Reynolds Bros., Inc. v. Commonwealth

586 N.E.2d 977, 412 Mass. 1, 1992 Mass. LEXIS 59
CourtMassachusetts Supreme Judicial Court
DecidedFebruary 24, 1992
StatusPublished
Cited by8 cases

This text of 586 N.E.2d 977 (Reynolds Bros., Inc. v. Commonwealth) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Reynolds Bros., Inc. v. Commonwealth, 586 N.E.2d 977, 412 Mass. 1, 1992 Mass. LEXIS 59 (Mass. 1992).

Opinion

O’Connor, J.

The plaintiffs appeal from an entry of summary judgment in favor of the Commonwealth on Count I of the complaint. 3 The plaintiffs, to whom we shall collectively refer as Reynolds, allege that they are entitled to recover for various delays, hindrances, and interferences in the performance of a contract between themselves and the Commonwealth, acting through its Department of Public Works (department). The contract involves the reconstruction of sidewalks and streets at eleven locations known generally as Downtown Crossing. Reynolds asserts a right to recover not only for losses caused by delays, but also for loss of productivity due to the department’s changing of the work schedule, the department’s denying Reynolds access to the job site, and the discovery of unanticipated subsurface conditions. We affirm the judgment entered in the Superior Court.

In ruling on the summary judgment motion, the judge appears to have relied on two department audit reports submitted by the Commonwealth in support of the motion and on an affidavit of William P. Reynolds, president of the plaintiff corporations at the relevant period, which was submitted in opposition to the motion. No one contests, and therefore we assume, the appropriateness of those documents to establish the facts of the case for summary judgment purposes. Based on those documents, the following facts appear not to be in dispute. By letter dated July 13, 1978, Reynolds was notified *3 as follows: “At a meeting of,the Public Works Commission held on July 12, 1978, the contract for Transit and Traffic Improvement Program in the City of Boston was awarded to you. Subject to the concurrence of the Federal Highway Administration.” The contract, only selected parts of which have been included in the record appendix, contains a timetable for work to be performed at eleven locations in downtown Boston. It provides that a large portion of the work should be completed by September 4, 1978, in order to accommodate bus traffic, and that approximately seventy-two per cent should be completed by October 10, 1978, in order to accommodate Christmas shoppers.

The contract also provides that “in general, all work may begin upon award of contract unless otherwise provided herein.” Reynolds planned to start work within five days after notice of the contract award but did not do so. Because the project involved Federal aid, the department required project approval from the Federal Highway Administration, which it received by letter dated July 21, 1978. The executed contract was not delivered to Reynolds until August 7, 1978, and Reynolds did not begin work until August 14. At that time, the department created several priority areas and delayed work in other areas, which in effect rearranged Reynolds’s work schedule. Reynolds’s schedule was also disrupted by the work of two other contractors working in areas where it was difficult for more than one contractor to work at one time. Although the contract specified June 30, 1979, as a completion date for the whole project, the actual completion date was one year later.

In August, 1978, Reynolds notified the department of its claim for delay and disruption damages, which was denied in 1981 by the department claims committee. Reynolds filed an amended claim on January 25, 1983, claiming damages of $154,053. While an appeal was pending before the board of contract appeals, Reynolds began this action in the Superior Court. The amended complaint essentially asserts in Count I that “[bjased upon the contract documents, the Plaintiffs planned their work in a specific sequence in order to obtain *4 the maximum productivity for their men and equipment. The Plaintiffs were unable to perform their work in accordance with the planned schedule because the Defendant prevented the Plaintiffs from commencing the work in a timely fashion and because the Defendant imposed a substantial change in the contract schedule.” In addition, the amended complaint alleged that Reynolds’s performance was delayed to their detriment by the work of other contractors.

The contract contains in § 8.05 a “no damages for delay” provision that says in relevant part: “The Contractor hereby agrees that he shall have no claim for damages of any kind on account of any delay in commencement of the work or any delay or suspension of any portion thereof, except as hereinafter provided.

“Provided, however, that if the [Public Works] Commission in [its] judgment shall determine that the performance of all or any major portion of the work is suspended, delayed, or interrupted for an unreasonable period of time by an act of the Department in the administration of the Contract, or by the Department’s failure to act as required by the Contract within the time specified in the Contract (or if no time is specified, within a reasonable time), and without the fault or negligence of the Contractor, an adjustment shall be made by the Department for any increase in the actual cost of performance of the Contract (excluding profit and overhead) necessarily caused by the period of such suspension, delay, or interruption. No adjustment shall be made if the performance by the Contractor would have been prevented by other causes even if the work had not been so suspended, delayed, or interrupted by the Department.”

General Laws c. 30, § 390 (1990 ed.), requires certain public contracts, including the contract involved in this case, to contain the following provision: “(a) The awarding authority may order, the general contractor in writing to suspend, delay, or interrupt all or any part of the work for such period of time as it may determine to be appropriate for the convenience of the awarding authority; provided however, that if there is a suspension, delay or interruption for fifteen days or *5 more or due to a failure of the awarding authority to act within the time specified in this contract, the awarding authority shall make an adjustment in the contract price for any increase in the cost of performance of this contract but shall not include any profit to the general contractor on such increase; and provided further, that the awarding authority shall not make any adjustment in the contract price under this provision for any suspension, delay, interruption or failure to act to the extent that such is due to any cause for which this contract provides for an equitable adjustment of the contract price under any other contract provisions.”

It is unclear from the record whether the provision required by c. 30, § 390, was expressly set forth in the contract but, in any event, the statute makes clear that the contract must be read as containing that provision. Also, to the extent there may be conflict between the expressed contract and the statutorily required provision, the required provision controls. Neither party contends otherwise.

Reynolds’s primary argument is that, despite the contract provision that, “in general, all work may begin upon award of contract unless otherwise provided herein,” the department failed to issue to Reynolds a formal “notice to proceed” until nearly one month after Reynolds had been notified that the contract had been awarded to them. The result, Reynolds says, was that Reynolds could not begin work as soon as planned, and was therefore forced to reschedule the work in a much less cost-efficient sequence.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

XL Specialty Insurance v. Massachusetts Highway Department
31 Mass. L. Rptr. 147 (Massachusetts Superior Court, 2013)
Mecca Construction Corp. v. All Interiors, Inc.
26 Mass. L. Rptr. 197 (Massachusetts Superior Court, 2009)
Fennelly v. Kimball Court Apartments Ltd. Partnership
14 Mass. L. Rptr. 37 (Massachusetts Superior Court, 2001)
JRJ Construction Co. v. R.W. Granger & Sons, Inc.
10 Mass. L. Rptr. 385 (Massachusetts Superior Court, 1999)
TLT Construction Corp. v. Anthony Tappe & Associates, Inc.
6 Mass. L. Rptr. 202 (Massachusetts Superior Court, 1996)
Bonacorso Construction Corp. v. Commonwealth
668 N.E.2d 366 (Massachusetts Appeals Court, 1996)
Sutton Corp. v. Metropolitan District Commission
667 N.E.2d 838 (Massachusetts Supreme Judicial Court, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
586 N.E.2d 977, 412 Mass. 1, 1992 Mass. LEXIS 59, Counsel Stack Legal Research, https://law.counselstack.com/opinion/reynolds-bros-inc-v-commonwealth-mass-1992.