G. C. S., Inc. v. Foster Wheeler Corp.

437 F. Supp. 764, 1977 U.S. Dist. LEXIS 14492
CourtDistrict Court, W.D. Pennsylvania
DecidedAugust 15, 1977
DocketCiv. A. 94-71 ERIE, 4-72 ERIE
StatusPublished
Cited by4 cases

This text of 437 F. Supp. 764 (G. C. S., Inc. v. Foster Wheeler Corp.) is published on Counsel Stack Legal Research, covering District Court, W.D. Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
G. C. S., Inc. v. Foster Wheeler Corp., 437 F. Supp. 764, 1977 U.S. Dist. LEXIS 14492 (W.D. Pa. 1977).

Opinion

OPINION

WEBER, Chief Judge.

These two actions are cross actions which arise out of the same contract and involve the same extensive mass of facts. Civil Action No. 4-72 Erie, Foster Wheeler Corporation vs. G.C.S. and I.S.C. was filed in New Jersey and transferred to this District under 28 U.S.C. § 1441 because of the location here of the essential operative facts. It was a non-jury action. Civil Action No. 94-71 Erie, was an action by G.C.S. and I.S.C. against Foster Wheeler brought in this district with a demand for jury trial. The cases were consolidated for pretrial purposes. The cases were consolidated for trial and the court submitted the entire case to the jury under special interrogatories which would provide an advisory verdict in the non-jury action at Civil Action No. 4-72 Erie.

The cases arise out of the construction of additions to an oil refinery owned by Pennzoil United, Inc. at Rouseville, Pennsylvania. Foster Wheeler was the general contractor for the project, and G.C.S. was its subcontractor for the construction and installation of concrete foundations, paving, underground electrical installation and underground piping. G.C.S. also performed some other subcontracting work by separate contracts, such as site clearance and the construction of masonry buildings which were not subject to the provisions of the time limits which are critical here, and thus not relevant to our present consideration.

Foster Wheeler had contracted with Pennzoil to complete the mechanical installation of the additions to the refinery by January 31,1971. The subcontract between Foster Wheeler and G.C.S. called for G.C.S. to start its work on April 1, 1970 and substantially to complete all foundations, underground electrical and piping, backfill and paving, by June 30, 1970, or within 90 days. This work was not completed until after November 1, 1970.

The main thrust of Foster Wheeler’s claim was that the continued presence of G.C.S. on the job site after September 1, 1970, and its failure to have substantially completed its subcontract work on foundations, underground electrical and piping, backfill and paving, interfered and delayed the start of Foster Wheeler’s scheduled above-ground steel erection and piping. It was contended that this delay prevented Foster Wheeler’s efficient start of its above-ground steel erection and pipe installation for two months and required Foster Wheeler to perform its major construction work during the worst winter months when Foster Wheeler was unable to obtain a sufficient crew of pipefitters because their efficiency, productivity and reliability of attendance was severely hampered because of the impact of severe winter weather on the performance. Foster Wheeler argues that as a direct and proximate result, Foster Wheeler’s above-ground piping operations took four months longer to complete than was originally scheduled and that as a result Foster Wheeler incurred direct additional out-of-pocket costs in the amount of $637,482.00.

The advisory jury was given three interrogatories addressed to this issue, and answered them as follows:

A. THE FOSTER WHEELER CLAIMS
1. Was Foster Wheeler caused to incur additional costs in its above-ground piping program because of delays of GCS for which GCS may be held responsible in its performance of the contract for foundations, underground piping and electrical work backfill and paving?
ANSWER YES_
(Yes) or (No).
If your Answer to No. 1 is Yes, answer No. 2.
2. Is there a reasonable basis in the evidence for determining how much of Foster Wheeler’s extra costs in its above ground piping resulted from delays caused solely by GCS exclusive of other causes?
Answer_YES_
(Yes) or (No).
If your Answer to No. 2 is Yes, answer No. 3.
*766 3. What is the amount of damages suffered by Foster Wheeler in its pipe installation program which was caused solely by GCS?
$ 159.371.00_

Thus, the jury concluded that Foster Wheeler suffered a one-month period of additional expense due to delay caused by G.C.S.

G.C.S. now argues that Foster Wheeler experienced no delay which was caused by G.C.S.; that the evidence establishes reasons that account for all significant delays to job progress aside from any fault of G.C.S., and that the evidence does not provide any reasonable basis for allocating damages to any various delay causing events.

THE APPLICABLE LAW

The ruling case law provides that where the cause and the fact of damages have been established, a party is not to be denied damages because they are difficult to determine with mathematical precision. Story Parchment Co. v. Paterson Co., 282 U.S. 555, 51 S.Ct. 248, 75 L.Ed. 544 [1931]. It is sufficient if the evidence provides a reasonable basis to determine the extent of damages. Bigelow v. RKO Radio Pictures, 327 U.S. 251, 66 S.Ct. 574, 90 L.Ed. 652 [1946]. More specifically applicable to this case is the rule applied to a construction contract where there were multiple causes for delay. In Lichter v. Mellon-Stuart, 193 F.Supp. 216 [W.D.Pa.1961], aff’d. 305 F.2d 216 [3d Cir. 1962], the court faced the problem of the apportionment of damages based upon the inability to provide a reasonable basis for allocating certain damages between actionable and non-actionable causes of delay. Plaintiff proved the actual cost of performing the masonry job as delayed and interrupted by various causes, and the calculated cost of performing this work without delay, and claimed the difference as damages. This amount was not allowed because the evidence submitted did not provide any reasonable basis to allocate this damage between those for which the defendant was responsible and those for which he was without blame. However, as to one particular item, the trial court found that there was a reasonable basis for the allocation of 42 days to the replacement of certain stone work made necessary because of negligent installation by the defendant. The court then took 42 days of the claimed delay time of 68 days and found 42/68 of the total claimed loss of $10,332 to be properly allocable to the item for which defendant was responsible.

The Court of Appeals affirmed:
“The court undertook such an allocation, guided by evidence concerning the extra time required for the performance of the stone contract as the result of improper shelf angles. We cannot say that this was an arbitrary method of allocation.” 305 F.2d 216 at p. 221.

Also in United States v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

John F. Harkins Co. v. SCH. DIST. OF PHIL.
460 A.2d 260 (Superior Court of Pennsylvania, 1983)
EC Ernst, Inc. v. Koppers Co., Inc.
476 F. Supp. 729 (W.D. Pennsylvania, 1979)
Foster Wheeler Corp. v. G. C. S. Inc
578 F.2d 1374 (Third Circuit, 1978)
G. C. S., Inc. v. Foster Wheeler Corp
578 F.2d 1374 (Third Circuit, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
437 F. Supp. 764, 1977 U.S. Dist. LEXIS 14492, Counsel Stack Legal Research, https://law.counselstack.com/opinion/g-c-s-inc-v-foster-wheeler-corp-pawd-1977.