Glasgow, Inc. v. Commonwealth

529 A.2d 576, 108 Pa. Commw. 48, 1987 Pa. Commw. LEXIS 2338
CourtCommonwealth Court of Pennsylvania
DecidedJuly 28, 1987
DocketAppeals, Nos. 284 C.D. 1986 and 317 C.D. 1986
StatusPublished
Cited by12 cases

This text of 529 A.2d 576 (Glasgow, Inc. v. Commonwealth) is published on Counsel Stack Legal Research, covering Commonwealth Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Glasgow, Inc. v. Commonwealth, 529 A.2d 576, 108 Pa. Commw. 48, 1987 Pa. Commw. LEXIS 2338 (Pa. Ct. App. 1987).

Opinion

Opinion by

Senior Judge Narick,

Petitioner Glasgow, Inc. (Glasgow) appeals and Respondent Commonwealth of Pennsylvania, Department of Transportation (Department)' cross-appeals from an order of the Board of Claims (Board). We affirm.

[50]*50This matter involves a contractual dispute between Glasgow, a Pennsylvania corporation engaged in the construction business, and the Department. On June 26, 1969, Glasgow entered into a contract with the Department whereby Glasgow was to perform certain highway and bridge construction regarding a certain portion of highway and bridge on Legislative Route (L.R.) 1016-8A, and located in Allegheny County.

The instant dispute arises out of delays in construction of a portion of L. R. 1016-8A at the interchange between L.R. I016-8A and the Penn Lincoln Parkway (Parkway).1 Glasgows claim for damages focuses on bridge S-7944, which is a two-tiered structure with its lower portion resting on the Parkway.2 Bridge S-7944 carries ramps over L.R. 765.

A certain bypass and other temporary structures were necessary to this project for the purpose of routing traffic off the Parkway and onto the bypass during construction. This temporary bypass which enabled Glasgow to perform reconstruction of the Parkway was constructed and used throughout the term of the project.3 The temporary bypass could not be removed until the reconstructed Parkway could again carry traffic. The project could not be completed until the temporary bypass was removed.

The two-tiered substructure of S-7944, as originally designed by the Department, included pier footers,4 pier columns and pier caps.5

[51]*51On or about March 28, 1972, the Department issued a stop order on the construction of pier 1 of S-7944 because testing revealed that the subsurface material was insufficient support for the foundation which had been designed for that pier. On or about April 26, 1972, the Department ordered a halt to the construction of pier 2 of S-7944 due to insufficient subsurface materials.

The evidence before the Board revealed the following. After issuing the stop orders regarding pier 1 and pier 2, the Department decided to redesign the substructure for both piers. Glasgow had been, up until the issuance of the stop orders, performing its obligations under the contract in a timely fashion. On or about June 26, 1972, Glasgow received the new design for the piers. However, as a result of the Departments stop orders, redesign, and additional work, the construction of S-7944 was delayed for approximately three months. The delay in completion of S-7944 delayed removal of the bypass which in turn delayed completion of the project as per the terms of the contract. Glasgow, in fts complaint, alleged it suffered damages in the amount of $874,790.50 as a result of the Departments breach of contract. After twenty-three days of hearings, the Board issued an order on January 6, 1986 which concluded that the redesign by the Department was a breach of contract which resulted in $389,645.44 in damages to Glasgow.6

The issues presented for our consideration are: (1) whether or not there was substantial evidence to indicate that the redesign of pier 1 and pier 2 resulted in damages to Glasgow; (2) whether or not the Board erred [52]*52in awarding damages on a total cost basis; (3) whether or not there was substantial evidence to support the Boards conclusion that 64.43% of Glasgows damage claim was attributable to Glasgows performance of extra work, and therefore properly excludable as an allowable damage expense; and (4) whether or not the Board correctly held that the instant cause of action was not barred by the doctrines of res judicata and collateral estoppel.

We are mindful that our scope of review is limited to a determination of whether constitutional rights were violated, an error of law was committed, or whether necessary findings of fact are supported by substantial evidence. Section 704 of the Administrative Agency Law, 2 Pa. C. S. §704; Estate of McGovern v. State Employees’ Retirement Board, 512 Pa. 377, 517 A.2d 523 (1986).

First, we will discuss the Boards award of damages to Glasgow and its utilization of the total cost theory for calculating damages.7 In its opinion, the Board stated:

Glasgow has proven that the delay in this instance caused a breach of the contract between the parties and as a result thereof Glasgow did sustain certain damages. This proof has been of a sufficient nature to comply with the law of the Commonwealth. . . . The Board, was presented with evidence, both physical and testamentary in nature, that would allow it to find that damages are due to the injured party.

The Board, in concluding that the total cost method was the appropriate theory to be applied in calculating [53]*53Glasgows damages indicated that “despite extensive record keeping and a genuine good faith effort to do so, the Plaintiff [Glasgow] was not able to specifically list the precise dollar amount of every cost incurred as a result of the Departments breach of this contract”.

The Boards calculations with regard to the total cost method are as follows. Glasgows overhead costs incurred as a direct result of the delay in construction were incurred during the year of 1973 and totalled $78,482.46. As to the amount of damages due Glasgow other than overhead costs the Board determined it could not accept the entire amount of delay damages claimed by Glasgow. More specifically, the Board concluded that the damages allegedly incurred for extra work performed could not be included in Glasgows damage calculations. The Board in calculating damages other than overhead did accept as a starting point Glasgows original damage calculation, including extra work, of $874,790.50. Based upon the testimony of the Departments accounting witness, Louis Rubino, the Board determined that extra work constituted 64.43% of the work performed.8 The Board, by subtracting 64.43% or $563,627.52 from $874,790.50, assessed Glasgows damages excluding overhead costs at $311,162.98. Thus, by combining $78,482.46 with $311,162.98 the Board concluded that Glasgows total damages were $389,645.44.

The total cost method for calculating damages involves the subtraction of the estimated costs set forth in the contract from actual costs. See E. C. Ernst, Inc. v. Koppers Co., Inc., 626 F.2d 324 (1980) which applied Pennsylvania law involving construction contracts. The Courts, recognizing that the total cost method is subject to speculation, will only utilize this method when there [54]*54is no other means of determining damages and the plaintiff has presented reasonably accurate evidence of the various costs incurred. Id., John F. Harkins Co. v. School District of Philadelphia, 313 Pa. Superior Ct. 425, 460 A.2d 260 (1983), and Armbruster and Sons, Inc. v. State Public School Building Authority, 95 Pa. Commonwealth Ct.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

B. Washington v. Bureau of Driver Licensing
Commonwealth Court of Pennsylvania, 2023
Wayne Knorr, Inc. v. Department of Transportation
973 A.2d 1061 (Commonwealth Court of Pennsylvania, 2009)
A. G. Cullen Construction, Inc. v. State System of Higher Education
898 A.2d 1145 (Commonwealth Court of Pennsylvania, 2006)
Abbott v. Schnader, Harrison, Segal & Lewis, LLP
805 A.2d 547 (Superior Court of Pennsylvania, 2002)
McKie v. Huntley
2000 SD 160 (South Dakota Supreme Court, 2000)
Yi v. COM., DOT, BUREAU OF DRIVER LIC.
646 A.2d 603 (Commonwealth Court of Pennsylvania, 1994)
Green Construction Co. v. Department of Transportation
643 A.2d 1129 (Commonwealth Court of Pennsylvania, 1994)
Hibbs v. Chester-Upland School District
606 A.2d 629 (Commonwealth Court of Pennsylvania, 1992)
Wagner v. Commonwealth
559 A.2d 999 (Commonwealth Court of Pennsylvania, 1989)
Commonwealth v. Crawford
550 A.2d 1053 (Commonwealth Court of Pennsylvania, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
529 A.2d 576, 108 Pa. Commw. 48, 1987 Pa. Commw. LEXIS 2338, Counsel Stack Legal Research, https://law.counselstack.com/opinion/glasgow-inc-v-commonwealth-pacommwct-1987.