Gratech Co., Ltd. v. WOLD ENGINEERING

2003 ND 200, 672 N.W.2d 672, 2003 N.D. LEXIS 225, 2003 WL 22998179
CourtNorth Dakota Supreme Court
DecidedDecember 23, 2003
Docket20030181
StatusPublished
Cited by24 cases

This text of 2003 ND 200 (Gratech Co., Ltd. v. WOLD ENGINEERING) is published on Counsel Stack Legal Research, covering North Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gratech Co., Ltd. v. WOLD ENGINEERING, 2003 ND 200, 672 N.W.2d 672, 2003 N.D. LEXIS 225, 2003 WL 22998179 (N.D. 2003).

Opinions

SANDSTROM, Acting Chief Justice.

[¶ 1] Gratech Company, Ltd., appeals a Northwest Judicial District Court’s grant of summary judgment dismissing Gra-tech’s complaint alleging several tort claims against Wold Engineering, P.C. The district court granted the summary judgment, finding that N.D.C.C. § 24-02-26 mandates the claims be arbitrated. Gra-tech argues that N.D.C.C. §§ 24-02-26 through 24-02-33 apply only to arbitration claims against the North Dakota Department of Transportation (“DOT”) or the prime contractor under the construction contract and do not apply to independent tort claims brought by a private engineering firm hired to perform services on a DOT project. Because there are no genuine issues of material fact, we affirm the summary judgment; however, we reverse the portion of the judgment dismissing the case with prejudice.

I

[¶ 2] The relevant facts are undisputed. Gratech is a grading contractor. On Octo[675]*675ber 30, 1997, the DOT entered into a contract with Gratech for the construction of a federal aid project on U.S. highway 281. The project was designated as Federal Aid Project No. NH-3-281 (032) 232. The contract was for grading, aggregate base course, and incidentals. The contract provided:

The work shall be done, pursuant to this contract and the laws of the State of North Dakota, and to the satisfaction of NDDOT, subject at all times to the inspection and approval of the U.S. Department of Transportation, its agents and representatives, and in accordance with the rules and regulations made pursuant to state and federal law.

[¶ 3] Wold is a professional engineering firm. On April 9, 1998, the DOT entered into a separate contract with Wold for construction engineering services on the same project. The contract provided:

The engineer shall perform the needed construction engineering work such as, but not limited to, staking, cross-sectioning, inspection, sampling and testing of materials and measuring and computing pay quantities. He shall prepare the required engineering and administrative documents and records as required by NDDOT. It is the engineer’s responsibility to perform construction inspections to verify the contractor’s work is performed according to the government specifications, plans and special provisions including but not limited to, the provisions of NDDOT’s Standards and Specifications for Road and Bridge Construction, Materials Sampling and Testing Manual, Field Office Procedures Manual, and Construction Manual,

[¶ 4] During construction, Gratech encountered difficult soil conditions, and a dispute arose about whether certain work was common excavation covered under the contract or was additional, unforeseen work entitling Gratech to extra compensation. State v. Gratech Co., Ltd., 2003 ND 7, ¶ 2, 655 N.W.2d 417. The project was completed on November 23, .1999, and accepted by the State.on December 28, 1999. Gratech filed an administrative claim against the DOT and .made a demand for arbitration. Gratech’s claim against the DOT was set to be arbitrated in April 2003.

[¶ 5] On May 10, 2002, Gratech filed an action against Wold. Gratech alleged several claims that it classified as tort claims. On February • 20, 2003, Wold moved for summary judgment. On May 6, 2003, the district court granted Wold summary judgment on the basis that N.D.C.C. § 24-02-26 requires Gratech to arbitrate its claims against Wold. The judgment of dismissal was filed on May 12, 2003. Gratech was denied relief from the judgment and is now appealing the grant of the summary judgment.

[¶ 6] The trial court had jurisdiction under N.D. Const, art. VI', § 8, and N.D.C.C. § 27-05-06. The appeal was timely under N.D.R.App.P. 4(a). This Court has jurisdiction under N.D. Const, art. VI, §§ 2 and 6, and N.D.C.C. §§ 28-27-01 and 28-27-02.

[¶ 7] Gratech argues the district court erred in granting Wold summary judgment, because N.D.C.C. §§ 24-02-26 through 24-02-33 apply only to arbitration claims against the DOT or the prime contractor under the construction contract and do not apply to independent tort claims brought against a private engineering firm hired to perform services on a DOT project. Gratech argues it is clear that N.D.C.C. §§ 24-02-26 through 24-02-33 provide for arbitration as the exclusive remedy for claims against the DOT, but [676]*676argues there is nothing in the statutes that prohibits litigation against private parties.

[¶ 8] We review this appeal under our standard for summary judgment. Summary judgment is a procedure for promptly resolving a controversy without a trial if the evidence shows there are no genuine issues as to any material fact and any party is entitled to judgment as a matter of law. N.D.R.Civ.P. 56(c); Koapke v. Herfendal, 2003 ND 64, ¶ 11, 660 N.W.2d 206. “ ‘Even if a factual dispute exists, summary judgment is proper if the law is such that resolution of the factual dispute will not change the result.' ” Id. (quoting Knight v. N.D. State Industrial School, 540 N.W.2d 387, 388 (N.D.1995)). A de novo standard of review is used to determine whether a district court erred in granting summary judgment. Id. On appeal, we view the evidence in the light most favorable to the non-moving party. Id.

[¶ 9] This case involves the interpretation of N.D.C.C. § 24-02-26. The district court found it did not have jurisdiction to hear the case under its interpretation of the statute. The statute provides:

All controversies arising out of any contract for the construction or repair of highways entered into by the director must be submitted to arbitration as provided in this chapter and chapter 32-29.2. Any person who voluntarily enters into a contract for the construction or repair of highways must be considered as having agreed to arbitration of all controversies arising out of that contract. For a claim for less than fifty thousand dollars, only one arbitrator may be jointly selected by the parties. For a claim for fifty thousand dollars or more, three persons comprise the arbitration board.

N.D.C.C. § 24^02-26.

[¶ 10] In construing a statute, we try to ascertain the intent of the legislature by looking at the plain language of the statute and giving every word of the statute its ordinary meaning. N.D.C.C. § 1-02-02; Gronfur v. N.D. Workers Comp. Fund, 2003 ND 42, ¶ 10, 658 N.W.2d 337. Although courts may resort to extrinsic aids to interpret an ambiguous statute, if the language is clear and unambiguous, the legislative intent is presumed clear from the face of the statute. N.D.C.C. §§ 1-02-02, 1-02-05, 1-02-39; State v. Norman, 2003 ND 66, ¶ 14, 660 N.W.2d 549.

[¶ 11] Both parties agree that N.D.C.C. § 24-02-26 is clear and unambiguous; however, they disagree with each other’s clear and unambiguous interpretation. Gratech argues that because the contract between Wold and the DOT is not for “construction work,” it is not for the “construction or repair of highways.” This narrow construction of the statute excludes professional services that are a part of every construction project. Gratech’s contract was for the improvement or construction of U.S. highway 281, while Wold’s contract was to perform construction engineering work on highway 281.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Schulke v. NDDOT
2020 ND 53 (North Dakota Supreme Court, 2020)
Sabo v. Job Service North Dakota
2019 ND 98 (North Dakota Supreme Court, 2019)
Rasnic v. ConocoPhillips Co.
2014 ND 181 (North Dakota Supreme Court, 2014)
Benson v. SRT Communications, Inc.
2012 ND 58 (North Dakota Supreme Court, 2012)
State v. Pack
2012 ND 48 (North Dakota Supreme Court, 2012)
Langowski v. Altendorf
2012 ND 34 (North Dakota Supreme Court, 2012)
Interest of T.H.
2012 ND 38 (North Dakota Supreme Court, 2012)
American Family Insurance v. Waupaca Elevator Co.
2012 ND 13 (North Dakota Supreme Court, 2012)
Thompson v. Thompson
2012 ND 15 (North Dakota Supreme Court, 2012)
Schwarz v. Gierke
2010 ND 166 (North Dakota Supreme Court, 2010)
State Ex Rel. Stenehjem v. Philip Morris, Inc.
2007 ND 90 (North Dakota Supreme Court, 2007)
Gratech Co., Ltd. v. Wold Engineering, PC
2007 ND 46 (North Dakota Supreme Court, 2007)
Ziegler v. Dahl
2005 ND 10 (North Dakota Supreme Court, 2005)
Tri-State Insurance Co. of Minnesota v. Commercial Group West, LLC
2005 ND 114 (North Dakota Supreme Court, 2005)
Makeeff v. City of Bismarck
2005 ND 60 (North Dakota Supreme Court, 2005)
Forster v. West Dakota Veterinary Clinic, Inc.
2004 ND 207 (North Dakota Supreme Court, 2004)
Interest of J.S.
2004 ND 159 (North Dakota Supreme Court, 2004)
Grand Forks County v. Tollefson
2004 ND 161 (North Dakota Supreme Court, 2004)
State v. Higgins
2004 ND 115 (North Dakota Supreme Court, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
2003 ND 200, 672 N.W.2d 672, 2003 N.D. LEXIS 225, 2003 WL 22998179, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gratech-co-ltd-v-wold-engineering-nd-2003.