John F. Harkins Co. v. SCH. DIST. OF PHIL.

460 A.2d 260, 313 Pa. Super. 425, 1983 Pa. Super. LEXIS 2955
CourtSuperior Court of Pennsylvania
DecidedApril 22, 1983
Docket358
StatusPublished
Cited by19 cases

This text of 460 A.2d 260 (John F. Harkins Co. v. SCH. DIST. OF PHIL.) is published on Counsel Stack Legal Research, covering Superior Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
John F. Harkins Co. v. SCH. DIST. OF PHIL., 460 A.2d 260, 313 Pa. Super. 425, 1983 Pa. Super. LEXIS 2955 (Pa. Ct. App. 1983).

Opinion

WIEAND, Judge:

In this appeal we are asked to review the trial court’s determination of the amount of increased compensation which a plumbing contractor was entitled to receive after the School District of the City of Philadelphia had temporarily advanced the date for completing a school construction *428 project. The trial court’s award of additional compensation was determined by the difference between the contractor’s actual labor costs and the amount of the estimated labor costs included in his original bid, plus 15 percent for profit and overhead. In addition, the court made an award representing a ten percent saving which the contractor might have been able to make on the estimated labor costs contained in his original bid.

On April 28, 1969, a contract was entered between John F. Harkins Co., Inc., appellee, and the School District of Philadelphia, appellant, by the terms of which Harkins was to do the plumbing work in connection with the construction of West Philadelphia University City High School. The contract price was $1,092,920, and the contract terms established a completion date of 1,000 consecutive calendar days following receipt of notice to proceed. After construction had commenced, the school district, in an attempt to achieve an earlier occupancy date, issued a change order accelerating performance of the contract by approximately five months, from January 30, 1972 to September 1, 1971. In order to permit early completion, the district placed Harkins on overtime for a period of 26 weeks. On or about February 1, 1970, the school district revoked its earlier change order and reinstated the original completion date.

The contract between the parties permitted the school district to make changes and modifications so long as they were within the contract’s general scope. The contract provided for an “equitable adjustment” by the school district in the event changes or modifications resulted in an increase or decrease in the contractor’s cost of performance of the contract. The contract’s general conditions, in paragraph 22(b), stipulated as follows:

(b) The determination of the increase or decrease in compensation to be paid the contractor for additions to or reductions to the work, respectively, shall be determined by application of unit prices as set forth in the special conditions of the contract, or, in those cases where unit prices are not applicable, by a lump sum mutually agreed *429 upon by the Board and the contractor. If, however, unit prices are not applicable, and if the parties cannot agree upon a lump sum then additional compensation to be paid the contractor shall be determined by the actual net cost in labor and materials plus fifteen per centum (15%) for profit and overhead.... The School District will make the final determination as to net cost of labor and materials.

The school district paid the contractor the sum of $57,241 to compensate him for the actual cost of overtime which he paid to his employees. However, Harkins was dissatisfied with this amount and commenced an action in assumpsit to recover additional damages allegedly sustained because of the overtime required before the accelerated completion date was revoked. The trial court, sitting without a jury, entered a general finding in favor of Harkins for $197,907, plus interest. The school district filed exceptions, alleging that the damages awarded by the court were improper and not supported by the evidence. In dismissing the school district’s exceptions, the trial judge authored an opinion explaining the manner in which he had calculated damages.

In awarding damages, the trial court had determined the difference between the contractor’s total labor costs of $481,803 and its initial bid estimate for labor in the amount of $276,513. This amount had then been reduced by the sum of $57,241 previously paid to the contractor by the school district to compensate him for actual overtime expenses incurred while the accelerated completion date remained in effect. The court had then added to this amount the sum of $27,651, which represented 10 percent of the original bid estimate. This additional sum, the court had concluded, was necessary to compensate the contractor for a built-in or engineered profit margin which might have been realized if the construction project had proceeded according to the original time schedule. Finally, the court had awarded the contractor an additional sum of $22,207, which represented profits and overhead at the rate of 15 percent on the labor overrun. After exceptions had been *430 dismissed, judgment was entered on the findings of the trial court, and the school district appealed.

The proceeding in the trial court was not an action for breach of contract. It was a claim for an equitable adjustment of the contract price because of the school district’s change order which required the contractor to place his employees on overtime to meet an accelerated completion date. The school district had early conceded that an adjustment was necessary because of the contractor’s additional labor costs and had paid to the contractor an additional sum of $57,241. This amount had been determined according to actual overtime costs incurred by the contractor, plus profit and overhead. The school district, therefore, denied further liability. At trial, appellant offered no evidence. It argued, however, as it does on appeal, that the contractor failed to prove that it was entitled to recover additional sums. It contends on appeal that the trial court erred by making an award and that in doing so the court adopted a measure of damages which was imprecise, speculative and improper. We agree.

In order to prove additional damages, the contractor showed that his total labor costs had exceeded the estimated labor costs upon which the contract price had been based by $205,290. This measure of damages was a variation of the “total cost” approach which requires that the estimated cost under the contract be subtracted from the actual cost to determine damages.

The total cost method of determining damages is “inseparably connected with the rule that the amount of damages need not be ascertained with mathematical certainty to sustain an award in the [contractor’s] favor.” Rubin, “The Total Cost Method of Computing an Equitable Adjustment — An Analysis,” 26 Fed.B.J. 303, 304 (1966). It is premised on the fact that where a contractor is entitled to an adjustment, the governmental body should not be exonerated merely because the contractor is unable to prove his increased costs with precision. However, because the total *431 cost method of measuring damages is imprecise it is fraught with danger and must be applied with caution.

This measure of damages has not been favored by the courts. It “ ‘has been tolerated only when no other mode was available and when the reliability of the supporting evidence was fully substantiated____ The acceptability of the method hinges on proof that (1) the nature of the particular losses make it impossible or highly impracticable to determine them with a reasonable degree of accuracy; (2) the plaintiffs bid or estimate was realistic; (3) its actual costs were reasonable; and (4) it was not responsible for the added expenses.’ ” Boyajian v. United States,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hempt Bros, Inc. v. Myers, A.
Superior Court of Pennsylvania, 2021
Wayne Knorr, Inc. v. Department of Transportation
973 A.2d 1061 (Commonwealth Court of Pennsylvania, 2009)
James Corp. v. North Allegheny School District
938 A.2d 474 (Commonwealth Court of Pennsylvania, 2007)
A. G. Cullen Construction, Inc. v. State System of Higher Education
898 A.2d 1145 (Commonwealth Court of Pennsylvania, 2006)
Green Construction Co. v. Department of Transportation
643 A.2d 1129 (Commonwealth Court of Pennsylvania, 1994)
Amp-Rite Electric Co. v. Wheaton Sanitary District
580 N.E.2d 622 (Appellate Court of Illinois, 1991)
Seattle Western Industries, Inc. v. David A. Mowat Co.
750 P.2d 245 (Washington Supreme Court, 1988)
Southeastern Sprinkler Co. v. Meyertech Corp.
831 F.2d 410 (Third Circuit, 1987)
Glasgow, Inc. v. Commonwealth
529 A.2d 576 (Commonwealth Court of Pennsylvania, 1987)
Commonwealth v. Trumbull Corp.
513 A.2d 1110 (Commonwealth Court of Pennsylvania, 1986)
Larry Armbruster & Sons, Inc. v. State Public School Building Authority
505 A.2d 395 (Commonwealth Court of Pennsylvania, 1986)
Scherbenske Excavating, Inc. v. North Dakota State Highway Department
365 N.W.2d 485 (North Dakota Supreme Court, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
460 A.2d 260, 313 Pa. Super. 425, 1983 Pa. Super. LEXIS 2955, Counsel Stack Legal Research, https://law.counselstack.com/opinion/john-f-harkins-co-v-sch-dist-of-phil-pasuperct-1983.