S. Leo Harmonay, Inc. v. Binks Manufacturing Co.

597 F. Supp. 1014, 1984 U.S. Dist. LEXIS 22438
CourtDistrict Court, S.D. New York
DecidedOctober 26, 1984
Docket82 Civ. 6868 (IBC)
StatusPublished
Cited by45 cases

This text of 597 F. Supp. 1014 (S. Leo Harmonay, Inc. v. Binks Manufacturing Co.) is published on Counsel Stack Legal Research, covering District Court, S.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
S. Leo Harmonay, Inc. v. Binks Manufacturing Co., 597 F. Supp. 1014, 1984 U.S. Dist. LEXIS 22438 (S.D.N.Y. 1984).

Opinion

OPINION

IRVING BEN COOPER, District Judge.

This is an action by S. Leo Harmonay, d/b/a Harmonay Company (Harmonay), a New York corporation, against Binks Manufacturing Company (Binks), a Delaware corporation with its principal place of business in Illinois, for breach of a construction contract. * , 1 Plaintiff was the mechanical piping subcontractor to defendant, one of a number of general contractors on the expansion of a General Motors (GM) automobile assembly plant in Tarry town, New York. Defendant’s project involved the construction of two additions to the plant, known as the Body Phosphate Facility and the Body Elpo Dip System; it subcontracted out thé mechanical piping work to plaintiff at a cost of approximately two million dollars.

Plaintiff claims that defendant breached the contract by causing certain project delays which resulted in an increased cost of materials, labor inefficiencies and excess supervision during an acceleration period; that it is entitled to a markup for overhead and profit for overtime work performed; and that it should be compensated for its field office costs incurred after the original job completion date.

Jurisdiction is vested in this court under 28 U.S.C. § 1332. The amount in controversy exceeds $10,000 exclusive of interest and costs.

Facts

In late 1980, defendant contracted with GM to construct the Body Elpo Dip System and Body Phosphate Facility, a new painting system for the GM automobile plant. The GM project site on which the construction was to occur consisted of two buildings, body and chassis plants, parallel to each other. The extension of the south end of the body plant in order to construct the new facilities was referred to as the “Elpo Building addition.” (Tr. 8) 2

At trial, Edward Klapp, the vice-president of Harmonay, first described the workings of a phosphate machine as follows: “[The new partially assembled car] comes on an overhead conveyor, [and] goes through eight stages of washing and cleaning ... inside of a totally enclosed housing where there are spray headers [and] drain pans to keep the water circulating over the [automobile] body.” (Tr. 15) After the car proceeds through the phosphate system, it is a “nice shiny piece of metal ... and clean.”

The Body Elpo Dip System then paints the cleaned automobile body. As explained by Klapp: “[After the car drip dries on the third floor] [i]t is ... returned by means of conveyor back down to the second floor, at *1019 which point it is put through the Elpo system. It starts by having the body totally immersed into paint substance which is basically a primer ... [i]t’s an electroly [sic] charged painting system.” (Tr. 15) Following the phosphate and Body Elpo treatments, the auto is conveyed back to the third floor of the body plant where it moves through a series of drying ovens prior to the application of other accessories onto the automobile.

The scope of defendant’s work on this project was set forth in the GM “Specifications for Body Phosphating Facilities— GMAD Elpo Building — S-358 and S-359”. (Ex. 10) Specification S-358 covered the phosphate facilities and S-359 encompassed the Body Elpo facilities. The GM specifications included instructions to bidders, proposal forms, a time schedule, a scope of work section, technical specifications, and “GM Contract General Conditions”. , The general conditions set forth, inter alia, basic provisions concerning time extensions, extra work, change orders, and overtime work. 3

Harmonay’s first contact with Binks was a phone call in October, 1980, from Fred Steinhebel, a representative of Binks, who told Klapp that Binks was bidding on a painting system for new cars, and requested a bid from Harmonay on the mechanical piping work. (Tr. 13) As was customary bidding procedure among contractors, plaintiff used the GM technical specifications, including bid drawings or schemactics, in order to prepare its bid for defendant. Klapp, whose duties were to oversee the daily office and field operations, testified that this bid was compiled by pricing materials required by types and sizes, adding labor values based on plaintiff’s “experience over the years working at General Motors” and finally adding overhead and profit to arrive at the bid price package. (Tr. 17)

Plaintiff was awarded the contract, and by signed purchase order dated December 9, 1980 4 agreed to perform the general mechanical piping work for a total compensation of approximately two million dollars. (Tr. 8) The October 31, 1980 quotation confirmed plaintiff’s verbal quotation to defendant to perform work “in accordance with specifications titled ‘Specifications for Body Phosphating Facilities’ and ‘Body Elpo Dip System’ ” (i.e., “GM Specifications”) and certain enumerated drawings. A second written purchase order, dated January 7, 1981 (Ex. 9) modified the original subcontract only to the extent of eliminating and adding various items of work for the prices therein enumerated.

It is well known in the construction business that the schemactics set forth in the owner’s specifications are approximations used to enable potential subcontractors to make bids; that they often lack, for instance, exact distances. (Tr. 18-23) Accordingly, a subcontractor who is awarded a contract receives from the contractor precise drawings (contract layout drawings) before the construction work begins so that he may order the proper types and amounts of materials. (Tr. 31) To that end, Klapp, prior to bidding, discussed with Steinhebel the defendant’s responsibility to provide contract layout drawings so that Harmonay could “make take-offs and order materials that would be needed to start the installation of the project.” The. drawings were to be prepared by another Binks subcontractor, Industrial Finish Engineering, Inc. (IFE), whose principal was Edwin Schacterle, and were to include, inter alia, plan views, elevations, equipment locations, tie-ins between the equipment and piping, and all pipe sizes. In addition, defendant retained IFE and Schacterle to render engineering services for the project as set forth by a purchase order dated December 9, 1980.

*1020 Pursuant to the GM Specification “Time Schedule,” bids were due on October 27, 1980; the bid award target date was November 3, 1980; and “Major Drawings Submittal (Layouts, Sections, Schemactics and Equipment Data) Complete” were to be submitted from “12/15/80 to 1/15/81.” Klapp testified that Steinhebel referred to the “importance [of] hav[ing] the drawings as quickly as possible, hopefully by the first of January, so that [Harmonay] could make our take-offs [drawings] and order the material that would be needed to start the installation of this project.” (Tr. 30-31) The GM Specifications further provided that the project site was to be available to defendant and its subcontractors to begin their work by February 1, 1981. The original date for substantial completion of the project was between August 15 and September 20, 1981.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

TGG Ultimate Holdings, Inc. v. Hollett
224 F. Supp. 3d 275 (S.D. New York, 2016)
Iron Mountain Information Management, Inc. v. Taddeo
455 F. Supp. 2d 124 (E.D. New York, 2006)
Estee Lauder Companies Inc. v. Batra
430 F. Supp. 2d 158 (S.D. New York, 2006)
CooperVision, Inc. v. Inter Integration Technologies, Inc.
7 Misc. 3d 592 (New York Supreme Court, 2005)
A.F. Lusi Construction, Inc. v. Peerless Insurance
847 A.2d 254 (Supreme Court of Rhode Island, 2004)
Bussanich v. 310 East 55th Street Tenants
282 A.D.2d 243 (Appellate Division of the Supreme Court of New York, 2001)
Gold v. Ziff Communications Co.
748 N.E.2d 198 (Appellate Court of Illinois, 2001)
Dunes Hospitality, L.L.C. v. Country Kitchen International, Inc.
2001 SD 36 (South Dakota Supreme Court, 2001)
Kellen Co., Inc. v. Calphalon Corp.
54 F. Supp. 2d 218 (S.D. New York, 1999)
Galloping, Inc. v. QVC, Inc.
27 F. Supp. 2d 466 (S.D. New York, 1998)
Carnrite v. Granada Hospital Group, Inc.
175 F.R.D. 439 (W.D. New York, 1997)
In re G. Marine Diesel Corp.
194 B.R. 306 (E.D. New York, 1996)
City of Amsterdam v. Daniel Goldreyer, Ltd.
882 F. Supp. 1273 (E.D. New York, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
597 F. Supp. 1014, 1984 U.S. Dist. LEXIS 22438, Counsel Stack Legal Research, https://law.counselstack.com/opinion/s-leo-harmonay-inc-v-binks-manufacturing-co-nysd-1984.