Acchione and Canuso v. COM., DEPT. OF TR.

461 A.2d 765, 501 Pa. 337, 1983 Pa. LEXIS 524
CourtSupreme Court of Pennsylvania
DecidedApril 25, 1983
Docket81-3-406
StatusPublished
Cited by12 cases

This text of 461 A.2d 765 (Acchione and Canuso v. COM., DEPT. OF TR.) is published on Counsel Stack Legal Research, covering Supreme Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Acchione and Canuso v. COM., DEPT. OF TR., 461 A.2d 765, 501 Pa. 337, 1983 Pa. LEXIS 524 (Pa. 1983).

Opinions

OPINION

ZAPPALA, Justice.

This is an appeal from an Order of the Commonwealth Court reversing a Board of Claims award granted to appellant-construction company for increased costs incurred due to extra trenching work not included in the original contract but ordered subsequent to that contract’s execution.

Facts relevant to the disposition of this appeal are summarized from the comprehensive findings made by the Board as follows:

Appellant and appellee entered into a contract on October 5, 1975 for highway improvements in Philadelphia County, Pennsylvania. Item 910-6000 of the contract called for 13,131 lineal feet (If) of trenching which was to be let at a unit price per lineal foot.

This trenching consisted of excavating areas of grass, sidewalk, and highway. These respective areas involved different costs per lineal foot due to the varying degree of difficulty required to trench those areas. Because the contract item required only a unit price for all trenching, it was important to ascertain the exact area to be trenched so that the amount of each respective area could be calculated and averaged into one unit price.

From an inspection of the site and a take-off of the plans, DePaul, the subcontractor of appellant, calculated that 16,-[340]*340658 linear feet of trenching would be required to complete the job. This was 3,527 linear feet more than the bid specifications required. Due to this discrepancy, he contacted the consulting engineers for the project who directed DePaul to assume that 50% of the existing conduit would be reusable and thus would require no new trenching.

From this information, DePaul proceeded to calculate the cost for individual areas of trenching and from that the unit price as follows:

Individual Areas Totals
Cost for Earth ____9,759 l.f. X $13 l.f. $126,867
Cost for Sidewalk .. 3,033 l.f. X $23 l.f. 69,759
Cost for Highway .. 3,866 l.f. X $52 l.f. 201,032
(126,867) + (69,759) + (201,032) = 397,658 = $23.87 Unit Price/l.f.
16,658 16,658

Based on this calculation, DePaul entered a $24 lineal foot bid for the trenching. This bid was included in the contract bid which was subsequently accepted by the Department of Transportation (PennDOT).

Following the award of the contract to appellant, Penn-DOT ordered pull tests to determine the reusability of the existing conduit. These tests revealed that a substantial amount of the existing conduit could not be reused.

In December of 1974, PennDOT’s engineers authorized an additional 17,433 linear feet of trenching, some of which had already been performed. This authorization, approved by the office of the Chief Engineer on January 6, 1975, did not categorize the amount of trenching to be performed in grass, sidewalk or highway areas. The reason given for this additional work order and its subsequent authorization was stated by Penn Dot’s engineer as follows:

. . . This work is required due to the omission by the designer and the consultant in the plans and in the Contract of a contingency item. This item was planned to cover the installation of conduit where reusable conduit does not check out to be usable. The corresponding trenching item was also not revised accordingly. The complete item for trenching on the interconnect system was also omitted by the designer and the consultant.

[341]*341As a result of the additional trenching authorized by the December 31, 1974 work order, increases in all trenching areas occurred, so that the final trenching totals were as follows: trenching in sidewalk increased to 3,393.00 lineal feet; trenching in roadway increased to 12,988.70 lineal feet; trenching in grass increased to 14,770.10 lineal feet. The total number of lineal feet to be trenched increased from 13,131 lineal feet to 31,151.80 lineal feet. The increase in the most expensive area of trenching, roadway, rose 336%. These increases had the effect of increasing the unit price $6.14 to $30.14 per lineal foot, based upon the original calculations.

Appellant did not become aware of the effect this extra trenching was having on the unit cost until late July of 1975, just prior to completion of the total project. It was at this time that they submitted a claim for extra compensation to Penn Dot. This claim was denied and appellant then filed his claim with the Board of Claims.

The Board, in awarding the extra compensation to appellant, found that the extra trenching materially changed the character of the work performed and also the cost to do that work. They also found that the increases resulted from appellant’s reliance on plan specifications and oral representations made by appellee’s engineers as to the amount of reusable conduit, and that these increases could not have been foreseen by appellant until most of the work was completed.

On appeal to the Commonwealth Court, the Court reversed the award of the board, holding that the board misapplied the rule of Pa. Turnpike Commission v. Smith, 350 Pa. 355, 39 A.2d 139 (1944) in finding constructive fraud on the part of PennDOT and further placed the burden of ascertaining the increased costs and negotiation for increased compensation on appellant in spite of the Board’s finding that appellant could not ascertain such increases until the end of the job. Pennsylvania Dept, of Trans, v. Acchione and Canuso, Inc., 55 Pa.Comwlth. 65, 423 A.2d 30 (1980).

[342]*342A close reading of Smith indicates to us that the Board’s application of the rule was valid and we therefore reverse the decision of the Commonwealth Court.

In Smith, this Court found constructive fraud where the Turnpike Commission failed to notify bidders of rock conditions known to it and different from those shown in the bidding documents. Smith, relying on those documents to prepare his bid, incurred additional expenses in completing the project when subsurface conditions were found to be much more difficult to excavate than the plans had shown. In allowing Smith to recover, this Court found that the bidding documents were positive statements upon which Smith had a right to rely, citing Hollerbach v. U.S., 233 U.S. 165, 34 S.Ct. 553, 58 L.Ed. 898 (1914). Hollerbach involved a government contract to repair a certain dam in Kentucky. In it’s bid documents, the government required bidders to examine the job site. The documents also contained a description of the dam site and the material backing the dam. In performing the contract work, the contractor found the backing material to be of a type more difficult to remove than that represented in the plans. There was no finding that the content of the actual backing material was known to the government at the time the bid documents were distributed. Rather, in allowing the contractor to recover, the U.S. Supreme Court stated:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kobin Coal Corp. & Hazleton Shaft Corp. v. DGS & DOC
Commonwealth Court of Pennsylvania, 2019
Eastern Electric Corp. v. Shoemaker Construction Co.
657 F. Supp. 2d 545 (E.D. Pennsylvania, 2009)
Mar-Paul Co. v. Jim Thorpe Area School District
7 Pa. D. & C.5th 387 (Carbon County Court of Common Pleas, 2008)
Department of General Services v. Pittsburgh Building Co.
920 A.2d 973 (Commonwealth Court of Pennsylvania, 2007)
A. G. Cullen Construction, Inc. v. State System of Higher Education
898 A.2d 1145 (Commonwealth Court of Pennsylvania, 2006)
Thomas M. Durkin & Sons, Inc. v. Department of Transportation
742 A.2d 233 (Commonwealth Court of Pennsylvania, 1999)
IA CONST. v. Dept. of Transp.
591 A.2d 1146 (Commonwealth Court of Pennsylvania, 1991)
I.A. Construction Corp. v. Department of Transportation
591 A.2d 1146 (Commonwealth Court of Pennsylvania, 1991)
Glasgow, Inc. v. Commonwealth
529 A.2d 576 (Commonwealth Court of Pennsylvania, 1987)
Black Top Paving Co. v. Commonwealth
466 A.2d 774 (Commonwealth Court of Pennsylvania, 1983)
Acchione and Canuso v. COM., DEPT. OF TR.
461 A.2d 765 (Supreme Court of Pennsylvania, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
461 A.2d 765, 501 Pa. 337, 1983 Pa. LEXIS 524, Counsel Stack Legal Research, https://law.counselstack.com/opinion/acchione-and-canuso-v-com-dept-of-tr-pa-1983.