Cives Corp. v. Callier Steel Pipe & Tube, Inc.

482 A.2d 852, 39 U.C.C. Rep. Serv. (West) 1705, 1984 Me. LEXIS 804
CourtSupreme Judicial Court of Maine
DecidedOctober 15, 1984
StatusPublished
Cited by8 cases

This text of 482 A.2d 852 (Cives Corp. v. Callier Steel Pipe & Tube, Inc.) is published on Counsel Stack Legal Research, covering Supreme Judicial Court of Maine primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cives Corp. v. Callier Steel Pipe & Tube, Inc., 482 A.2d 852, 39 U.C.C. Rep. Serv. (West) 1705, 1984 Me. LEXIS 804 (Me. 1984).

Opinion

*854 DUFRESNE, Active Retired Justice.

A jury-waived trial in Superior Court (Kennebec County) resulted in the entry of judgment in the amount of $15,679.91 in favor of the plaintiff, Cives Corporation (“Cives”) in its breach of contract suit against Callier Steel Pipe & Tube, Inc. (“Callier”), and of judgment in the amount of $1,168.23 in favor of the defendant, Cal-lier, on its counterclaim. Cives appeals the court’s denial of damages for certain overhead expenses and Callier cross-appeals the breach of contract award. We affirm the Superior Court on all issues under appeal.

In late 1977 Georgia-Pacific Corporation was seeking bids for the construction of a tissue products plant in Plattsburg, New York. As a result of its low bid, Cives was given the contract to provide the structural steel for part of the roof of this plant. This contract called for payment of slightly less than $400,000 out of a total cost of $35 million for the entire project. Cives was to deliver the steel by January 23, 1978 at the site, and the contract expressly provided that time was of the essence. Because Cives is not usually a manufacturer of steel tubes (it usually deals with steel plates), Cives’ production manager, Stephen Astoria, Jr., discussed the purchase of the needed tubes with one Joseph Shaeffer, a salesman at Callier’s. Following their verbal agreement of purchase and sale over the phone, Astoria, according to trade practices, sent a written purchase order to Cal-lier Steel Pipe & Tube, Inc., of St. Louis, Missouri, purportedly incorporating the oral contract. This purchase order, dated December 7, 1977, called for the delivery at the Cives plant in Augusta, Maine, of steel tubing of specific shape, length and weight with unit prices, “All materials to conform to A501-Hot Formed or A500 Grade B-Cold Formed” and “All welds are to be 100% penetration.” At the top right corner of the purchase order appeared the legend “REQD BY (meaning required by) [followed by the time] 1/3/78.” In bold print on the face of the order, it was provided

THIS ORDER IS SUBJECT TO ALL TERMS AND CONDITIONS SHOWN ON THE FACE AND REVERSE SIDE HEREOF

Among the conditions articulated in smaller print on the reverse side of the order, there were provisions calling for time being of the essence of the contract and limiting assignments thereof. 1 Again, on the face of the order form in the left bottom corner, space was provided for acceptance by the supplier with the word “ACCEPTED” in bold print positioned to the left of where the intended signature or authentication was contemplated. Although this purchase order stated at the very bottom on its face to

execute and return duplicate copy to Cives Steel Company New England Division^]

no such execution by signing or authenticating, nor any return thereof was ever made. Callier, however, never objected to any of the terms of the purchase order, except after litigation when it claimed that all delivery dates under industry custom are approximate only. The total price of this subcontract as modified by two change orders respectively dated December 9 and 12, 1977, was $28,546.00.

It was on the 12th of December that Astoria of Cives, in conversation with *855 Shaeffer of Callier, discovered that the company did not have the tubes in its inventory and could not obtain them from the mill. This, Astoria was informed, would necessitate the fabrication of the tubes. This in turn would require a change in the process of manufacture and bring about an increase in the price. The stated second change order confirmed Cives’ agreement to these particular adjustments. In that same conversation, it was learned that the fabrication of the steel tubes had been subcontracted to another company, the identity of which the Callier personnel was reluctant to disclose. It was late December when Cives’ project manager, Kurt Huber, after persistent prodding, finally learned that Lanan Products of Chicago (“Lanan”) would be fabricating the tubes for Callier. Donald Hardy, Cives’ president and general manager of its New England Division, Augusta, at that point became apprehensive concerning Callier’s ability to meet the January 3rd delivery deadline under the contract. Eric Johanson, Cives’ sales manager, was then directed to check on the progress of the company’s order. On his visit at Lanan’s plant in Chicago in company of Callier’s Niewoehner on January 3, 1978 (the date called for delivery of the tubes in the purchase order), Johanson found out that Lanan not only had not commenced work on the fabrication of these tubes, but had not received the raw material with which to make the tubes. In addition, it was discovered that Lanan had not been informed about important specifications of the Cives-Callier purchase order such as the 100% weld penetration and backing bar reinforcement requirements. Although Lanan then agreed to comply with these conditions and promised delivery of the tubes in two shipments, respectively on January 13 and January 18, 1978, Cives’ managerial team in Maine, after considering Johanson’s negative report of his January 3rd visit to the Lanan plant, was skeptical about relying on these proffered delivery dates. At a meeting on the very next day, January 4, 1978, they considered their own delivery date under the Georgia-Pacific contract, January 23, 1978, to be in jeopardy and decided to cancel the Callier contract. Callier was notified the same day. Factors which entered into the decision to cancel the Callier contract appear as follows: 1) Cives’ steel tube contract with Georgia-Pacific involved minor monetary gains compared to the great amount of damages to which the company would be exposed if the multimillion dollar project was delayed in construction by reason of Cives’ failure to meet its delivery date; 2) Callier’s failure to meet the January 3rd delivery deadline, its disregard of the contract terms requiring company consent on subcontracting the fabrication of the tubes, its non-disclosure of essential contract specifications to the subcontracting firm, its evident reluctance to disclose the identity of the manufacturing outfit, all served to cast doubt on punctual performance and to support Cives’ claim of loss of faith in any of the seller’s promises for the future.

Unable to find any other steel manufacturer to fabricate the steel tubing to meet the Georgia-Pacific schedule, Cives decided to make the tubes in-house, with the assistance of its New York division. Cives’ purchase order to its New York division went out on January 9, 1978 and called for deliveries on the 16th and 23rd of January; this latter date was the stated time for performance under the Georgia-Pacific contract. Up until that time, Cives did not expect that its deadline delivery date would be moved to February 13, 1978, notice of which it received on January 11, 1978. Cives fully performed its contract with Georgia-Pacific which accepted tube deliveries from mid January through the end of March. Georgia-Pacific brought no action against Cives for breach.

Cives brought action in Superior Court against Callier for breach of contract. It sought damages equal to the cost of cover, plus incidental and consequential damages, minus the contract price at which Cives could have gotten the tubing from Callier, if Callier had fulfilled its obligations under the agreement.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

M&T Bank v. Lawrence F. Plaisted
2018 ME 121 (Supreme Judicial Court of Maine, 2018)
M & T Bank v. Plaisted
192 A.3d 601 (Supreme Judicial Court of Maine, 2018)
Bridgeport Harbour Place I, LLC v. Ganim
30 A.3d 703 (Connecticut Appellate Court, 2011)
State v. Hernandez
1998 ME 73 (Supreme Judicial Court of Maine, 1998)
Doner v. Snapp
649 N.E.2d 42 (Ohio Court of Appeals, 1994)
Lowell Paper Box Co. v. Omni Resources Corp.
2 Mass. L. Rptr. 649 (Massachusetts Superior Court, 1994)
Continental Can Co. v. Poultry Processing, Inc.
649 F. Supp. 570 (D. Maine, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
482 A.2d 852, 39 U.C.C. Rep. Serv. (West) 1705, 1984 Me. LEXIS 804, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cives-corp-v-callier-steel-pipe-tube-inc-me-1984.