Linan v. Housing Auth. /Camden

CourtCourt of Appeals for the Third Circuit
DecidedFebruary 13, 1995
Docket94-5193
StatusUnknown

This text of Linan v. Housing Auth. /Camden (Linan v. Housing Auth. /Camden) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Linan v. Housing Auth. /Camden, (3d Cir. 1995).

Opinion

Opinions of the United 1995 Decisions States Court of Appeals for the Third Circuit

2-13-1995

Linan v Housing Auth. /Camden Precedential or Non-Precedential:

Docket 94-5193

Follow this and additional works at: http://digitalcommons.law.villanova.edu/thirdcircuit_1995

Recommended Citation "Linan v Housing Auth. /Camden" (1995). 1995 Decisions. Paper 45. http://digitalcommons.law.villanova.edu/thirdcircuit_1995/45

This decision is brought to you for free and open access by the Opinions of the United States Court of Appeals for the Third Circuit at Villanova University School of Law Digital Repository. It has been accepted for inclusion in 1995 Decisions by an authorized administrator of Villanova University School of Law Digital Repository. For more information, please contact Benjamin.Carlson@law.villanova.edu. UNITED STATES COURT OF APPEALS FOR THE THIRD CIRCUIT

No. 94-5193

LINAN-FAYE CONSTRUCTION CO., INC.

Appellant v.

HOUSING AUTHORITY OF THE CITY OF CAMDEN

Appeal from the United States District Court for the District of New Jersey (D.C. Civ. No. 90-cv-04651)

Argued: September 23, 1994 BEFORE: BECKER, COWEN and GARTH, Circuit Judges

(Filed February 13, 1995)

Cary L. Flitter (argued) Lundy, Flitter & Beldecos 450 North Narberth Avenue P.O. Box 278 Narberth, PA 19072-0278

Counsel for Appellant Linan-Faye Construction Co., Inc.

Mark D. Caswell (argued) Freeman, Zeller & Bryant Ten Melrose Avenue Woodcrest Pavilion, Suite 400 Cherry Hill, NJ 08003-3647

Counsel for Appellee Housing Authority of the City of Camden OPINION

COWEN, Circuit Judge. Linan-Faye Construction Company Co., Inc. ("Linan-

Faye"), a public housing contractor, appeals from orders of the

district court that granted summary judgment for the Housing

Authority of the City of Camden ("HACC") on Linan-Faye's claims

under public contract law and 42 U.S.C. § 1983. Because the

district court erred in applying federal common law rather than

state law to resolve this dispute, we will reverse and remand to

the district court for further proceedings. Nevertheless, since

we conclude that in the absence of New Jersey law which

specifically interprets "termination for convenience" clauses New

Jersey courts would look to federal common law for guidance, we

will limit the triable issues on remand to a determination of:

(1) the definition of "work performed" for purposes of paragraph

17 of Linan-Faye's contract with HACC; (2) the pre-termination

expenses incurred by Linan-Faye that may be compensable as "work

performed" under paragraph 17 of the contract; and (3) HACC's

liability, if any, for damages resulting from HACC's withholding

of Linan-Faye's performance bond after termination. Finally,

because the district court did not err in determining that Linan-

Faye failed to demonstrate a protectible property or liberty

interest sufficient to support its § 1983 claim, we will affirm

the district court's grant of summary judgment on this claim. I. FACTS & PROCEDURAL HISTORY

On August 11, 1988, HACC advertised for bids on a

housing modernization project. The project involved the

renovation and rehabilitation of 244 housing units and was to be

funded in substantial part by a grant from the United States

Department of Housing and Urban Development pursuant to the

Public and Indian Housing Comprehensive Improvement Assistance

Program ("CIAP"). Plaintiff, Linan-Faye, attended all required

pre-bid meetings and submitted a bid of $4,264,000, together with

supporting documentation which included a bid bond, performance

bond, qualification statement, and required affidavits. Linan-

Faye was the lowest responsible bidder for the job, underbidding

its nearest competitor by $600,000. Accordingly, HACC informed

Linan-Faye that the contract was to be forthcoming.

Linan-Faye engaged in preparatory activities in

connection with the contract, including meeting with prospective

subcontractors, job planning and pricing, talking with relevant

inspectors, and securing insurance. Also, on several occasions,

representatives of Linan-Faye met with HACC and its architect to

discuss specifications and make preparations for the commencement

of physical construction. Linan-Faye, however, never began

physical construction because numerous disputes broke out between

the parties over interpretation of the specifications.

Linan-Faye contends that HACC demanded concessions

before permitting work to begin. HACC maintains that the parties arrived at different interpretations of the project plans and

specifications, and this conflict became evident at pre-

construction meetings. On November 29, 1988, as the result of

these disputes, HACC advised Linan-Faye that it was going to

rebid the project. Linan-Faye filed suit to enjoin this

rebidding and allow it to complete the project as bid.

The district court entered a temporary restraining

order to prevent HACC from accepting further bids. Subsequently,

the court approved a Stipulation of Settlement and Order of

Dismissal with Prejudice, under which the parties agreed to

execute the contract and proceed with the project as originally

planned. Nevertheless, disputes soon broke out again.

On November 22, 1989, HACC issued a Notice to Proceed.

Linan-Faye contends that the notice was limited to an order to

correct certain plumbing problems that were a portion of the

original contract. Linan-Faye refused to proceed in a piecemeal

fashion, and insisted that it would not begin work until a

certain number of vacant buildings were available at the same

time so that it could achieve economies of scale. HACC responded

that it had scattered vacant units available, but not rows of

units.

Subsequently, HACC attempted first to extract the

plumbing segment from the contract and, when that failed,

proposed a complete buy-out of Linan-Faye's contract. The

parties entertained the possibility of a buy-out until July of 1990, at which time HUD informed HACC that it would not approve a

buy-out. HACC reinstated the previous Notice to Proceed by

letter dated July 23, 1990.

At a preconstruction meeting on September 6, 1990,

Linan-Faye informed HACC that it would not start work until the

contract price was increased to reflect the costs incurred by the

delay in commencing construction. HACC responded that Linan-Faye

had to begin work before it would address the issue of the price

increase.

HACC elected to terminate Linan-Faye's contract by

letter dated September 25, 1990. In that letter, Gregory Kern,

the Interim Executive Director of HACC, stated that HACC would

instruct the Modernization Office to assist Linan-Faye in

reclaiming its performance bonds. While the letter did not

mention the terms "breach" or "default," it did state that Linan-

Faye "had continually failed to demonstrate its intent to perform

under the public contract." Letter from Kern to Norman Faye

(September 25, 1990); App. Vol. I at 114-115. HACC confirmed its

decision to terminate by letter dated October 23, 1990.

Linan-Faye objected to the termination and filed the instant

action on October 26, 1990, setting forth theories of recovery

Free access — add to your briefcase to read the full text and ask questions with AI

Related

College Point Boat Corp. v. United States
267 U.S. 12 (Supreme Court, 1925)
Erie Railroad v. Tompkins
304 U.S. 64 (Supreme Court, 1938)
Greene v. McElroy
360 U.S. 474 (Supreme Court, 1959)
Wallis v. Pan American Petroleum Corp.
384 U.S. 63 (Supreme Court, 1966)
Perry v. Sindermann
408 U.S. 593 (Supreme Court, 1972)
Texas Industries, Inc. v. Radcliff Materials, Inc.
451 U.S. 630 (Supreme Court, 1981)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Boyle v. United Technologies Corp.
487 U.S. 500 (Supreme Court, 1988)
United States v. R. H. Taylor
333 F.2d 633 (Fifth Circuit, 1964)
Nolan Brothers, Incorporated v. The United States
405 F.2d 1250 (Court of Claims, 1969)
Herz v. Degnan
648 F.2d 201 (Third Circuit, 1981)
Maxima Corporation v. The United States
847 F.2d 1549 (Federal Circuit, 1988)
Salsbury Industries v. The United States
905 F.2d 1518 (Federal Circuit, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
Linan v. Housing Auth. /Camden, Counsel Stack Legal Research, https://law.counselstack.com/opinion/linan-v-housing-auth-camden-ca3-1995.