XL Specialty Insurance v. Massachusetts Highway Department

31 Mass. L. Rptr. 147
CourtMassachusetts Superior Court
DecidedJanuary 3, 2013
DocketNo. SUCV200804093
StatusPublished

This text of 31 Mass. L. Rptr. 147 (XL Specialty Insurance v. Massachusetts Highway Department) is published on Counsel Stack Legal Research, covering Massachusetts Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
XL Specialty Insurance v. Massachusetts Highway Department, 31 Mass. L. Rptr. 147 (Mass. Ct. App. 2013).

Opinion

Billings, Thomas P., J.

For want of a nail the shoe was lost; For want of a shoe the horse was lost; For want of a horse the battle was lost; For the failure of battle the kingdom was lost —-All for the want of a horse-shoe nail.1

Disregard of seemingly small details can have costly consequences. At issue in this case is whether, and in what amount, the plaintiff {“XL”), as surely and sub-rogee of general contractor Roads Corporation (“Roads”), may recover damages incurred as a result of a two-year delay in a roadway reconstruction and bridge replacement project at Winter Street, Waltham. The delay resulted from MassHighway’s failure to arrange and accomplish certain utility relocation work that it knew needed to happen before Roads could begin construction. After it mobilized and while it was still waiting for the utilities, Roads failed. XL stepped into its shoes, ultimately completing the project successfully with another contractor, but at significant cost.

XL seeks compensation over and above the contract price, in the amount of $5,215,513. It is entitled to most of this amount, but not all. For the reasons that follow, judgment is to enter in favor of XL, in the principal amount of $3,853,453.

FINDINGS OF FACT

The case was tried to me, jury-waived, over nine days between September 5 and September 17, 2012. There were ten witnesses and 727 exhibits. Based on the credible evidence and the reasonable inferences therefrom, I find the following facts.2

A. The Parties.

1. XL is a Delaware corporation licensed to issue construction contract surety bonds in Massachusetts. It issued both performance and payment bonds on behalf of Roads for the project in question.

2. Until 2009, the entity responsible for administering most public road and bridge construction projects in Massachusetts was known as the Massachusetts Highway Department (“MassHighway”). On November 1, 2009, pursuant to G.L.c. 6C, MassHighway and several other agencies were integrated into the Massachusetts Department of Transportation (“MassDOT”).

3. MassDOT is a department of the Commonwealth, organized and existing pursuant to G.L.c. 16, §1. It is, as MassHighway was, headquartered in the Transportation Building at Ten Park Plaza, Boston and has various district offices throughout the Commonwealth. The project at issue in this case fell within the jurisdiction of the District 4 office, located at 519 Appleton Street, Arlington.

B. The Winter Street Project and Contract.

4. In late summer 2004, MassHighway solicited bids for the construction of a project called “Roadway Reconstruction and Bridge Replacement (W-04-025) on Winter Street at Interstate 95, Federal Aid project No. BR-001S(072)” (the “Winter Street project”). The project was to replace a four-lane bridge carrying Winter Street, Waltham over Interstate 95 with a new, seven-lane bridge, and to construct a new collector/distributor roadway at the interchange for 1-95 northbound. Because the bridge was critical to both vehicular traffic over it3 and utility lines that had, over the years, been installed under it, all understood that the work must be completed without interruption to either, as further described below.

5. The project was initially proposed by the Ciiy of Waltham..The City retained Rizzo Associates to develop the design in tandem with a structural engineering firm, Edwards and Kelcey. The design work began in August 1999.

6. At some later date, the project was approved for state funding and ultimately, for federal-funding, with an 80/20 federal/state funding ratio.

7. MassHighway and the City formalized their relationship for the project’s actual construction in a “City/Town Agreement” dated December 2004. (Ex. 12.) Under the agreement, MassHighway agreed to put the project out to bid; to construct, oversee and administer it; and to participate in its cost up to a 10% overrun; the City agreed to pay anything over this. Rizzo would do the design, with the Ciiy taking respon[149]*149sibility for any costs caused by errors in the plans or by extras ordered by the City.

8. Subject to the requirements of the public works procurement law {Chapter 30 of the General Laws), MassDOT was in sole control of the procurement process, including the bid solicitation, the award and execution of a contract, and the issuance of a Notice to Proceed.

9. MassHighway advertised the project on or about June 26, 2004. Sealed bids were opened on or about September 21, 2004.

10. There were several bidders, whose bids were relatively close in price. Roads was deemed the lowest responsible bidder and was awarded the contract on or about November 23, 2004.

11. Upon notice of the award, Roads was required to execute a contract within 14 days, on pain of forfeiting 5% of the bid amount (about $950,000). Roads and MassHighway executed the contract on or about December 1, 2004. The contract price was $19,055,914.

12. The contract specified the construction sequence and required that the construction proceed in several phases. In its simplest form, the schedule was as follows:

a. In Phase I, a new two-lane bridge would be constructed abutting, and immediately to the north of, the existing four-lane bridge. Just to the north of and abutting the new bridge, a temporary two-lane bridge (known in the trade as a “Bailey” bridge) would be constructed.
b. In Phase II, the existing four-lane bridge would be demolished and replaced with a new structure wide enough to handle five lanes of traffic. Vehicular traffic would be diverted to the structures erected in Phase I during the Phase II work.
c. The Bailey bridge would then come down, and what was left—all new construction—would carry four lanes eastbound and three lanes westbound.

13. The contract (Ex. 1A, six pages from the end, at Clause 2, last sentence) specifically incorporated MassHighway’s Standard Specifications for Highways and Bridges—long known as the “Blue Book”4—of which the 1995 edition (Ex. IB) and the 2002 supplement (Ex. 1C) constituted the then-current version. The Standard Specifications included the following provisions (among many others).

14. The project’s Engineer was to be “[t]he Chief Engineer of the Department acting directly or through an authorized representative, such representative acting within the scope of the particular duties entrusted to him/her.” (Ex. 1C, sec. 1.19.) Under section 5.01,

The Engineer shall decide all questions which may arise as to the interpretation of the plans and specifications, and the Engineer may alter, adjust and approve same when necessary; all questions which may arise as to the quality, quantity, value and acceptability of materials furnished or to be furnished and work performed or to be performed; all questions which may arise as to the progress of the work and need for and manner of correcting same; and also the need for and terms of delays and suspensions; all questions relating to the need for and terms of extra work; all questions relating to the supervision, control and direction of all work on the site and the use thereof; [and] all questions as to the acceptable fulfillment of the Contract on the part of the Contractor.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Utah Construction & Mining Co.
384 U.S. 394 (Supreme Court, 1966)
L. L. Hall Construction Company v. The United States
379 F.2d 559 (Court of Claims, 1966)
Grant Construction Co. v. Burns
443 P.2d 1005 (Idaho Supreme Court, 1968)
Glynn v. City of Gloucester
487 N.E.2d 230 (Massachusetts Appeals Court, 1986)
Wes-Julian Construction Corp. v. Commonwealth
223 N.E.2d 72 (Massachusetts Supreme Judicial Court, 1967)
St. Germain & Son, Inc. v. Taunton Redevelopment Authority
340 N.E.2d 916 (Massachusetts Appeals Court, 1976)
Glynn v. City of Gloucester
401 N.E.2d 886 (Massachusetts Appeals Court, 1980)
Ted's Master Service, Inc. v. FARINA BROS. CO. INC.
178 N.E.2d 268 (Massachusetts Supreme Judicial Court, 1961)
Agoos Leather Companies, Inc. v. American & Foreign Insurance
174 N.E.2d 652 (Massachusetts Supreme Judicial Court, 1961)
Save the Bay, Inc. v. Department of Public Utilities
322 N.E.2d 742 (Massachusetts Supreme Judicial Court, 1975)
Reynolds Bros., Inc. v. Commonwealth
586 N.E.2d 977 (Massachusetts Supreme Judicial Court, 1992)
Commonwealth v. S. J. Groves & Sons Co.
343 A.2d 72 (Commonwealth Court of Pennsylvania, 1975)
Blanchard v. Inhabitants of Blackstone
102 Mass. 343 (Massachusetts Supreme Judicial Court, 1869)
Zarthar v. Saliba
185 N.E. 367 (Massachusetts Supreme Judicial Court, 1933)
Charles I. Hosmer, Inc. v. Commonwealth
19 N.E.2d 800 (Massachusetts Supreme Judicial Court, 1939)
Morgan v. Town of Burlington
55 N.E.2d 758 (Massachusetts Supreme Judicial Court, 1944)
Farina Bros. v. Commonwealth
257 N.E.2d 450 (Massachusetts Supreme Judicial Court, 1970)
Sutton Corp. v. Metropolitan District Commission
667 N.E.2d 838 (Massachusetts Supreme Judicial Court, 1996)
Skopek Bros. v. Webster Housing Authority
416 N.E.2d 1006 (Massachusetts Appeals Court, 1981)