710 (Court of Claims, 1970)
G. C. Casebolt Co. v. The United States
421 F.2d 710 (Court of Claims, 1970)
Mid-West Construction, Ltd. v. The United States
387 F.2d 957 (Court of Claims, 1968)

Cite This Page — Counsel Stack

Bluebook (online)
351 F.2d 1004, 173 Ct. Cl. 259, Counsel Stack Legal Research, https://law.counselstack.com/opinion/coastal-cargo-co-v-united-states-cc-1965.