Scherbenske Excavating, Inc. v. North Dakota State Highway Department

365 N.W.2d 485
CourtNorth Dakota Supreme Court
DecidedApril 9, 1985
DocketCiv. 10818
StatusPublished
Cited by21 cases

This text of 365 N.W.2d 485 (Scherbenske Excavating, Inc. v. North Dakota State Highway Department) is published on Counsel Stack Legal Research, covering North Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Scherbenske Excavating, Inc. v. North Dakota State Highway Department, 365 N.W.2d 485 (N.D. 1985).

Opinion

LEVINE, Justice.

This is an appeal by the State Highway Department from a district court judgment affirming an arbitration award of $781,-604.00 in favor of Scherbenske Excavating, Inc. (Scherbenske) and denying the Highway Department’s motion to vacate the award.

In the summer of 1980 Scherbenske contracted with the Highway Department to pave 21.5 miles of roadway near Beulah. The contract provided that Scherbenske would commence work by mid-August 1980 and complete the project by the fall of 1980. It was further agreed that Scher-benske would work on a mile-by-mile basis as the subcontractors completed their preparatory work on the road. Subsequently the State Highway Department decided that Scherbenske could not begin work until all subcontractors had completed preparation of the entire stretch of 21.5 miles. As a result, Scherbenske was delayed in beginning its work for approximately two months until mid-October 1980, and was unable to complete the job until September 1981. Factors contributing to the delay in completion were inclement weather in the summer of 1981, inferior preparation by the subcontractors, and a greater than anticipated increase of traffic.

Because of these delays the State imposed liquidated damages of $11,600.00. However, the State later conceded responsibility for Scherbenske’s delay in commencement and agreed that the assessment of liquidated damages was not warranted.

Scherbenske made a claim against the Highway Department for the increased cost due to the delay and subsequently demanded arbitration pursuant to North Dakota Century Code § 24-02-26. A hearing was held before three arbitrators. They awarded Scherbenske $781,604.00 1 and Scherbenske subsequently moved the district court to affirm the award while the State moved to vacate it. Following a *487 hearing the court denied the State’s motion to vacate and granted Scherbenske’s motion to affirm the award. Judgment was entered and the State filed this appeal.

The Highway Department’s initial contention is that the “completely irrational” standard of review of arbitration awards announced in Nelson Paving Co., Inc. v. Hjelle, 207 N.W.2d 225 (N.D.1973), should be abandoned in favor of a more liberal scope of review.

In Nelson Paving, decided a little over a decade ago, the North Dakota State Highway Department argued, as it does in the instant case, for vacation of the arbitration award under NDCC § 32-29-08(4) 2 because the arbitrators “exceeded their powers” in making their award. This Court, after surveying case law of other jurisdictions, adopted the New York rule and concluded that an arbitration award would not be vacated pursuant to § 32-29-08(4) unless the award were completely irrational. Nelson Paving, supra at 234.

In Nelson Paving the court set out the perimeter of complete irrationality from which it reasoned that an award not devoid of rationality would be affirmed:

“The mistakes that will void an award are those appearing on its face or gross mistakes of the arbitrators extraneously appearing as to their powers or duties, which result in real injustice or constructive fraud.” Nelson Paving, supra at 230.

This court has not had occasion since Nelson Paving to apply or discuss the completely irrational standard of review. Other courts have done so and their analyses are helpful in filling in the interstices of an abstract principle with particular instances.

In O-S Corporation v. Samuel A. Kroll, Inc., 29 Md.App. 406, 348 A.2d 870, 872 (1975), an arbitration award was vacated as completely irrational because the contract provided no rationale for the award without resort to a wholly spurious, illogical interpretation of essential contractual language.

The Maryland Court of Appeals offered a rather poetic if not elucidating definition of a “completely irrational” award as one which is “inferentially opprobrious, i.e., ‘[expressing or carrying a sense of disgrace or contemptuous scorn’ causing it to be suspect in its conception.” O-S Corporation, supra 348 A.2d at 872. However, some light was shed by its explanation that there need be only some evidence to meet the test of rationality, i.e., it may be so little as to make the result “arbitrary,” so long as it is not completely irrational. O-S Corporation, supra 348 A.2d at 874.

Representative of another line of cases holding that an arbitration award is not completely irrational so long as the arbitrators considered the “proper sources” in fashioning the award is the Rhode Island Supreme Court’s prescription:

“As long as the award ‘draws its essence’ from the contract, and is based upon a ‘passably plausible’ interpretation of the contract, it is within the arbitrator’s authority and our review must end.” Rhode Island Council 94 v. State, 456 A.2d 771, 773 (R.I.1983).

In Rhode Island Council 94, the contention was that an arbitration award was completely irrational in retroactively suspending two employees because there was no contract provision for retroactive suspension. The court affirmed the award on the basis of the arbitrator’s inherent power to fashion an appropriate remedy, noting that the employment contract did not specifically prohibit retroactive suspension and thus the award “drew its essence” from the contract. Rhode Island Council 94, supra at 774-775.

Yet another explanation of the completely irrational standard of review is that an arbitrator exceeds his powers when he *488 gives a completely irrational construction to the agreement in dispute, thereby effectively creating a new contract between the parties. Sweeney v. Herman Management, Inc., 85 A.D.2d 34, 447 N.Y.S.2d 164, 168 (1982). In the Sweeney case the court concluded the arbitrator took a contract with arguable terms, and, by ignoring and misrepresenting some facts and adding new ones, created nonexistent legal duties and an entirely new contract with different obligations, rendering the resulting award completely irrational. Sweeney, supra at 168.

As the foregoing discussion illustrates the definitive constituents of a completely irrational award cannot be formulated in the abstract but, like all legal principles, can best be developed on a case-by-case basis. The Highway Department urges revision of the present scope of review to require vacation of an arbitration award under NDCC § 32-29-08(4) if it is not “supported by evidence or. other basis of reason,” a standard adopted by the New York Court of Appeals in Mount St. Mary’s Hospital of Niagara Falls v. Catherwood,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Shafer v. Scarborough
2022 ND 233 (North Dakota Supreme Court, 2022)
Gratech Co., Ltd. v. Wold Engineering, PC
2007 ND 46 (North Dakota Supreme Court, 2007)
John T. Jones Construction Co. v. City of Grand Forks
2003 ND 109 (North Dakota Supreme Court, 2003)
O&K Glass Co. v. Innes Const. Co., Inc.
2000 ND 56 (North Dakota Supreme Court, 2000)
McKibben v. Grigg
1998 ND App 5 (North Dakota Court of Appeals, 1998)
Superpumper, Inc. v. Nerland Oil, Inc.
1998 ND 144 (North Dakota Supreme Court, 1998)
Allstate Insurance Co. v. Nodak Mutual Insurance Co.
540 N.W.2d 614 (North Dakota Supreme Court, 1995)
Little v. Tracy
497 N.W.2d 700 (North Dakota Supreme Court, 1993)
Byron's Construction Co. v. North Dakota Department of Transportation
463 N.W.2d 660 (North Dakota Supreme Court, 1990)
Byron's Construction Co. v. North Dakota State Highway Department
448 N.W.2d 630 (North Dakota Supreme Court, 1989)
State v. Stremick Construction Co.
370 N.W.2d 730 (North Dakota Supreme Court, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
365 N.W.2d 485, Counsel Stack Legal Research, https://law.counselstack.com/opinion/scherbenske-excavating-inc-v-north-dakota-state-highway-department-nd-1985.