J. E. Brenneman Co. v. Commonwealth

424 A.2d 592, 56 Pa. Commw. 210, 1981 Pa. Commw. LEXIS 1077
CourtCommonwealth Court of Pennsylvania
DecidedJanuary 21, 1981
DocketAppeal, No. 1752
StatusPublished
Cited by4 cases

This text of 424 A.2d 592 (J. E. Brenneman Co. v. Commonwealth) is published on Counsel Stack Legal Research, covering Commonwealth Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
J. E. Brenneman Co. v. Commonwealth, 424 A.2d 592, 56 Pa. Commw. 210, 1981 Pa. Commw. LEXIS 1077 (Pa. Ct. App. 1981).

Opinion

OpiNioN by

Judge Blatt,

The petitioner in this case, J. E. Brenneman Company, appeals a decision of the Board of Claims (Board) rejecting the petitioner’s contractual claims against the Commonwealth’s Department of Transportation (DOT).

In 1970, the petitioner, after being chosen as the successful bidder in the construction project in question, entered into a written agreement with DOT in which the petitioner agreed to provide all the materials and labor for the improvement of the road and bridges along a certain section of highway in Montgomery County. As part of the construction of twin bridges involved in the project, the petitioner originally was to furnish 271 lengths of 36-inch diameter drilled caissons,1 aggregating approximately 5271 linear feet, but the project was subsequently redesigned, requiring the addition of extra caissons for a total of 276. When DOT sent out its initial requests [212]*212for bids, it included plans and specifications declaring that the caissons were to be seated on rock with a bearing capacity of 15 tons per square foot and delineating, as the Board found, “the distance into which the foot of the caissons was to be socketed into solid rock or minimum tip elevations.”2 The documents also contained the results of 73 test holes which had been bored by an independent company at DOT’S direction in order to indicate subsurface conditions and facilitate the design of the pier structures which were to support the roadbeds of the bridges. The petitioner began installation of the caissons and, at times, encountered rock above the minimum tip elevation which was not shown in the test hole data. In 78 of the caissons in which unanticipated rock was discovered, DOT did not insist that the petitioner reach the minimum tip elevation specified in the drawings, but in all other such instances DOT required that the rock be removed and that the caissons penetrate at least to the minimum tip elevation.

The petitioner filed a complaint before the Board alleging four counts against DOT. Count I maintained that DOT failed to provide adequate test bor-ings for the project, that there was insufficient time between DOT’S solicitation of bids and the deadline for their submission to allow the petitioner to seek its own subsurface survey and, as a result, materially different subsurface conditions were discovered which required the petitioner to excavate and extract 1523.6 linear feet of excess rock. Count II alleged that the drawings specify that the caissons were to be socketed one foot into solid rock and that DOT’s insistence that the petitioner could not stop after drilling one foot into rock but must continue to penetrate at least [213]*213to the minimum tip elevation caused the petitioner damages by necessitating removal of 1812.4 linear feet of additional rock. Count III claims that DOT acted arbitrarily and capriciously by requiring that the caissons penetrate through more than one lineal foot of rock and to the minimum tip elevation. Count IY contends that, as a result of the delays caused by the unnecessary excavation delineated in the first three counts, the petitioner could not keep up its schedule for erection of the structural steel used to support the bridges and consequently incurred damages for storage and repainting of that steel. After multiple hearings and the taking of extensive evidence, the Board denied all the petitioner’s claims.

Our scope of review is limited to determining whether or not the order of the Board of Claims was supported by substantial evidence and was in accordance with law, PennDOT v. E. J. Albrecht Co., 48 Pa. Commonwealth Ct. 491, 409 A.2d 1202 (1980), and, after reviewing the case law and the reproduced record, we must affirm the Board’s order.

The petitioner contends that the Board erred in not finding that DOT was guilty of constructive fraud in that the test hole data misrepresented the subsurface conditions which could be expected. Pennsylvania Turnpike Commission v. Smith, 350 Pa. 355, 39 A.2d 139 (1944), or, alternatively, that the insufficiency of that data combined with ambiguities within the contract and DOT’S arbitrary administration of the agreement amounted to such fraud.

The petitioner declares that DOT misrepresented the subsurface conditions of the area in that prospective bidders were given insufficient time between DOT’s request for bids and the deadline for submission of bids to undertake independent tests of the subsurface and that, therefore, the petitioner [214]*214necessarily and justifiably relied upon tbe test bole data wbicb was distributed by DOT, but wbicb did not adequately depict tbe actual subsurface conditions.

Tbe very language of tbe contract itself refutes tbis argument. Tbe contract documents included Form 408, Specifications, Section 102.05 wbicb provides :

Wherever subsurface material information is indicated on tbe drawings, based upon soundings, dug test pits, and/or auger or test borings, sucb information relative to tbe character of subsurface material is of a preliminary nature and has been obtained for the exclusive use of tbe Department to facilitate tbe design of tbe project. Therefore, tbis information is not to be considered as a part of the drawings, cross-sections, proposal, or contract, nor as a factor for computation of the unit prices used for bidding purposes. There is no expressed or implied agreement that tbe depths or tbe character of tbe material have been correctly indicated at, or that uniformity of material exists between, tbe explored locations, and the bidder is expressly cautioned not to rely on the privileged information, but to assume the possibility that conditions, affecting the cost and/or quantities of work to be performed, may differ from those indicated. (Emphasis added.)

And paragraph 4 of tbe contract states:

The contractor further covenants and warrants that he has had sufficient time to examine the site of the work; that he has examined the site of the work; that be has bad sufficient time to examine tbe site of tbe work to deter[215]*215mine the character of the subsurface material and conditions to be encountered; that he is fully aware and knows of the character of the subsurface material and conditions to be encountered; and that he has based the within contract prices on his own independent examination and investigation of the site, subsurface materials, and conditions and has not relied on any subsurface information furnished to him by the Commonwealth of Pennsylvania, Department of Transportation. (Emphasis added.)

In Department of Transportation v. Acchioni & Canuso, Inc., 14 Pa. Commonwealth Ct. 596, 601, 324 A.2d 828, 831 (1974), this Court enforced identical exculpatory clauses in a similar case and noted:

Bidding on contracts is unquestionably a risky operation especially where, as here, it is made clear that reliance cannot be assumed on the tests which the Commonwealth had taken in order to determine its design criteria. . . .

Free access — add to your briefcase to read the full text and ask questions with AI

Related

R. Zoppo Co. v. City of Dover
475 A.2d 12 (Supreme Court of New Hampshire, 1984)
Acchione and Canuso v. COM., DEPT. OF TR.
461 A.2d 765 (Supreme Court of Pennsylvania, 1983)
County of Montgomery v. Commonwealth, Department of Commerce
434 A.2d 1316 (Commonwealth Court of Pennsylvania, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
424 A.2d 592, 56 Pa. Commw. 210, 1981 Pa. Commw. LEXIS 1077, Counsel Stack Legal Research, https://law.counselstack.com/opinion/j-e-brenneman-co-v-commonwealth-pacommwct-1981.