Rogerson Aircraft Corp. v. Fairchild Industries, Inc.

632 F. Supp. 1494, 1 U.C.C. Rep. Serv. 2d (West) 1512, 1986 U.S. Dist. LEXIS 26568
CourtDistrict Court, C.D. California
DecidedApril 17, 1986
DocketCV 83-6124-AAH (TX)
StatusPublished
Cited by9 cases

This text of 632 F. Supp. 1494 (Rogerson Aircraft Corp. v. Fairchild Industries, Inc.) is published on Counsel Stack Legal Research, covering District Court, C.D. California primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rogerson Aircraft Corp. v. Fairchild Industries, Inc., 632 F. Supp. 1494, 1 U.C.C. Rep. Serv. 2d (West) 1512, 1986 U.S. Dist. LEXIS 26568 (C.D. Cal. 1986).

Opinion

MEMORANDUM OP DECISION AND ORDER OF JUDGMENT FOR PLAINTIFF

HAUK, Senior District Judge.

1. PRELIMINARY STATEMENT

This matter is an action for damages brought by Rogerson Aircraft Corporation (Rogerson), a California corporation with its principal place of business in Irvine, California, against Fairchild Industries, Inc. (Fairchild), a Maryland corporation with its principal place of business in Germantown, Maryland, charging that a putative termination for default of an aircraft parts manufacturing contract for engine de-icing equipment between Rogerson as supplier and Fairchild as buyer was improper and therefore constituted a breach of contract. Federal jurisdiction is founded on diversity of citizenship, 28 U.S.C. § 1332 (1985).

On or about January 25, 1980, Fairchild and Saab-Scania AB (Saab), a Swedish manufacturing company, entered into a joint venture agreement to develop, manufacture and market a passenger aircraft known as the SF-340. 1 As part of its joint venture undertaking, Fairchild entered into an agreement with Rogerson on August 7, 1981 (August 7 Agreement) under which Rogerson was to supply certain SF-340 equipment unrelated to this action.

In November, 1981, pursuant to a Fair-child Request for Proposals for the manufacture of the component parts central to the present litigation, an engine de-icing duct and controller system for the SF-340, 2 *1497 Rogerson submitted a proposal for the manufacture of a Kevlar duct, a substance on the cutting edge of aircraft manufacturing technology. Fairchild accepted Roger-son’s proposal, and on January 14, 1982 issued a purchase order authorizing Roger-son to begin production on three test units, four prototype units, and 24 units of production equipment. The unit prices for the production equipment were set at $9,960 per duct and $300 per controller. On November 12, 1982, Rogerson and Fairchild executed an amendment to the August 7, 1981 Agreement providing that the production of the duct and controller system would be under the terms of the Agreement.

Although the production of the duct and controller system was plagued with technical and design problems from the start, Fairchild nevertheless issued a second purchase order on January 28,1983 instructing Rogerson to manufacture 34 additional shipsets of ducts and controllers for delivery in October, 1983. However, due to Rogerson’s continuing difficulty in producing a workable system from the specifications and models supplied by Fairchild, and problems with the controller’s performance in a February 1983 icing tunnel test, Fair-child issued an order on May 26, 1983 instructing Rogerson to stop all work under the original purchase orders. In early June, 1983, Fairchild issued Rogerson a new purchase order calling for the fabrication of a second test article for a second icing tunnel test, to be delivered to Fair-child on August 15, 1983.

Subsequent to the February 1983 icing tunnel test, Fairchild began exploring alternative designs and alternative producers for the duct and controller system. However, contrary to aircraft industry custom, Fairchild did not inform Rogerson that it was looking for an alternative supplier for the ducts and controllers. From April, 1983 to June, 1983, again without advising Rogerson, Fairchild solicited alternative design proposals from several aircraft industry contractors including Lucas Aerospace, an English manufacturer.

On July 7, 1983, the Fairchild executive committee responsible for overseeing the contracts of Fairchild’s suppliers held a special meeting to discuss the SF-340 duct and controller program. At this meeting, the committee decided to award Lucas Aerospace a de-icing duct and controller development contract with production options on terms more favorable to Fairchild than its contract with Rogerson. The committee also decided to terminate the Roger-son duct and controller contract for default, even though the test article under the June, 1983 purchase order was not due to be delivered until August 15, 1983 and the contract was therefore not in default. Subsequent to the July 7 meeting, Fairchild did not immediately inform Rogerson of its intent to terminate the Rogerson contract or its awarding of a contract to Lucas. Fairchild also did not advise Rogerson to stop work on the test articles under the June, 1983 purchase order.

Rogerson first learned that Fairchild was terminating the SF-340 duct and controller contract for default, with no liability to Fairchild, at a meeting between Fairchild and Rogerson personnel on July 21, 1983. At this meeting, Michael Rogerson, the president of Rogerson, was bluntly told that the contract was being terminated for default, and the Fairchild principals who delivered the information then intentionally left the room without further discussion. On July 22, 1983, Fairchild gave Rogerson formal written notice of the termination for default.

Rogerson instituted the present action for breach of contract on September 23, 1983. Fairchild initially responded by denying its termination for default was improper and asserting a counterclaim for breach of contract against Rogerson. However, on December 27,1984, more than *1498 one year after this action was filed, Fair-child withdrew its counterclaim and filed an amended answer asserting that the correct basis for its termination of the duct and controller contract was a termination for convenience provision contained in the August 7 Agreement. Fairchild has thus implicitly admitted that its termination of the duct and controller contract for default was improper.

Now, after a waiver of jury trial by the parties and a full court trial, lasting 11 days, on the issues of liability and damages, and after full consideration of the law and evidence and the arguments presented by both parties, the Court hereby renders its decision and order for judgment, which shall constitute findings of fact and conclusions of law as required by Rule 52(a), Federal Rules of Civil Procedure.

II. DISCUSSION

A. FAIRCHILD’S LIABILITY FOR BREACH OF CONTRACT

The threshhold issue to be decided in this action is whether Fairchild’s improper termination of the duct and controller contract “for default” constituted a breach of contract which entitles Rogerson to damages under New York law, 3 or whether Fair-child’s contractual right to terminate the contract at will pursuant to the termination “for convenience” provision of the August 7 Agreement limits Rogerson’s recovery to those actual amounts specified in the “termination for convenience” provision.'

Article 9 of the August 7 Agreement governs termination of the duct and controller contract. Article 9.4, the termination for default provision, provides:

If SELLER fails to delivery [sic] any EQUIPMENT in accordance with the agreed upon delivery schedule ...

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ivey v. Transunion Rental Screening Solutions, Inc.
2021 IL App (1st) 200894 (Appellate Court of Illinois, 2021)
Galloping, Inc. v. QVC, Inc.
27 F. Supp. 2d 466 (S.D. New York, 1998)
The Corner v. Pinnacle, Inc.
907 P.2d 1281 (Wyoming Supreme Court, 1995)
Golden State Transit Corp. v. City of Los Angeles
773 F. Supp. 204 (C.D. California, 1991)
Ford Motor Co. v. Kuan Tong Indus. Co., Ltd.
697 F. Supp. 1108 (N.D. California, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
632 F. Supp. 1494, 1 U.C.C. Rep. Serv. 2d (West) 1512, 1986 U.S. Dist. LEXIS 26568, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rogerson-aircraft-corp-v-fairchild-industries-inc-cacd-1986.