Guy James Construction Company, Cross-Appellant v. Trinity Industries, Inc., Cross-Appellee

644 F.2d 525, 31 U.C.C. Rep. Serv. (West) 1627, 1981 U.S. App. LEXIS 13482
CourtCourt of Appeals for the Fifth Circuit
DecidedMay 8, 1981
Docket80-1322
StatusPublished
Cited by32 cases

This text of 644 F.2d 525 (Guy James Construction Company, Cross-Appellant v. Trinity Industries, Inc., Cross-Appellee) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Guy James Construction Company, Cross-Appellant v. Trinity Industries, Inc., Cross-Appellee, 644 F.2d 525, 31 U.C.C. Rep. Serv. (West) 1627, 1981 U.S. App. LEXIS 13482 (5th Cir. 1981).

Opinion

SPEARS, District Judge:

Guy James Construction Company (James) recovered a $252,016.08 judgment for damages sustained when Trinity Industries, Inc. (Trinity) breached a construction contract providing for the timely delivery of trapezoidal steel girders, to be utilized by James in a construction project at Dallas-Fort Worth Regional Airport (DFW). Both parties appealed the amount of damages awarded by the district court. Except for certain items of recovery, which are reversed, we affirm the judgment of the district court.

In 1971, DFW and James entered into a contract for the construction of four taxiway bridges over the public access road bisecting the airport. The contract provided that a designated engineer would represent DFW in all aspects of the bridge construction, and would, accordingly, supervise the construction activities. In addition, James was required to employ an independent testing laboratory to inspect the component construction materials for compliance with manufacturing plans and specifications.

Trinity submitted to James alternative offers for fabrication of the steel girders required for the bridges. These proposals were identical except for a time/price differential; one offer provided for a six week earlier delivery date at a one-half cent per pound higher price, which, based upon the quantity of steel ultimately delivered, amounted to a difference of $17,129.65. Although James accepted neither proposal, it subsequently issued a purchase order incorporating the earlier delivery date and the higher price provisions quoted in one of the original offers. Delivery under this contract was to commence not later than January, 1972, and was to be completed by June, 1972.

During January, 1972, Trinity began delivering the steel girders contracted for. Inspection of the girders, however, revealed that they were not manufactured in accordance with plans and specifications. By order of DFW’s engineer representative, the girders were rejected and returned to Trinity. Thereafter, delivery of acceptable steel girders, fabricated by a subcontractor, commenced in December, 1972.

Trinity’s failure to timely produce the girders in accordance with the contract prevented James from timely completing performance under its construction contract with DFW, and, pursuant to a provision of the DFW contract providing for absolute liquidated damages of $1,500.00 per day, DFW withheld, because of the delay, $453,-000.00 from its payment to James upon completion of the project. James instituted this suit against DFW, Trinity, and various subcontractors and consultant engineers to recover the additional costs occasioned by the delay. The original complaint stated in pertinent part:

As a result of the rejection of the trapezoidal girders by the AIRPORT BOARD’S engineer, JAMES sustained additional and extra costs in the performance of its contract with the AIRPORT BOARD... Plaintiff JAMES, is entitled to recover the above amounts from the Defendant, AIRPORT BOARD; or, in the alternative, is entitled to recover as indemnity, from TRINITY ..., or from *529 both Defendants, jointly and severally, the full amount of JAMES’ said extra cost....

An amended complaint further alleged that:

D/FW has unreasonably and improperly deducted from contract payments due to plaintiff the sum of $453,000.00 assessed as alleged liquidated damages for delayed completion of contract work on the Taxiway Bridges, despite the fact that the delays in completion were the direct and proximate result of errors and omissions on the part of D/FW . . .

This complaint, like the original pleading, requested an alternative judgment against Trinity. Thereafter, all of the defendants, except Trinity, settled with James for a total sum of $424,000.00.

On July 10, 1976, James filed a second amended complaint against Trinity, wherein James held Trinity accountable for the $453,000.00 in liquidated damages retained by DFW. In addition, James sought to recover administrative expenses, and home and site office overhead expenses associated with the additional eleven month construction period. The complaint also charged Trinity with excess welding costs incurred for incorporating the rejected girders into another facet of the construction project.

The district court granted James a partial summary judgment against Trinity for breach of contract. In a subsequent bench trial on the issue of damages, James was permitted to recover from Trinity the reasonable expenditures made in good faith by James as a consequence of Trinity’s breach. The following recoverable expenditures were awarded:

Liquidated damages $102,162.43

Home office overhead 34,450.00

Field office overhead 11,500.00

Early delivery premium 17,192.65

Prejudgment interest 1 86,711.00

This appeal from the bench trial followed.

I. Election of Remedies

Initially, we must determine whether this suit was barred, as a matter of law, by the Texas “election of remedies” doctrine. The doctrine of election may preclude the recovery of damages based upon inconsistent theories arising from the same state of facts. See Bocanegra v. Aetna Life Ins. Co., 605 S.W.2d 848, 850 (Tex. 1980). “[A]n election will bar recovery when the inconsistency in the assertion of a remedy, right, or state of facts is so unconscionable, dishonest, contrary to fair dealing, or so stultifies the legal process or trifles with justice or the courts as to be manifestly unjust.” Id. at 851. As this Circuit has recognized,

[A] claimant should not be permitted to assert formally the existence of one state of facts in a claim against one party and accept complete or partial satisfaction of that claim, and then maintain an action against another party on the ground that the facts first asserted did not exist.

Lubbock Feed Lots, Inc. v. Iowa Beef Processors, 630 F.2d 250, 274 (5th Cir. 1980), quoting Ward v. Shriro Corp., 561 S.W.2d 589, 591-92 (Tex.Civ.App.—Dallas), rev’d on other grounds, 570 S.W.2d 395 (Tex. 1978). Trinity argues that James’ claims, herein, were asserted against former parties to the lawsuit from whom James obtained a substantial sum in settlement, and, therefore, *530 James may not maintain this action against Trinity.

Trinity’s reliance on the doctrine of election is inappropriate. Election of remedies is an affirmative defense that must be pleaded. Lubbock Feed Lots, Inc. v. Iowa Beef Processors, supra, 630 F.2d at 274 n.34; Bradley v. Straus-Frank Co., 414 S.W.2d 504, 510 (Tex.Civ.App.—Dallas 1967, ref’d n.r.e.).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Huffman v. Union Pacific Railroad
675 F.3d 412 (Fifth Circuit, 2012)
Veneklase v. Bridgewater Condos, L.C.
670 F.3d 705 (Sixth Circuit, 2012)
Fournigault v. Independence One Mortgage Corp.
242 F.R.D. 486 (N.D. Illinois, 2007)
In Re Bayou Group, LLC
362 B.R. 624 (S.D. New York, 2007)
Bedard v. Martin
100 P.3d 584 (Colorado Court of Appeals, 2004)
Chilton Insurance Co. v. Pate & Pate Enterprises, Inc.
930 S.W.2d 877 (Court of Appeals of Texas, 1996)
Lowell Paper Box Co. v. Omni Resources Corp.
2 Mass. L. Rptr. 649 (Massachusetts Superior Court, 1994)
Ex Parte Chrysler First Financial Serv.
608 So. 2d 734 (Supreme Court of Alabama, 1992)
William Jones v. Roadway Express, Inc.
936 F.2d 789 (Fifth Circuit, 1991)
Butcher v. Cessna Aircraft Co.
668 F. Supp. 569 (S.D. Mississippi, 1987)
Murr v. Odmark
733 P.2d 827 (Idaho Court of Appeals, 1987)
Allstate Insurance v. James
779 F.2d 1536 (Eleventh Circuit, 1986)
Aetna Cas. & Sur. Co. v. Doleac Elec. Co.
471 So. 2d 325 (Mississippi Supreme Court, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
644 F.2d 525, 31 U.C.C. Rep. Serv. (West) 1627, 1981 U.S. App. LEXIS 13482, Counsel Stack Legal Research, https://law.counselstack.com/opinion/guy-james-construction-company-cross-appellant-v-trinity-industries-ca5-1981.