Commonwealth v. S. J. Groves & Sons Co.

343 A.2d 72, 20 Pa. Commw. 526, 1975 Pa. Commw. LEXIS 1123
CourtCommonwealth Court of Pennsylvania
DecidedJuly 29, 1975
DocketAppeals, Nos. 1577 and 1589 C.D. 1974
StatusPublished
Cited by20 cases

This text of 343 A.2d 72 (Commonwealth v. S. J. Groves & Sons Co.) is published on Counsel Stack Legal Research, covering Commonwealth Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Commonwealth v. S. J. Groves & Sons Co., 343 A.2d 72, 20 Pa. Commw. 526, 1975 Pa. Commw. LEXIS 1123 (Pa. Ct. App. 1975).

Opinion

Opinion by

Judge Rogers,

These are cross-appeals by the Commonwealth’s Department of Transportation and S. J. Groves and Sons Company from a decision by the Board of Arbitration of Claims in litigation arising out of a highway construction contract entered into in 1961, under which the work was completed in 1964, with respect to which the contractor’s claim was filed with the Board in 1968, and the Board’s decision was rendered in 1974. The Board awarded Groves, the contractor, damages in the amount of $819,999.88, for extra costs and expenses on account [528]*528of the Department’s failure to advise the contractor prior to the award of the contract that the latter would not have access to a portion of the construction site for 14 weeks while the American Telephone & Telegraph Company removed and replanted coaxial conduits.

The Department of Transportation presents three questions. The first is that the Board was without jurisdiction because Groves’ claim was not filed within six months after it accrued as required by Section 6 of the Act of May 20, 1937, P.L. 728, 72 P.S. §4651.6. This argument can be quickly disposed of by reference to the specifications, Section 1.9.8 of which provides: “[t]he date on which the Secretary of Highways, through his authorized representative, notifies the contractor of the final certificate computations, or revised computations, as the case may be, shall be the date from which the time limit shall begin to run for the submission of claims to the Board of Arbitration of Claims named in the contract, and for such purpose shall be the date of completion of the contract.” The Department’s district engineer did not issue Final Certificate Computations until September 16, 1968, a date more than a year after Groves filed its claim with the Board. In Lashner, Inc. v. Department of Highways, 1 Pa. Commonwealth Ct. 486, 275 A.2d 403 (1971), we had occasion to consider the same contention by the Department in connection with a contract containing the same clause and there, by Judge Crumlish, Jr., we wrote:

“It is clear that the specification incorporated into the contract which set the date of notification of computations as the date which commenced the running of the statute of limitations and which made notification a prerequisite to any suit under the contract, indicate the undeniable intent of both Lashner and the Commonwealth to consider the date of notification as the accrual date of any cause of action under the contract.” (Emphasis in original.) 1 Pa. Commonwealth Ct. at 490, 275 A. 2d at 405.

[529]*529Hence, the claim was timely filed and the Board had jurisdiction.

Furthermore, the Commonwealth objected preliminarily that the claim was filed late; it never objected that it was prematurely filed. Indeed, after its preliminary objection to the original complaint was sustained with leave to Groves to plead again, the Department failed to file objections to Groves’ amended complaint, but answered on the merits and went to trial. The first day of trial was a date after the issuance of the Final Certificate Computations.

The Department next contends that the Board erred in concluding that the Commonwealth committed constructive fraud by failing to notify Groves that a portion of the work area would be unavailable during 141/a weeks1 while AT&T relocated its coaxial cables.

The Board made comprehensive findings which our careful review convinced us are supported by the evidence. The Board summarized these findings in its Discussion which we adopt as a brief but accurate account of the facts, as follows:

“There appears to be no substantial dispute of the relevant facts. Plaintiff was the successful bidder on a contract involving the improvement of Bristol Pike (Route #13) and intersecting roads and bridges in Bucks County. The area of the project involved in this dispute was at the intersection of Bristol Pike and Woodhaven Road. At this point, Bristol Pike runs in an east-west direction and Woodhaven Road in a north-south direction. Prior to the awarding lof this contract, these two roads intersected each other at ground level.

“The Defendant, Department of Highways, desired to have these two roads intersect at different levels to facilitate the flow of traffic in the area. This was to be [530]*530accomplished by the excavation and lowering of Wood-haven Road and the construction of a bridge on Bristol Pike, allowing traffic on Bristol Pike to be carried over Woodhaven Road. In addition, under the contract, an interchange between the two roads was to be built.

“In order to perform the work under the contract, it was necessary to excavate a large quantity of earth located north of Bristol Pike and use said excavated material as fill in various areas south of Bristol Pike. However, one of the special requirements of the contract ... prohibited the contractor from crossing Bristol Pike with construction equipment and required the work north of Bristol Pike to await the completion of the bridge, so that the excavation could be moved by going under Bristol Pike.

“In order to construct the bridge on Bristol Pike, Plaintiff planned to direct traffic to the north side of Bristol Pike on a temporary run-around road. This would enable Plaintiff to excavate south of Bristol Pike and to construct the bridge. Upon completion of the bridge and placing it in service, excavation and the other work could proceed to the north without interfering with traffic on Bristol Pike.

“The special requirement referred to provided inter alia:

‘. . . the contractor will be required to confine his excavating operations for the Woodhaven Interchange to the area (south of the temporary road) . . . until the proposed Bristol Pike Bridge over Woodhaven Road and the new pavement on Bristol Pike is opened to traffic and in use by the public.’

“Thus, the prompt and timely completion of the bridge on Bristol Pike was a matter of great importance; for the orderly prosecution of the entire project required access to the area north of Bristol Pike at the earliest possible time.

“On August 9, 1961 at the pre-construction meeting, Plaintiff first learned that the work site would be bur[531]*531dened with the excavation and relocation of the A. T. & T. coaxial conduit; that it would be obliged to do the excavation of the cable; and that thereafter there would be a fourteen (14) week delay in access to the work site until A. T. & T. completed their work.

“Contractor further learned that negotiations concerning the cable had been the subject of correspondence between Defendant (Department of Highways) and A. T. & T. since at least June 10, 1959.2 This information concerning the correspondence and negotiations between the Department of Highways and A. T. &T. was never communicated to the Plaintiff or noted in any portion of the bid documents or contract prior to Plaintiff’s bid on the project.

“Since Plaintiff was unable to proceed in accordance with their Schedule of Operation, (which, incidentally, [532]*532was in substantial agreement with that submitted by the Department), because of the A. T. & T. presence, the project sequence was compressed and thrown ‘out of gear’.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Myco Mechanical, Inc. v. The City of York
Commonwealth Court of Pennsylvania, 2022
John Spearly Construction, Inc. v. Penns Valley Area School District
121 A.3d 593 (Commonwealth Court of Pennsylvania, 2015)
XL Specialty Insurance v. Massachusetts Highway Department
31 Mass. L. Rptr. 147 (Massachusetts Superior Court, 2013)
Eastern Electric Corp. v. Shoemaker Construction Co.
657 F. Supp. 2d 545 (E.D. Pennsylvania, 2009)
James Corp. v. North Allegheny School District
938 A.2d 474 (Commonwealth Court of Pennsylvania, 2007)
Guy M. Cooper, Inc. v. East Penn School District
903 A.2d 608 (Commonwealth Court of Pennsylvania, 2006)
A. G. Cullen Construction, Inc. v. State System of Higher Education
898 A.2d 1145 (Commonwealth Court of Pennsylvania, 2006)
Department of Transportation v. Anjo Construction Co.
666 A.2d 753 (Commonwealth Court of Pennsylvania, 1995)
Department of Transportation v. Herbert R. Imbt, Inc.
39 Cont. Cas. Fed. 76,548 (Commonwealth Court of Pennsylvania, 1993)
Grimme Combustion, Inc. v. Mergentime Corp.
595 A.2d 77 (Superior Court of Pennsylvania, 1991)
Coatesville Contractors & Engineers, Inc. v. Borough of Ridley Park
506 A.2d 862 (Supreme Court of Pennsylvania, 1986)
Coatesville Contractors & Engineers, Inc. v. Borough of Ridley Park
488 A.2d 353 (Superior Court of Pennsylvania, 1984)
Acchione and Canuso v. COM., DEPT. OF TR.
461 A.2d 765 (Supreme Court of Pennsylvania, 1983)
Commonwealth, Department of Community Affairs v. Craftech International, Ltd.
456 A.2d 247 (Commonwealth Court of Pennsylvania, 1983)
Commonwealth v. General Asphalt Paving Co.
405 A.2d 1138 (Commonwealth Court of Pennsylvania, 1979)
C. J. Langenfelder & Son, Inc. v. Commonwealth
404 A.2d 745 (Commonwealth Court of Pennsylvania, 1979)
Commonwealth v. Paoli Construction Co.
386 A.2d 173 (Commonwealth Court of Pennsylvania, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
343 A.2d 72, 20 Pa. Commw. 526, 1975 Pa. Commw. LEXIS 1123, Counsel Stack Legal Research, https://law.counselstack.com/opinion/commonwealth-v-s-j-groves-sons-co-pacommwct-1975.