G. C. S., Inc. v. Foster Wheeler Corp.

437 F. Supp. 757, 1975 U.S. Dist. LEXIS 12290
CourtDistrict Court, W.D. Pennsylvania
DecidedMay 19, 1975
DocketCiv. A. 94-71 Erie, 4-72 Erie
StatusPublished
Cited by7 cases

This text of 437 F. Supp. 757 (G. C. S., Inc. v. Foster Wheeler Corp.) is published on Counsel Stack Legal Research, covering District Court, W.D. Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
G. C. S., Inc. v. Foster Wheeler Corp., 437 F. Supp. 757, 1975 U.S. Dist. LEXIS 12290 (W.D. Pa. 1975).

Opinion

MEMORANDUM OPINION

WEBER, Chief Judge.

These are cross-suits between a prime contractor and its sub-contractor over damages for delay in completion. We have a motion for partial Summary Judgment filed by the prime contractor, Foster-Wheeler, on certain of the claims asserted by the subcontractor, G.C.S. Inc. in its complaint and in its counterclaim to Foster-Wheeler's suit.

We have previously considered a motion for summary judgment by Foster-Wheeler on its “no damages for delay” clause of its contract. We found that issue not appropriate for disposition by summary judgment at that time.

The matter has proceeded through voluminous discovery and pre-trial statements to a point where we can determine the evidentiary basis for the delay damage claims sufficiently to consider them with *758 respect to partial summary judgment to define and narrow the fact issues that can be presented at trial. We have pressed G.C.S. Inc. to supply at the pretrial the evidentiary basis by which its loss and damage can be established by reason of its claims that damages were caused by change orders, extra work and drawing revisions.

The contract between the parties contains the following provisions with respect to change orders, extra work and revisions: *

Foster Wheeler Purchase Order.
Terms and Conditions .
“2. CHANGES: Purchaser shall have the right from time to time by written notice, without notice to Seller’s sureties, to make changes in or additions to the instructions, drawings, or specifications for the items to be supplied under this Order and Seller agrees to comply with such change notices which shall become a part of the contract. If such changes cause an increase or decrease in the cost of or time required for performance, an equitable adjustment in the price and delivery schedule shall be made.”

Through interrogatories, depositions and documentary discovery it has been established that in all cases where GCS performed extra work under contract changes GCS agreed to all changes and was compensated for such extra work in accordance with the provisions of the agreement. Although the above quoted provision of the contract allowed GCS to request additional time to complete its work by reason of any change order the evidence shows that at no time did GCS ask for such additional time. Actually, one item of extra work was performed by GCS prior to the execution of the Purchase Order and prior to the date of commencement of the contract work, this being the excavation and site-preparation work for the north end of the refinery project.

The Purchase Order provided the method for the authorization of changes and extra work and the compensation to be paid therefor:

PURCHASE ORDER.
“Sec. 4 B PART ONE (PHASE “B”) BUILDING.
FOR PART ONE 1PHASE “B” ONLY) THE FOLLOWING SHALL APPLY FOR AUTHORIZED EXTRA WORK.
a) Materials Cost plus 10%
b) Subcontracts Cost plus 10%
e) Labor (Burdens included) Cost plus 15% Plus 10%
d) Equipment (Company Owned) A.E.D. Less 10%
e) Equipment (Rented) Cost plus 10%
C. PART TWO-“UNDERGROUND PIPING”
d) For authorized extra work not covered by Units Costs, the following Cost Plus Formula shall apply.
1. Materials Cost Plus 10%
2. Labor (Burdens Included) Cost Plus 15% Plus 10%
Sec. 7. EXTRA WORK AND/OR DELETED WORE
a) No field Extra Work (above original scope) shall be performed without authorization in writing by “PURCHASER’S” Representative.
b) Reimbursement For: (See Item lid)
1. Authorized Field Extra Work. (Item 7a).
2. Extra Work, and/or Credits for Deleted Work due to revisions to drawings previously transmitted to “SELLER” shall be in accordance with quoted Unit Costs.
See. 11. TERMS OF PAYMENT & INSTRUCTIONS.
d) Extra and/or Credits Cif anvl must first be:
1. Authorized by change to subject order.
2. Properly included on Form 282, (after receipt of proper change order), before submitted to “PURCHASER’S” Field Representative.”

That the subcontractor’s delay and the consequences thereof were within the contemplation of the parties is also evidenced by the terms of the Purchase Order:

5. GENERAL
(d)
1. Further, installed Unit Costs shall remain FIRM if “SELLER” is released to commence work before April 1, 1970 and is not delayed by “PURCHASER” or Pennzoil United beyond the date of June 30, 1970 for substantial completion, and July 15, 1970 for final completion and cleanup.
2. In the event that “SELLER” is delayed beyond the above dates by either “PURCHASER” or Pennzoil United, the *759 labor portion of “SELLER’S” costs may be subject to escalation due to renegotiated labor contracts. In this event, “SELLER” will invoice “PURCHASER” his out-of-pocket labor costs, which shall consist of actual increase in base pay, plus applicable insurance and payroll taxes and any additions to fringe packages. The foregoing applies to direct labor only.
Material costs shall be firm and not subject to escalation.

The above extracts from the Purchase Order are recited to make clear that all items of extra work were contemplated by the parties and were the subject of negotiations between the parties and prior to the performance of any extra work or changes or revisions.

In addition to the contract provisions governing the extra work, the testimony of Mr. Christensen and Mr. Grey on deposition clearly establishes that GCS expected to be requested to perform extra work on the job and that the contract made provision for such extra work and the method of payment for such work.

There is no claim here that GCS was not paid for any extra work called for by contract changes or drawing revisions.

While GCS does not dispute this fact it contends that not all of the extra work was contemplated by the parties at the time the contract was entered into, and that certain of the items were of such magnitude and occurred sufficiently late on the job as not to be within the contemplation of the parties. Further, GCS contends that the change orders, extra work and drawing revisions were of such a scope as to amount to active interference by Foster-Wheeler on the job which therefore entitled GCS to damages for delay despite-the inclusion of a clause in the contract barring any claim for damages for delay.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

ILM Systems, Inc. v. Suffolk Construction Co.
252 F. Supp. 2d 151 (E.D. Pennsylvania, 2002)
Spang & Co. v. United States Steel Corp.
518 A.2d 273 (Superior Court of Pennsylvania, 1986)
Delahanty v. First Pennsylvania Bank, N.A.
464 A.2d 1243 (Supreme Court of Pennsylvania, 1984)
John F. Harkins Co. v. SCH. DIST. OF PHIL.
460 A.2d 260 (Superior Court of Pennsylvania, 1983)
EC Ernst, Inc. v. Koppers Co., Inc.
476 F. Supp. 729 (W.D. Pennsylvania, 1979)

Cite This Page — Counsel Stack

Bluebook (online)
437 F. Supp. 757, 1975 U.S. Dist. LEXIS 12290, Counsel Stack Legal Research, https://law.counselstack.com/opinion/g-c-s-inc-v-foster-wheeler-corp-pawd-1975.