Gratech Co., Ltd. v. Wold Engineering, PC

2007 ND 46, 729 N.W.2d 326, 2007 N.D. LEXIS 46, 2007 WL 896059
CourtNorth Dakota Supreme Court
DecidedMarch 27, 2007
Docket20060272
StatusPublished
Cited by23 cases

This text of 2007 ND 46 (Gratech Co., Ltd. v. Wold Engineering, PC) is published on Counsel Stack Legal Research, covering North Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gratech Co., Ltd. v. Wold Engineering, PC, 2007 ND 46, 729 N.W.2d 326, 2007 N.D. LEXIS 46, 2007 WL 896059 (N.D. 2007).

Opinions

MARING, Justice.

[¶ 1] Gratech Company, Ltd., (“Gra-tech”) appeals the district court’s judgment confirming an arbitration award in favor of Wold Engineering, P.C., (“Wold”) and against Gratech. Wold cross-appeals that part of the district court’s judgment denying it attorney’s fees. We hold that the district court’s order confirming the arbitration award was proper because the arbitration award was neither completely irrational nor evidenced a manifest disregard for the law. We hold that a district court must provide its rationale for its decision on a request for attorney’s fees so that this Court can properly review whether there was an abuse of discretion. Therefore, we affirm the district court’s judgment confirming an arbitration award in favor of Wold, and reverse and remand that part of the judgment denying Wold attorney’s fees for the district court to explain its reasoning.

I

[¶ 2] Gratech entered into a contract with the North Dakota Department of Transportation (“NDDOT”) on August 18, 1997, to work on U.S. Highway 281 in Rolette County. Wold entered into a subcontract with the NDDOT on April 9,1998, to perform engineering work on the U.S. Highway 281 project.

[¶ 3] Gratech encountered poor soil conditions, which required additional sub-cutting, plowing, discing, and drying of the soil. Gratech requested additional compensation from the NDDOT. When the NDDOT denied Gratech’s claim for additional compensation, Gratech filed a demand for arbitration. The arbitration panel concluded Gratech’s failure to file a written notice of claim precluded arbitration of all but one of Gratech’s claims against the NDDOT. This Court, in Gratech Co. v. North Dakota Dep’t of Transp., 2004 ND 61, 676 N.W.2d 781, affirmed a judgment dismissing Gratech’s application to vacate the arbitration panel’s decision. In Gratech Co. v. North Dakota Dep’t of Transp., Gratech asked this Court to adopt a de novo standard of review for questions of law in a statutorily-mandated arbitration. Id. at ¶¶ 10, 12. This Court decided it was unnecessary to resolve the issue because the arbitration panel correctly decided the issue regardless of the standard used. Id. at ¶ 13.

[¶ 4] In a complaint against Wold dated April 11, 2002, Gratech alleged breach of duty, bad faith, misconstruction of a contract, negligent misrepresentation, and deceit. Gratech, in its complaint, claimed Wold, contrary to the contract, classified plowing, discing, and drying as unplanned subcuts, or incidental work, and refused to pay for them. Purportedly unknown to [329]*329Gratech, at the beginning of the project Wold classified the unstable soils encountered during the project as unsuitable. Gratech contended Wold threatened liquidated damages if the project was not completed on time, even though Wold knew of the conditions that delayed the project. Gratech claimed Wold ordered and directed a substantial amount of uncompensated extra work.

[¶ 5] Wold answered on May 16, 2002, seeking dismissal of Gratech’s complaint, attorney’s fees, and a jury trial. On February 18, 2003, Wold moved for summary judgment, claiming Gratech’s claims were barred by res judicata or collateral estop-pel, or alternatively, Gratech was required to arbitrate all claims. Gratech moved for partial summary judgment on liability. The district court granted Wold’s motion and denied Gratech’s motion. In Gratech Co. v. Wold Engineering, P.C., 2003 ND 200, ¶ 25, 672 N.W.2d 672, this Court held that N.D.C.C. § 24-02-26 required Gra-tech to arbitrate its claims against Wold.

[¶ 6] Subsequently, Gratech filed a demand for arbitration against Wold. On April 7, 2005, Wold moved for summary disposition of the arbitration proceedings based on res judicata, collateral estoppel, statute of limitations, and exclusivity of remedy. The motion was denied by the arbitrator, although he found Wold had satisfied the second, third, and fourth elements of collateral estoppel. The arbitrator determined the first element of collateral estoppel had not been established, as a matter of law and, therefore, required an evidentiary hearing. Following a four day hearing, on January 11, 2006, the arbitrator awarded Gratech nothing on its claims against Wold, but awarded Wold costs. In his explanation of the award, the arbitrator stated that the claim was barred by res judicata and collateral estoppel. The arbitrator found that “the facts giving rise to Gratech’s claim in the first arbitration against ND/DOT are the same in this, the second arbitration.”

[¶ 7] On January 13, 2006, Gratech moved to vacate the arbitration award and sought a new arbitrator. Wold moved to have the arbitration award confirmed. On September 13, 2006, the district court denied Gratech’s motion to vacate the arbitration award. The district court entered judgment confirming the arbitrator’s award in favor of Wold, but denying Wold’s request for attorney’s fees. Gra-tech appeals the district court’s judgment confirming the arbitration award and Wold cross-appeals that part of the district court’s judgment denying it attorney’s fees.

II

[¶ 8] Gratech argues the district court’s judgment confirming the arbitration award in favor of Wold should be reversed and the arbitration award vacated because the arbitration award was completely irrational, or alternatively, evidences a manifest disregard for the law. This Court has said before, “without a transcript, we would not be able to conduct a meaningful review of the ... factual findings.” Superpumper, Inc. v. Nerland Oil, Inc., 2003 ND 33, ¶ 17, 657 N.W.2d 250. “The appellant assumes the consequences and the risk for the failure to file a complete transcript. If the record on appeal does not allow for a meaningful and intelligent review of alleged error, we will decline review of the issue.” Id. This Court, in Superpumper, reviewed the issue under the limited record, because a transcript was not provided. Id. at ¶ 18. In this case, there is not a transcript of the arbitration proceeding. Gratech, as the appellant, assumed the consequences and risk for failing to file a complete transcript. This Court’s ability to administer a mean[330]*330ingful and intelligent review is severely-hindered by the incomplete record available on appeal. This Court, therefore, reviews the issues under the limited record provided.

[¶ 9] Gratech relies on N.D.C.C. § 32-29.3-23 to support its claim that the arbitration award should be vacated.

1. Upon motion to the court by a party to an arbitration proceeding, the court shall vacate an award made in the arbitration proceeding if:
[[Image here]]
d. An arbitrator exceeded the arbitrator’s powers;
[[Image here]]
3 .... If the award is vacated on a ground stated in subdivision ... d ... of subsection 1, the rehearing may be before the arbitrator who made the award or the arbitrator’s successor.

N.D.C.C. § 32-29.3-23.

[¶ 10] In Nelson Paving Co. v. Hjelle, 207 N.W.2d 225, 234 (N.D.1973), this Court, after considering decisions from other jurisdictions, adopted the rule that an arbitration award will not be vacated unless the award is completely irrational.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sanderson v. Agotness
2024 ND 232 (North Dakota Supreme Court, 2024)
Nelson, et al. v. Lindvig, et al.
2024 ND 208 (North Dakota Supreme Court, 2024)
LAWC Holdings v. Vincent Watford
2024 ND 16 (North Dakota Supreme Court, 2024)
Shafer v. Scarborough
2022 ND 233 (North Dakota Supreme Court, 2022)
Hagen v. North Dakota Insurance Reserve Fund
2022 ND 53 (North Dakota Supreme Court, 2022)
Neppel v. Development Homes
2021 ND 5 (North Dakota Supreme Court, 2021)
Rocky Mountain Steel Foundations. v. Brockett Company
2019 ND 252 (North Dakota Supreme Court, 2019)
Beckstrand Ex Rel. Beckstrand v. Beckstrand
2017 ND 20 (North Dakota Supreme Court, 2017)
Podrygula v. Bray
2014 ND 226 (North Dakota Supreme Court, 2014)
C.V. v. Guardian & Protective Services, Inc.
2011 ND 10 (North Dakota Supreme Court, 2011)
State v. Martin
2011 ND 6 (North Dakota Supreme Court, 2011)
Riemers v. State
2008 ND 101 (North Dakota Supreme Court, 2008)
Guardianship & Conservatorship of D.M.O. v. M.O.
2008 ND 100 (North Dakota Supreme Court, 2008)
In Re Guardianship of DMO
2008 ND 100 (North Dakota Supreme Court, 2008)
Rutherford v. Rutherford
552 F. Supp. 2d 980 (D. North Dakota, 2008)
Geraci v. Women's Alliance, Inc.
547 F. Supp. 2d 1022 (D. North Dakota, 2008)
Lynch v. Sweeney
2007 ND 81 (North Dakota Supreme Court, 2007)
Gratech Co., Ltd. v. Wold Engineering, PC
2007 ND 46 (North Dakota Supreme Court, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
2007 ND 46, 729 N.W.2d 326, 2007 N.D. LEXIS 46, 2007 WL 896059, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gratech-co-ltd-v-wold-engineering-pc-nd-2007.