JRJ Construction Co. v. R.W. Granger & Sons, Inc.

10 Mass. L. Rptr. 385
CourtMassachusetts Superior Court
DecidedJuly 29, 1999
DocketNo. 972194
StatusPublished

This text of 10 Mass. L. Rptr. 385 (JRJ Construction Co. v. R.W. Granger & Sons, Inc.) is published on Counsel Stack Legal Research, covering Massachusetts Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
JRJ Construction Co. v. R.W. Granger & Sons, Inc., 10 Mass. L. Rptr. 385 (Mass. Ct. App. 1999).

Opinion

Kottmyer, J.

I. INTRODUCTION

This action arises out of a public construction contract entered into between defendant R.W. Granger & Sons, Inc. (“Granger”) and defendant town of Franklin (“Franklin”). The contract involves the construction of the Franklin Elementary & Middle School in Franklin, Massachusetts. Granger, as the general contractor, entered into a subcontract with plaintiff JRJ Construction Co., Inc. (“JRJ”), pursuant to which JRJ agreed to perform the veneer plaster work at the school. Defendant United States Fidelity & Guaranly (“USF&G”) acted as Granger’s surety, and defendant Drummey, Rosane & Anderson, Inc. (“DRA”) was the architect on the project. JRJ has filed several claims against the defendants, asserting that they directed JRJ to perform work that was not required under the contract, which resulted in extra labor and costs. JRJ has filed ten claims against Granger for breach of contract (Counts I, III-VI, IX), misrepresentation (Count II), deceit by silence (Count VIII), negligence (Count X), and violations of G.L.c. 93A (Count XIII). JRJ has filed two claims against DRA for making bad faith decisions (Count VII), and for violations of G.L.c. 93A (Count XIII). Three claims have been filed against Franklin by JRJ for unjust enrichment (Counts XI & XV), and violations of c. 93A (Count XIII). And three claims have been filed against USF&G by JRJ for default on payment and performance bonds (Count XII), violations of G.L.c. 93A (CountXIII), and damages in excess of the penal sum (Count XIV).

Granger filed cross claims against Franklin for breach of contract (Count I) and indemnification (Count II). USF&G also filed cross claims against Franklin for indemnification (Counts I & II), and DRA filed a counterclaim against JRJ for breach of contract (Count I).

Granger and USF&G have moved for partial summary judgment, arguing that JRJ released them from most, if not all, of the contested work. DRA also filed a motion for summary judgment, arguing: (1) that DRA had no duty to JRJ because the contract documents obligated DRA only to consider requests of the general contractor (Granger), and it is undisputed that Granger never requested the payments that JRJ seeks in this case; (2) that JRJ waived its claims against DRA by signing a release; (3) that JRJ failed to provide timely written notice of its claims; (4) that JRJ’s claims against DRA are barred by the economic loss doctrine; and (5) that JRJ’s 93A claim fails because DRA did not engage in conduct that is actionable under c. 93A, nor did it engage in trade or commerce as required under c. 93A.2 JRJ has filed oppositions to both motions, and Granger filed a partial opposition to DRA’s motion.

Because the original summary judgment record was so confused as to preclude meaningful review, the Court issued an order dated February 1, 1999 to Granger and JRJ requiring, inter alia, that they document, by affidavit and otherwise, timely compliance with the notice provisions under the contract for each claim for which recovery is sought. Granger and JRJ responded to the Court’s order by supplying summaries with supporting materials. In addition, Granger filed a renewed motion for partial summary judgment, which again relies primarily on the doctrine of release, but makes three additional arguments. The additional arguments are as follows: that several of JRJ’s claims [387]*387are barred by a “no damages for delay” clause under the contract, that several of JRJ’s claims have been accounted for, and that JRJ failed to give timely written notice on certain claims.

II. SUMMARY JUDGMENT RECORD

The material facts, as taken from the summary judgment record and viewed in the light most favorable to JRJ, are as follows. On October 1, 1994, Granger entered into a public construction contract with the town of Franklin for the construction of the Franklin Elementary and Middle School, in Franklin, Massachusetts. (See General Contract between Granger and the town of Franklin (“General Contract”)). On October 3, 1994, Granger, as the general contractor, entered into a subcontract with JRJ, which provided that JRJ would perform the veneer plaster work for the project for the sum of $328,900. (See Subcontract between Granger and JRJ (“Subcontract”)). DRA, the architect on the project, prepared the specifications and plans on the project. (See id.). DRA also served as Franklin’s representative and was responsible for administering the construction contract. (See General Contract, Article 4.2.1.)

A.Disputed Work

During construction, JRJ performed certain work that it considered to be outside the scope of the contract documents. (See Statement of Factual and Legal Issues of JRJ in Opposition to Granger and USF&G’s Motion for Partial Summary Judgment. (Aff. of Joseph Schena, Ex. 8 (“Schena Aff. I”), par. 3.) This work generally falls into two categories: (1) work that was directed by Granger, which JRJ considered to be the responsibility of other subcontractors, or outside the scope of its responsibility under the contract, and (2) work resulting from DRA changes, drawing revisions, and interpretations. (See JRJ’s Memorandum in Opposition to Granger and USF&G’s Renewed Motion for Partial Summary Judgment (“JRJ Opposition to Granger and USF&G Motion II”), Exhibits 1-53 and Aff. of Joseph Schena (“Schena Aff. II”).)

With regard to this disputed work, JRJ submitted requests for extra work change orders to Granger, and JRJ was told that these requests were sent to DRA. (See Schena Aff. II, pars. 4-5.) Under the general contract, a “change order” is defined as:

a written instrument prepared by the Architect and signed by the Owner, Contractor and Architect, stating their agreement upon all of the following:
. 1 a change in the Work,
.2 the amount of the adjustment in the Contract Sum, if any; and
.3 the extent of the adjustment in Contract Time, if any.

(General Contract, Article 7.2.1.) DRA and Granger directed JRJ to perform the disputed work, and to invoice the work upon completion. (See Schena Aff. II, par. 7.) DRA and Granger also told JRJ that the disputed work would be resolved by arbitration or litigation. (See id., par. 8.)

Towards the end of the project, Granger informed JRJ that it did not have all of the extra work claims from JRJ. (See id., par. 10.) On October 11, 1996, JRJ sent a letter to Granger referencing over fifty unpaid invoices and proposals for work on the project. (See Granger and USF&G’s Renewed Motion for Partial Summary Judgment, Aff. of Timothy O’Neil, Ex. II (“O’Neil Aff. II”), par. 4 and Ex. L.) The letter stated that Granger owed $276,320.31 to JRJ for work incurred on the project. (See id.) JRJ sent Granger copies of JRJ’s claims on November 26, 1996. (See Schena Aff. II, par. 10.)

B.Releases

During the course of JRJ’s work on the project, JRJ submitted requisitions for payment and Granger made payments. (See Granger and USF&G’s Renewed Motion for Partial Summary Judgment (“Granger and USF&G’s Renewed Motion”), Aff. of Tim O’Neil, Ex. I (“O’Neil Aff I”), par. 5.) As part of the regular requisition process, subcontractors, including JRJ, were required to execute partial waiver and release forms (“releases”) when they were paid for their work. (See id., par. 6.) During the course of the project, JRJ executed a number of releases. (See id., par.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Utah Construction & Mining Co.
384 U.S. 394 (Supreme Court, 1966)
Glynn v. City of Gloucester
487 N.E.2d 230 (Massachusetts Appeals Court, 1986)
Lawrence-Lynch Corp. v. Department of Environmental Management
467 N.E.2d 838 (Massachusetts Supreme Judicial Court, 1984)
Pederson v. Time, Inc.
532 N.E.2d 1211 (Massachusetts Supreme Judicial Court, 1989)
LaLonde v. Eissner
539 N.E.2d 538 (Massachusetts Supreme Judicial Court, 1989)
Schuster v. Baskin
236 N.E.2d 205 (Massachusetts Supreme Judicial Court, 1968)
Community National Bank v. Dawes
340 N.E.2d 877 (Massachusetts Supreme Judicial Court, 1976)
Kourouvacilis v. General Motors Corp.
575 N.E.2d 734 (Massachusetts Supreme Judicial Court, 1991)
Flesner v. Technical Communications Corp.
575 N.E.2d 1107 (Massachusetts Supreme Judicial Court, 1991)
Cassesso v. Commissioner of Correction
456 N.E.2d 1123 (Massachusetts Supreme Judicial Court, 1983)
Glynn v. City of Gloucester
401 N.E.2d 886 (Massachusetts Appeals Court, 1980)
Reynolds Bros., Inc. v. Commonwealth
586 N.E.2d 977 (Massachusetts Supreme Judicial Court, 1992)
First Enterprises, Ltd. v. Cooper
425 Mass. 344 (Massachusetts Supreme Judicial Court, 1997)
Clark v. Rowe
701 N.E.2d 624 (Massachusetts Supreme Judicial Court, 1998)
B. J. Harland Electrical Co. v. Granger Bros.
510 N.E.2d 765 (Massachusetts Appeals Court, 1987)
Nota Construction Corp. v. Keyes Associates, Inc.
694 N.E.2d 401 (Massachusetts Appeals Court, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
10 Mass. L. Rptr. 385, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jrj-construction-co-v-rw-granger-sons-inc-masssuperct-1999.