Eastern Electric Corp. v. Shoemaker Construction Co.

657 F. Supp. 2d 545, 2009 WL 2914212, 2009 U.S. Dist. LEXIS 75959
CourtDistrict Court, E.D. Pennsylvania
DecidedAugust 26, 2009
DocketCivil Action 08-3825
StatusPublished
Cited by59 cases

This text of 657 F. Supp. 2d 545 (Eastern Electric Corp. v. Shoemaker Construction Co.) is published on Counsel Stack Legal Research, covering District Court, E.D. Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Eastern Electric Corp. v. Shoemaker Construction Co., 657 F. Supp. 2d 545, 2009 WL 2914212, 2009 U.S. Dist. LEXIS 75959 (E.D. Pa. 2009).

Opinion

MEMORANDUM

PRATTER, District Judge.

The complications attendant to the procedural history of this litigation among the contractors, subcontractors, and owners of a multimillion dollar condominium project in Philadelphia rival the intricacies of the project itself. However, because much of the procedure is irrelevant to the pending motion for entry of default judgment, the Court will discuss here only history relevant to this particular motion.

On August 12, 2008, Eastern Electric Corp. of New Jersey (“Eastern”), a subcontractor on the condominium project, filed suit against the general contractor (Shoemaker Construction Co.) and the project owners (1419 Tower L.P., Urban Residential, LLC, and Metropolitan Housing Partners, LLC) alleging breaches of the construction contracts. On January 15, 2009, Shoemaker filed cross claims against 1419 Tower and Urban Residential. 1

Upon request from Shoemaker, the Clerk of Court entered default on April 7, 2009 against 1419 Tower and Urban Residential for failure to appear, plead or defend. Shoemaker moved for entry of default judgment on May 8, 2009. The Court ordered 1419 Tower and Urban Residential to respond to Shoemaker’s motion on or before June 12, 2009. Neither third-party Defendant responded to the motion.

For the reasons set forth below, the Court will grant Shoemaker’s Motion for Entry of Default Judgment.

1. Background

Shoemaker and 1419 Tower, an affiliate of Urban Residential, entered into a written contract (the “Contract”) in January 2006 for the rehabilitation and conversion of an office building into a residential building (the “Project”). The office building, which is located at 1419 Locust Street in Philadelphia, was to be converted into a condominium containing 114 residential units. Cross-claim ¶ 6; Ball Aff., Exhibit B. According to the terms of the contract, Shoemaker was to perform construction work 2 for the Project as dictated by the *549 plans and specifications provided by 1419 Tower. Shoemaker submitted to 1419 Tower (“Owner”) its final guaranteed maximum price (“GMP”) for the Project on or about March 6, 2006, and 1419 Tower accepted. This GMP was incorporated into the Contract by written Amendment No. 1. Cross-claim ¶ 7; Ball Aff., Exhibit C. Both parties agreed that Amendment No. 1 would reflect that the original GMP for the Project was $34,989,000, and the date of Substantial Completion of the Project was scheduled for July 31, 2007. Cross-claim ¶ 8; Ball Aff. ¶ 6, Exhibit C.

Before entering into the contract with Shoemaker, 1419 Tower also entered into contracts with a number of design professionals. 1419 Tower named Handle Architects, LP (“Handel” or “Architect”) the project architect, and 1419 Tower also contracted with Paul H. Yoemans, Inc. (“PHY”), Sehirmer Engineering (“Schirmer”), The Kachele Group (“TKG”), and VDA Associates (“VDA”). Collectively, these companies are known as the “Owner’s Design Team.” The Owner’s Design Team then created detailed drawings and specifications for the Project, which were presented to Shoemaker to facilitate construction of the Project. 3 Cross-claim ¶¶ 9-13; Ball Aff. ¶ 7.

Next, Shoemaker, in accordance with the Contract and upon review and approval by the Owner, entered into a number of contracts with subcontractors. These subcontractors included Eastern, A.T. Chadwick Service Co., Inc. (“Chadwick”), James J. Gory Mechanical Contracting, Inc. (“Gory”), and Wyatt, Inc. (“Wyatt”). Cross-claim ¶ 16; Ball Aff. ¶ 9, Exhibits D, E, F, and G. In accordance with the terms of the subcontracts, each of the subcontractors agreed (1) to cooperate with Shoemaker regarding claims involving the Owner, (2) to be bound to Shoemaker in the same manner in which Shoemaker was bound to 1419 Tower pursuant to the Contract, and (3) to be ruled by the decisions of a court of competent jurisdiction with respect to related pass-through claims. See e.g., Ball Aff., Exhibit D ¶ 20.

In the months between February 2006 and October 2006, the Project was delayed by a number of problems, including issues with mechanical, electrical, plumbing, and sprinkler rise coordination; a loss of temporary power to the high rise portion of the building; unforeseen site conditions discovered in the clay tile lining of shaft walls; and mud slab removal. Cross-claim ¶¶ 17-24.

In the months between October 2006 and August 2007, the Project was again delayed by a lengthy list of problems, including shaft in fill work, shaft remediation work for damaged clay tile, 1419 Tower’s inability to process change orders in a timely fashion, design changes to the MEP work and pressure reducing valves (“PRV’s”), design changes in the scope of the work for the elevator buffers, design changes to add a dual gas main, delays to the hoist removal, and allegedly Owner-initiated changes to customize and combine condominium units. Cross-claim ¶¶ 25-32.

In early 2007, as the Project progressed, 1419 Tower was unable to process change orders. Shoemaker worked with Owner to *550 resolve the problem. At Owner’s request, on or about April 4, 2007, Shoemaker and Urban Residential entered into a new written agreement (the “Construction Agreement” or “Sub-Job Agreement”) for the performance of the then-identified additional work and the changed work. Cross-claim ¶ 28; Ball Aff. ¶ 12, Exhibit I.

In accordance with the Sub-Job Agreement, Urban Residential acknowledged Shoemaker’s claim and the reservation of the right to an extension of time to complete the additional and changed work. Also, the parties agreed that the schedule of requirements of the Project would be relaxed. Lastly, it was agreed that Shoemaker would use its best efforts to complete the low-rise portion of the building on or before July 31, 2007, and that Shoemaker would use its reasonable best efforts to complete the high rise portion prior to October 31, 2007. Cross-claim ¶ 28; Ball Aff. ¶ 13. All change orders with respect to the Project issued on or before January 1, 2007 were issued under the Sub-Job Agreement. Cross claim ¶ 28(e).

By September 2007, the July 2007 Substantial Completion date of the Project had come and gone and was pushed back to December 18, 2007. This was as a result of multiple prior delays that Shoemaker claims occurred through no fault of its own or any of the subcontractors it hired. The December deadline was predicated on accelerating the remaining work in the hopes of achieving the Temporary Certificate of Occupancy by October 12 and conveying units for occupancy before the end of 2007. In order to meet these deadlines, parallel work had to be performed on multiple floors at once. In the months from September to December, the subcontractors’ available manpower and the rate of material deliveries could not support the accelerated schedule. Due to additional delays that occurred between September and December, the projected Substantial Completion date again was pushed back to March 28, 2008. Cross-claim ¶ 34; Ball Aff. ¶¶ 15-16.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
657 F. Supp. 2d 545, 2009 WL 2914212, 2009 U.S. Dist. LEXIS 75959, Counsel Stack Legal Research, https://law.counselstack.com/opinion/eastern-electric-corp-v-shoemaker-construction-co-paed-2009.