Department of Transportation v. Herbert R. Imbt, Inc.

39 Cont. Cas. Fed. 76,548, 630 A.2d 550, 157 Pa. Commw. 573, 1993 Pa. Commw. LEXIS 515
CourtCommonwealth Court of Pennsylvania
DecidedAugust 13, 1993
Docket1178 C.D. 1992 and 1277 C.D. 1992
StatusPublished
Cited by9 cases

This text of 39 Cont. Cas. Fed. 76,548 (Department of Transportation v. Herbert R. Imbt, Inc.) is published on Counsel Stack Legal Research, covering Commonwealth Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Department of Transportation v. Herbert R. Imbt, Inc., 39 Cont. Cas. Fed. 76,548, 630 A.2d 550, 157 Pa. Commw. 573, 1993 Pa. Commw. LEXIS 515 (Pa. Ct. App. 1993).

Opinion

SMITH, Judge.

The Department of Transportation (DOT) and Herbert R. Imbt, Inc., by change of corporate name now known as HRI, Inc. (HRI) cross-petition for review of the May 7, 1992 decision of the Pennsylvania Board of Claims (Board) which determined that DOT breached a bridge construction contract with HRI and awarded $84,521.36 in damages. The issues presented in this consolidated appeal are whether the Board erred in awarding damages for anticipated profit and overhead for work that would have been performed under the contract; and whether the Board erred by deducting overhead recovered for work performed beyond the expiration of the contract from unabsorbed overhead for work performed during the original contract period, and in not awarding damages for idled equipment placed on standby due to DOT’s breach of contract. 1

I.

On June 5, 1986, HRI and DOT entered into a highway bridge construction contract. After HRI commenced con *577 struction activities, the United States Army Corps of Engineers (Corps) issued an order demanding that DOT and HRI cease filling operations on the site in Centre County as it violated the Clean Water Act, 33 U.S.C. §§ 1344-1387. DOT confirmed the cessation of most operations on the project by letter to HRI and stated that the anticipated length of delay was to be six to eight weeks, and that HRI should remove all construction equipment from the site. DOT applied to the Corps for a wetlands permit which was denied on May 12, 1987. After the United States Environmental Protection Agency advised DOT that any disturbed wetlands had to be remediated or restored to their original condition, DOT directed HRI to begin restoration work. On May 24, 1988, DOT issued an acceptance certificate indicating completion of the work.

Subsequently, HRI filed a statement of claim with the Board seeking $402,527.49 in damages for overhead, profit, standby equipment, and bond and railroad insurance. After a hearing, the Board found:

9. In designing the Mt. Eagle Bridge Project, [DOT] and/or its representatives and agents were aware that compliance with the Federal Clean Water Act would be necessary and that the general locale of the project included areas which were wetlands under the Act. The [DOT] intended to design the alignment of the project so as to avoid wetlands; however, by virtue of an error in identifying wetlands, the Department placed the alignment of the project within a wetland area.
13. Prior to accepting the bids for the contract, representatives of [DOT] were aware that a Wetlands Permit would be necessary for the performance of the contract work.
14. [DOT] did not advise HRI or the other bidders, prior to the bid opening, that a Section 404 Wetlands Permit from the Corps might be required.

Board Decision, pp. 4-5. The Board also found that it was DOT’s responsibility to obtain the permit; the contract work *578 could not be performed without the permit; DOT warranted that the right-of-way would be provided; and DOT’s actions in awarding the contract and issuing a notice to proceed was a positive misrepresentation.

The Board concluded that DOT breached its contractual relations with HRI by misrepresenting the nature of the project, by failing to provide adequate plans and specifications to resolve the wetlands issue to obtain a permit, and by failing to obtain a proper right-of-way. The Board stated that HRI was not able to recover the overhead and profit it anticipated for the original contract work and awarded HRI $84,521.36 in damages, refusing HRI’s request for compensation for standby equipment. 2

II.

DOT’s claim that it did not anticipate a need for the wetlands permit is clearly not supported by the record. The parties stipulated that prior to accepting bids on this project, an environmental evaluation was prepared which indicated that a consent agreement and wetlands permit will be obtained from the Corps, and that DOT received a letter from the Centre County Conservation District concerning the project which indicated that it appears to disturb wetlands and may require a permit. In C.J. Langenfelder & Son, Inc. v. Department of Transportation, 44 Pa.Commonwealth Ct. 585, 404 A.2d 745 (1979), this Court affirmed the Board’s holding that DOT was liable for damages resulting from a delay caused by its failure to secure a permit from the Corps for *579 dredging a marsh as part of a project to build 13,205 feet of highway and bridge because DOT’s actions constituted a breach of contract as it amounted to a denial of access to the job site.

Further, DOT does not contest the Board’s finding that the contract work could not be performed without the permit and has cited no authority to support the argument that it should be relieved of its obligation to provide access to the job site because the Corps failed to issue the permit. Since it was DOT’s responsibility to obtain the permit, the contract did not provide any exceptions to the requirement that DOT secure all necessary rights-of-way as contained in Section 107.18 of the Publication 408 Specifications (1983) (Specifications), and the permit was essential to the contract, DOT breached the contract by failing to obtain the permit and is therefore liable for damages.

This Court has recognized that the victim of a breach of contract is entitled to damages for the net amount of losses caused and gains prevented by the breach to the extent that the evidence affords a sufficient basis for estimating the amount with reasonable certainty. C.J. Langenfelder; Department of Highways v. S.J. Groves & Sons, Co., 20 Pa.Commonwealth Ct. 526, 343 A.2d 72 (1975). In Coatesville Contractors & Engineers, Inc. v. Borough of Ridley Park, 509 Pa. 553, 506 A.2d 862 (1986), a contractor was denied full access to a construction site due to the owner’s failure to drain a lake as provided in the contract documents. After the work was completed, the contractor sought additional money for extra work caused by owner’s failure to provide full access to the site. The owner attempted to avoid payment on the basis of several exculpatory clauses. However, the Pennsylvania Supreme Court held that exculpatory provisions in a contract cannot be raised as a defense where there is an affirmative or positive interference by the owner with the contractor’s work, or there is a failure on the part of the owner to act in some essential matter necessary to performance of the work.

*580

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gibraltar Rock, Inc. v. PA DEP
Commonwealth Court of Pennsylvania, 2024
J.R. Piccirilli v. The Bureau of Unclaimed Property
Commonwealth Court of Pennsylvania, 2021
Balshy v. Pennsylvania State Police
988 A.2d 813 (Commonwealth Court of Pennsylvania, 2010)
A. G. Cullen Construction, Inc. v. State System of Higher Education
898 A.2d 1145 (Commonwealth Court of Pennsylvania, 2006)
Darien Capital Management, Inc. v. Public School Employes' Retirement System
668 A.2d 210 (Commonwealth Court of Pennsylvania, 1995)
Green Construction Co. v. Department of Transportation
643 A.2d 1129 (Commonwealth Court of Pennsylvania, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
39 Cont. Cas. Fed. 76,548, 630 A.2d 550, 157 Pa. Commw. 573, 1993 Pa. Commw. LEXIS 515, Counsel Stack Legal Research, https://law.counselstack.com/opinion/department-of-transportation-v-herbert-r-imbt-inc-pacommwct-1993.