Baker v. J. W. McMurry Contracting Co.

223 S.W. 45, 282 Mo. 685, 1920 Mo. LEXIS 146
CourtSupreme Court of Missouri
DecidedJune 4, 1920
StatusPublished
Cited by17 cases

This text of 223 S.W. 45 (Baker v. J. W. McMurry Contracting Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Baker v. J. W. McMurry Contracting Co., 223 S.W. 45, 282 Mo. 685, 1920 Mo. LEXIS 146 (Mo. 1920).

Opinion

*692 WALKER, C. J.

This is a suit on a contract for construction work on, a railroad instituted in the Circuit Court of Jackson County by Baker against the McMurry Contracting Company. Upon a trial at the May term, 1917, of said court a judgment was rendered in favor of the plaintiff. Under a writ of error the defendant seeks a review of this judgment.

The contract upon which this action is based was in the form of a letter addressed by the defendant to the plaintiff and accepted by the latter.' The subject-matter of this contract is as follows:

“Agreeable with our conversation this morning, we herewith make you the following proposition on work to be done on the N. O. T. & M. R. R. east of Houston, Texas. Repairing pier No. 2 at the San Jacinto River bridge, building piers and abutments at Barnes Creek, Cowpen Creek, Hickory Creek and Anchorage, La., at the following unit prices:

(Omitted as not in issue.)

“It is understood that you are to furnish all material and all labor necessary to complete this work, and that the railroad company will refund freight charges and railroad fares.paid on laborers on the N. 0. T. & M. R. R. It is understood that they will also pay for extra labor performed at San Jacinto River; such as removing old cofferdam, and preparing the pier and footing' courses for new concrete, at cost plus 10 per cent. It is further understood that we are to furnish two hoisting engines, two derricks, complete with wire rigging,- one concrete mixer, one centrifugal pump, one force pump, pile driver hammer, and one stationary 30-horse-power boiler free of charge to you, except that you are to pay the freight on this plant from Van Burén, Ark., to Quincy or Beaumont, which are the connections with the N. O. T. & M. R. R. All of the above described work to be done under the direction and according to the plans furnished by the chief engineer of the N. 0. T. & M. R. R. Co.”

*693 The material averments necessary to charge a liability on this contract are embodied in the petition, concerning the sufficiency of which there is no controversy. The material averments of the answer are as follows:

That the railroad company under which defendant was a general contractor, and plaintiff a sub-contractor under defendant, had become insolvent; that under the laws of Louisiana, where the work was being done, there could be no statutory lien for the. work done; that defendant had taken all possible steps to establish an equitable lien, but unsuccessfully; that the plaintiff had joined defendant-in these efforts; that a general custom existed and was in force in the railroad contracting business, in which both the parties were engaged, and of which both had notice and knowledge at the time of the making of any contracts, that if, by reason of insolvency or otherwise, the railroad company delayed or was unable, in whole or in part, to pay promptly for work and labor done and materials furnished by a sub-contractor, the claim of the sub-contractor would not be enforced against the original contractor and did not become due and payable unless and until the railroad company paid therefor, and that the sub-contractor must and does look to the railroad company for payment direct or through the original contractor; that the plaintiff, by his course of dealing, acts and conduct, waived payment of any amount coming to him until and unless same was collected from the railroad company, and that he is estopped from collecting any amount from defendant unless and until same is collected from said company; that the work in question was done under an original contract between the defendant in the case at bar and the railroad company, which provided that the work must be completed by December 3, 1912; that plaintiff had full notice and knowledge thereof and that the contract with him was entered into subject to such requirement; that the plaintiff delayed the work in violation of his contract *694 for a long time, to-wit, five months, and that all work so paid for mentioned in the petition was done after the date said work should have been completed, and that if plaintiff had promptly performed his contract payment therefor would have been made by the railroad company, as it was then operating the property and supplied the funds to pay therefor, and that plaintiff’s delay and breach prevented the payment for the work, resulting in great damage to the defendant.”

Plaintiff’s reply was a general denial.

The testimony for the plaintiff was that he had performed the work required by the contract and that there ■y^as due him therefor $11,125.54.

McMurry, defendant’s president, testified that he went over the work with plaintiff and that the. latter reported to him that it could be completed in about four months; that McMurry on behalf of the defendant company then entered into a contract to perform the work with the railroad company within the time stated by plaintiff, and sub-let the same to the plaintiff as per the contract heretofore set forth.

The defendant then offered to prove, and the court excluded the testimony, that the railroad company went into the hands of a receiver and that up to that time it paid its estimates for the work promptly. Defendant’s president further testified that there was a custom in railroad construction work that when it was done by a sub-contractor he was not paid therefor until his estimates were received by the railroad company and payment had been made by it to the general contractor; that if for any reason a railroad company delays or does not pay the general contractor on the subcontractor’s estimates the money for the work performed is not due the latter until the railroad company has paid the general contractor; that this custom existed at the time the work was done and was acquiesced in by the parties; that the plaintiff had performed subcontractor work for the president of the defendant company for many years prior thereto and that this method *695 of payment had prevailed during that time. Defendant further offered to show, and the testimony was excluded, that on each payment by the railroad company on the estimates of the sub-contractor the full amount, less the difference in the general and the sub-contractor’s price, was paid over to the plaintiff.

On cross-examination defendant’s president testified that the custom he had referred to applied where the railroad work was done under an agreement, and that this particular work was an isolated case, and that as the plaintiff was on the ground he assumed all the risk of the work.

Plaintiff in rebuttal' denied that there was any sucb custom as had been testified to by.the defendant’s president. As to the general course of dealing between these parties it was testified to by the plaintiff, as it had been by the defendant’s president, that the question as to the right to the sub-contractor’s payments being deferred until the railroad company had settled with, the general contractor had never come up between them; that for about seventeen years plaintiff had been contracting with the defendant and had been paid promptly at the time of the delivery of the monthly estimates with one exception, in which the payment had been made to him before the estimate came in. There was introduced in evidence a'

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Montrose Savings Bank v. Landers
675 S.W.2d 668 (Missouri Court of Appeals, 1984)
Beard v. Jackson
502 S.W.2d 416 (Missouri Court of Appeals, 1973)
Hjelle v. Sornsin Construction Company
173 N.W.2d 431 (North Dakota Supreme Court, 1969)
Playboy Club, Inc. v. Myers
431 S.W.2d 228 (Supreme Court of Missouri, 1968)
State Ex Rel. H. K. Porter Co. v. Nangle
405 S.W.2d 501 (Missouri Court of Appeals, 1966)
Kansas City Bridge Co. v. Kansas City Structural Steel Co.
317 S.W.2d 370 (Supreme Court of Missouri, 1958)
Davis v. Gatewood
299 S.W.2d 504 (Supreme Court of Missouri, 1957)
HW Kastor & Sons Adv. Co. v. Grove Laboratories
58 F. Supp. 1011 (E.D. Missouri, 1945)
White v. Kentling
134 S.W.2d 39 (Supreme Court of Missouri, 1939)
Mitchell v. Wabash Railway Co.
69 S.W.2d 286 (Supreme Court of Missouri, 1934)
O'Donnell v. Baltimore & Ohio Railroad
26 S.W.2d 929 (Supreme Court of Missouri, 1930)
Fowlkes v. Fleming
17 S.W.2d 511 (Supreme Court of Missouri, 1929)
City of Cape Girardeau v. Hunze
284 S.W. 471 (Supreme Court of Missouri, 1926)

Cite This Page — Counsel Stack

Bluebook (online)
223 S.W. 45, 282 Mo. 685, 1920 Mo. LEXIS 146, Counsel Stack Legal Research, https://law.counselstack.com/opinion/baker-v-j-w-mcmurry-contracting-co-mo-1920.