Hjelle v. Sornsin Construction Company

173 N.W.2d 431, 1969 N.D. LEXIS 66
CourtNorth Dakota Supreme Court
DecidedDecember 29, 1969
Docket8564
StatusPublished
Cited by39 cases

This text of 173 N.W.2d 431 (Hjelle v. Sornsin Construction Company) is published on Counsel Stack Legal Research, covering North Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hjelle v. Sornsin Construction Company, 173 N.W.2d 431, 1969 N.D. LEXIS 66 (N.D. 1969).

Opinions

ERICKSTAD, Judge.

This is an appeal by the plaintiff, Walter R. Hjelle, State Highway Commissioner, hereafter called the Commissioner, from a judgment of the District Court of Burleigh County dated April 2, 1969, in favor of Nelson Paving Company, Inc., of Williston, hereafter called the Subcontractor. A cross-appeal has been filed by Sornsin Construction Company of Fargo and Sellin Brothers, Inc., of Hawley, Minnesota, a joint venture, hereafter called the Prime Contractor.

The pertinent part of the judgment appealed from reads:

1. That Sections 24-02-26 through 24-02-33 of the North Dakota Century Code are valid and constitutional.
2. That there is privity of contract between the Plaintiff and the Defendant, [433]*433Nelson Paving Company, Inc., and that the controversies arising herein shall be determined by arbitration pursuant to Section 24-02-26 through 24-02-33 of the North Dakota Century Code.
3. That the controversies between the Defendant, Nelson Paving Co., Inc., and the Defendant, Sornsin-Sellin, a Joint Venture, may be determined by arbitration under Section 24-02-26 through 24— 02-33 or by action in Court.

On April 11, 1966, the Prime Contractor was awarded certain highway construction contracts, mainly for the grading and application of aggregate base to certain parts of U. S. Highway 83 situated in Botti-neau, Renville, and Ward Counties. On April 20, 1966, the Commissioner approved the Prime Contractor’s request to sublet certain items of the contract to the Subcontractor. On February 1, 1968, the Subcontractor served the Commissioner and the Prime Contractor with a “petition for arbitration,” naming the Commissioner and the Prime Contractor as respondents. By complaint dated February 8, 1968, the Commissioner initiated a declaratory judgment action whereby he sought (1) to have N.D.C.C. §§ 24-02-26 through 24-02-33 declared unconstitutional and void, and (2) if the sections were found to be constitutional, to have the court award a judgment declaring that the Subcontractor could not assert any claims against the Commissioner.

The Subcontractor filed an answer and counterclaim, denying the contentions of the Commissioner and asserting that if the Court did determine that the arbitration statutes were unconstitutional and void or that they were not applicable to the claims of the Subcontractor, the Subcontractor was entitled to a judgment against the Commissioner of $497,660.80, the amount being the same that it asserted it was entitled to in its petition for arbitration.

The Prime Contractor denied that the provisions of N.D.C.C. ch. 24-02 were unconstitutional, asserted that the petition of the Subcontractor was fatally defective in that it did not comply with the applicable provisions of ch. 24-02, and asserted that to the extent the claims set forth in the petition for arbitration were not frivolous and greatly exaggerated, they could properly be the subject of arbitration between the Commissioner and the Prime Contractor, acting on behalf of the Subcontractor.

At the same time the Subcontractor filed its cross-claim, asking that a declaratory judgment be entered, declaring that the arbitration statutes (§§ 24-02-26 through 24-02-33) are valid and constitutional and apply to the claims of the Subcontractor as set forth in its petition for arbitration, and asking that a board of arbitration be established, pursuant to § 24-02-26, with the Subcontractor being entitled to one arbiter and the Commissioner and the Prime Contractor together being entitled to one arbiter, a third arbiter to be chosen by the other two. It further asks that if the Court determines that the arbitration statutes are unconstitutional and void or that they are not applicable to the claim of the Subcontractor as set forth in its petition, a judgment be given the Subcontractor against the Commissioner for $497,660.80.

The Prime Contractor filed an answer to the cross-claim, asserting that it had fully performed all of its undertakings and obligations under its contract with the Commissioner and under the subcontract with the Subcontractor; and, pertinent among many other allegations, it asserted that the Subcontractor did not have any right to invoke arbitration against the Prime Contractor, but that the Prime Contractor, on behalf of the Subcontractor, was fully prepared and willing to submit to arbitration under ch. 24-02 any claim that the Subcontractor made in good faith against the Commissioner, providing a sufficient surety was obtained.

It was stipulated that the counterclaim and cross-claim of the Subcontractor should be held in abeyance until final disposition of the issues raised in the declaratory judgment action.

[434]*434It is from the judgment of the district court earlier referred to that the Commissioner appeals and the Prime Contractor cross-appeals.

The first point asserted by the Commissioner on appeal is that §§ 24-02-26 through 24-02-33 (requiring the Commissioner and all parties contracting with him to submit to compulsory arbitration all controversies arising out of any contract for the construction or repair of highways which cannot be voluntarily resolved between the parties) are unconstitutional. The arbitration statute most relevant to the issue is § 24-02-26, which reads:

24-02-26. Controversies to be arbitrated —Arbitrators—How named. — All controversies arising out of any contract for the construction or repair of highways entered into by the commissioner shall be submitted to arbitration as provided in this chapter, if the parties cannot agree. Any person who voluntarily enters into a contract for the construction or repair of highways shall be considered as having agreed to arbitration of all controversies arising out of such contract. Three persons shall compose the arbitration board, one of whom shall be appointed by each of the parties and the two thus appointed shall name a third.
North Dakota Century Code.

The Commissioner contends that the compulsory arbitration called for under the statute denies to him, acting as agent of the people of North Dakota, and to private parties who engage in highway construction, the right to due process of law and the use of the courts as guaranteed by §§ 13 and 22 of article I of the North Dakota Constitution and § 1 of article 14 of the amendments to the United States Constitution. He further asserts that the statutes deprive the parties of the right to a jury trial reserved to them by § 7 of article I of the North Dakota Constitution, and that they are in violation of § 120 of article IV of the North Dakota Constitution, which provides that tribunals of conciliation have no power to render judgment obligatory on the parties unless the parties have voluntarily submitted their matters of difference and have agreed to abide by the judgment of the tribunal.

The pertinent parts of those sections read:

Section 13. In criminal prosecutions in any court whatever, the party accused shall have the right to a speedy and public trial; to have the process of the court to compel the attendance of witnesses in his behalf; and to appear and defend in person and with counsel. No person shall be twice put in jeopardy for the same offense, nor be compelled in any criminal case to be a witness against himself, nor be deprived of life, liberty or property without due process of law.
North Dakota Constitution.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Seretta Const., Inc. v. Great American Ins. Co.
869 So. 2d 676 (District Court of Appeal of Florida, 2004)
Harris Associates v. Clark County School District
81 P.3d 532 (Nevada Supreme Court, 2003)
Gratech Co., Ltd. v. WOLD ENGINEERING
2003 ND 200 (North Dakota Supreme Court, 2003)
A. Fred Miller v. Purvis
921 P.2d 610 (Alaska Supreme Court, 1996)
Matter of Adoption of KAS
499 N.W.2d 558 (North Dakota Supreme Court, 1993)
Bayscene Resident Negotiators v. Bayscene Mobilehome Park
15 Cal. App. 4th 119 (California Court of Appeal, 1993)
Little v. Tracy
497 N.W.2d 700 (North Dakota Supreme Court, 1993)
Ure v. Wangler Const. Co., Inc.
597 N.E.2d 759 (Appellate Court of Illinois, 1992)
Grand Forks-Traill Water Users, Inc. v. Hjelle
413 N.W.2d 344 (North Dakota Supreme Court, 1987)
Hanson v. Williams County
389 N.W.2d 319 (North Dakota Supreme Court, 1986)
State v. Stremick Construction Co.
370 N.W.2d 730 (North Dakota Supreme Court, 1985)
Scherbenske Excavating, Inc. v. North Dakota State Highway Department
365 N.W.2d 485 (North Dakota Supreme Court, 1985)
State v. Rivinius
328 N.W.2d 220 (North Dakota Supreme Court, 1982)
W. J. Megin, Inc. v. State
434 A.2d 306 (Supreme Court of Connecticut, 1980)
Shaw v. Burleigh County
286 N.W.2d 792 (North Dakota Supreme Court, 1979)
Power Fuels, Inc. v. Elkin
283 N.W.2d 214 (North Dakota Supreme Court, 1979)
North American Coal Corp. v. Huber
268 N.W.2d 593 (North Dakota Supreme Court, 1978)
Polshek v. Bergen Cty. Iron Works
362 A.2d 63 (New Jersey Superior Court App Division, 1976)
Horst v. Guy
219 N.W.2d 153 (North Dakota Supreme Court, 1974)

Cite This Page — Counsel Stack

Bluebook (online)
173 N.W.2d 431, 1969 N.D. LEXIS 66, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hjelle-v-sornsin-construction-company-nd-1969.