Kansas City Bridge Co. v. Kansas City Structural Steel Co.

317 S.W.2d 370, 85 A.L.R. 2d 1252, 1958 Mo. LEXIS 591
CourtSupreme Court of Missouri
DecidedNovember 10, 1958
Docket46887
StatusPublished
Cited by27 cases

This text of 317 S.W.2d 370 (Kansas City Bridge Co. v. Kansas City Structural Steel Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kansas City Bridge Co. v. Kansas City Structural Steel Co., 317 S.W.2d 370, 85 A.L.R. 2d 1252, 1958 Mo. LEXIS 591 (Mo. 1958).

Opinion

COIL, Commissioner.

Plaintiff below received a judgment for $139,438.85, which it claimed as damages resulting from defendant’s alleged breach of a contract which plaintiff had averred was partly written and partly oral, and by the terms of which defendant was to fabricate and furnish to plaintiff the steel required for the erection of the river spans— superstructure for the bridge spanning the Missouri River at Leavenworth, Kansas.

Defendant’s first contention is that there was a contract in writing which was silent as to time of performance, and thus that the trial court erred in admitting evidence of a prior oral agreement between plaintiff and defendant as to a specific time for delivery of the steel (in so far as the purpose of the evidence was to prove the oral part of the contract alleged) for the reason that the oral agreement contradicted the terms of the written contract. Plaintiff’s case was submitted on the sole theory that the contract was partly written and partly oral, including the oral agreement that defendant would begin to deliver the steel in time for plaintiff to commence erection of the bridge’s river spans during July 1954 and would continue deliveries thereafter so that construction could proceed uninterruptedly to completion.

The City of Leavenworth advertised for bids on the bridge in accordance with detailed plans and specifications prepared by its consulting engineers. Plaintiff’s evidence tended to show that after deciding to bid, but before bidding, on what was known as contract No. 2 (i. e., construction of the river spans as distinguished from contracts for each the east and west bridge approaches) in accordance with usual practice it discussed matters relating to steel fabrication and prices with defendant. After preliminary conversations, defendant, in November 1953, quoted approximate prices for the estimated quantities of steel required and at that time plaintiff pointed out to defendant that whoever received the bid would have to substantially complete it in the relatively short time stated in the proposed contract in order to avoid penalties therein also provided; and that, consequently, if plaintiff were the successful bidder, it would need the necessary steel in time to begin construction in the early part of July 1954 so that the steel would be erected in time to comply with the contract and also to avoid the increased costs which would result from pouring the concrete bridge roadway during cold weather rather than during early fall. Defendant’s proper officer assured plaintiff that he could foresee no problem of difficulty in meeting such a proposed delivery date. Again, early in December, defendant’s contracting engineer confirmed the prices that plaintiff was to. use in its bid, and again the necessity of delivery in time to begin steel erection in early July was discussed, and defendant again assured plaintiff that he could foresee no. problem in meeting such a delivery requirement.

Based upon the approximate prices quoted' and upon defendant’s statements which plaintiff construed to mean that defendant agreed to begin delivery of the necessary steel in time for construction to start in early July and to continue deliveries so-that construction could proceed without interruption thereafter, plaintiff submitted a bid on December 15 and was awarded contract No. 2 on December 21, 1953. Under the terms of plaintiff’s contract with. Leavenworth, the bridge was to be substantially completed (i. e., open to traffic), on or before December 26, 1954.

Later in December 1953 or in early January 1954, the consulting engineers indicated a desire for a bid on substituted steel. Defendant’s bid (through plaintiff) on such was accepted with the assurance to plaintiff *372 that the substituted steel could be furnished without change in the delivery picture. After defendant had begun its preliminary work preparatory to fabricating and furnishing the steel, it sent to plaintiff the following writing on defendant’s stationery, headed “Proposal”:

“Confirming our prices given you for your structural steel requirements for bridge over Missouri river at Leavenworth, Kansas, consisting of 2-420' Continuous Arch Spans, known as Contract No. 2, we are pleased to quote as follows:

Item #1 — Approx. 1,710,000 # Carbon Steel — $15.22 per 100 lbs.

Item #5A — Approx. 1,645,000 # Low Alloy Steel — $16.72 per 100 lbs.

“The above prices are f. o. b. cars Leavenworth, Kansas, and cover fabrication as per plans and specifications by Howard, Needles, Tammen & Bergendoff, Consulting Engineers.

“The above prices do not include sandblasting or shop coat of paint.

“This confirmation is rendered to you in duplicate, your signature of acceptance on one copy and the return of the same to us will constitute a contract between us.”

Plaintiff’s vice-president received the writing and, after finding that the proposed prices were in accord with those priorly discussed, directed the purchasing agent to accept on behalf of plaintiff and to attach a purchase order for the quantities of steel stated in the proposal at the prices there stated. The purchasing agent did as directed and, on January 12, returned to defendant the signed contract and plaintiff’s purchase order.

Defendant contended at the trial and here contends that the portions of the evidence heretofore related, tending to show that there was an oral agreement as to a specific time for steel delivery, was not admissible as part of the contract between the parties for the reason that, inasmuch as the written contract of January 11, 1954, above set forth, made no reference to time of performance, the law implied that it was to be performed in a reasonable time; and thus to show an oral agreement for a specific time contradicted the terms of the written contract.

Defendant conceded at the trial that the evidence heretofore mentioned was admissible as bearing upon the jury question of what was a reasonable time. The parties entered into a stipulation with reference to that matter and are here in dispute as to its effect. In the view we take of this case, however, it will be unnecessary to determine the effect of that stipulation. For our present purposes, it suffices to say that unless the evidence of a prior oral agreement as to time of performance was properly admitted as tending to prove the proposition that as part of the pleaded contract defendant agreed to deliver the steel in time to permit plaintiff to commence erection of the bridge by a specific date and to permit uninterrupted construction thereafter, plaintiff did not prove the contract which it alleged in its petition and submitted to the jury as the basis for its recovery, and, in that event, the result would be a reversal and remand of the case for a trial on the theory of whether the written contract was performed by defendant in a reasonable time.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

General Electric Capital Corp. v. Rauch
970 S.W.2d 348 (Missouri Court of Appeals, 1998)
Lowell Paper Box Co. v. Omni Resources Corp.
2 Mass. L. Rptr. 649 (Massachusetts Superior Court, 1994)
Jake C. Byers, Inc. v. J.B.C. Investments
834 S.W.2d 806 (Missouri Court of Appeals, 1992)
Cives Corp. v. Callier Steel Pipe & Tube, Inc.
482 A.2d 852 (Supreme Judicial Court of Maine, 1984)
Liberty Financial Management Corp. v. Beneficial Data Processing Corp.
670 S.W.2d 40 (Missouri Court of Appeals, 1984)
Wells v. Holiday Inns, Inc.
522 F. Supp. 1023 (W.D. Missouri, 1981)
Weltscheff v. Medical Center of Independence, Inc.
597 S.W.2d 871 (Missouri Court of Appeals, 1980)
W. G. Cornell Co. v. Ceramic Coating Co.
626 F.2d 990 (D.C. Circuit, 1980)
Gustav Thieszen Irrigation Co., Inc. v. Meinberg
276 N.W.2d 664 (Nebraska Supreme Court, 1979)
Southern New England Contracting Co. v. State
345 A.2d 550 (Supreme Court of Connecticut, 1974)
Natkin & Company v. George A. Fuller Company
347 F. Supp. 17 (W.D. Missouri, 1972)
Beuc v. Morrissey
463 S.W.2d 851 (Supreme Court of Missouri, 1971)
A. A. Baxter Corp. v. Colt Industries, Inc.
10 Cal. App. 3d 144 (California Court of Appeal, 1970)

Cite This Page — Counsel Stack

Bluebook (online)
317 S.W.2d 370, 85 A.L.R. 2d 1252, 1958 Mo. LEXIS 591, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kansas-city-bridge-co-v-kansas-city-structural-steel-co-mo-1958.