TLT Construction Corp. v. Anthony Tappe & Associates, Inc.

6 Mass. L. Rptr. 202
CourtMassachusetts Superior Court
DecidedNovember 15, 1996
DocketNo. 951049C
StatusPublished
Cited by1 cases

This text of 6 Mass. L. Rptr. 202 (TLT Construction Corp. v. Anthony Tappe & Associates, Inc.) is published on Counsel Stack Legal Research, covering Massachusetts Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
TLT Construction Corp. v. Anthony Tappe & Associates, Inc., 6 Mass. L. Rptr. 202 (Mass. Ct. App. 1996).

Opinion

Cratsley, J.

INTRODUCTION

The defendants, A. Anthony Tappe and Associates, Inc. (“Tappe”), Jeffrey M. Hoover, Keith Hoffses, and A. Anthony Tappe as an architectural firm and individual architects, bring these motions against plaintiff, TLT Construction Corp. (“TLT") for summary judgment. See Massachusetts Rules of Civil Procedure, Rule 56(b). Defendants, have moved for summary judgment of all “delay” claims asserted by the plaintiff in their Motion for Partial Summary Judgment and of all remaining claims in their Supplemental Motion for Summary Judgment (“motions”).

Plaintiffs action arises from a construction project on the Beverly Library in which defendants acted as the project architect and plaintiff as the general contractor. TLT brought the current action against Tappe alleging negligent misrepresentation, interference with contractual relations, tort (including intentional & negligent misrepresentation, fraud, deceit, and defamation), interference with advantageous business relations, and violations of Mass. Gen. L. ch. 93A. Defendants argue through their motions that summary judgment should be granted for one or all of three reasons; (1) TLT’s contract with the City of Beverly (“City”) contained a “no damages for delay” clause, (2) arbitration between the City and TLT bars the claims and/or issues resolved in that proceeding from being litigated again, and (3) the economic loss doctrine prohibits TLT from recovering for purely economic damages.

Before this Court are two motions for summary judgment which would dismiss all claims alleged by TLT against Tappe. For the reasons discussed below, defendants’ motions for summary judgment are ALLOWED.

BACKGROUND

The following information, in pertinent part, was presented to this Court in materials appropriate for consideration on motions for summary judgment:

I. Contractual Provisions

Tappe entered into an agreement titled “Standard Form of Agreement Between Owner and Architect” (“Architect Contract”) for the architectural design and supervision of renovations and additions to the City of Beverly Public Libraiy (“Project”). (The American Institute of Architects 1987 Edition of document B141; Kostinden Aff. at par. 3.) TLT entered into an agreement entitled “General Conditions of the Contract for [203]*203Construction” (“Construction Contract”) for construction of the Project. (The American Institute of Architects 1976 Edition of document A201; Kostinden Aff. at par. 4.) The Construction Contract contained the flowing provision:

The Architect will be the Owner’s representative during construction and until final payment is due. The Architect will advise and consult with the Owner. The Owner’s instructions to the Contractor shall be forwarded through the Architect. The Architect will have authority to act on behalf of the Owner only to the extent provided in the Contract Documents, unless otherwise modified by written instrument in accordance with Subparagraph 2.2.18.

(Construction Contract at pg.5-6, par. 2.2.2.)

Additionally there were supplementary conditions to the Construction Contract incorporating Mass. Gen. L. ch. 30, §390. Paragraph 1.2 of the Supplementary Conditions, Part II, provides:

Except as otherwise provided by law and by this Paragraph 1.2, the Contractor shall not be entitled to damages on account of any hindrances or delays, avoidable or unavoidable; but if such delay be occasioned by the awarding authority, the Contractor may be entitled to an extension of time only, in which to complete the work, to be determined by the Architect.
(a) The awarding authority may order the Contractor in writing to suspend, delay or interrupt all or any part of the work for such period of time as it may determine to be appropriate for the convenience of the awarding authority; provided, however, that if there is a suspension, delay or interruption for fifteen days or more or due to a failure of the awarding authority to act within the time specified in this contract, the awarding authority shall make an adjustment in the contract price for any increase in the cost of performance of this contract but shall not include any profit to the Contractor on such increase; and provided further, that the awarding authority shall not make any adjustment in the contract price under this provision for any suspension, delay, interruption or failure to act to the extent that such is due to any cause for which this contract provides for an equitable adjustment of the contract price under any other contract provisions.

(Supplementary Conditions atpg. SCII-5, par. 1.2(a).)

II. Allegations by TLT against Tappe

Pursuant to the current action, TLT has made the following allegations against Tappe:

Tappe was the architect for the Project, designed all the plans and specifications for the project including but not limited to the architectural elevations, structural steel, and other incidental drawings and also acted as the administrator of the project. (Kostinden Aff. at par. 5.) Tappe represented to TLT and TLT’s subcontractors that the architectural drawings for the project were proper. (Kostinden Aff. at par. 7.) In accordance with the contract requirements, Tappe was suppose to review the structural steel drawings, but they refused to do so in a timely fashion pursuant to the contract requirements. (Kostinden Aff. at par. 8.) Tappe sent the drawings back to TLT, refusing to review them. (Kostinden Aff. at par. 8.) Tappe made substantial modifications adding additional steel. (Kostinden Aff. at par. 9.) The architect refused to admit that there were errors in the drawings and refused to issue a written stop work order. (Kostinden Aff. at par. 10.) Tappe added steel at a substantial cost to the steel fabricator and TLT. (Kostinden Aff. at par. 10.) There was a delay of approximately 114 days due to the flaws in the structural steel design. (Kostinden Aff. at par. 11.) Tappe did not adhere to the contractually specified submittal schedule resulting in approximately 74 submittals exceeding the 21 days allowed for review of shop drawing submittals. (Kostinden Aff. at par. 13, 14.) Tappe did not give any time extensions for this protracted review of TLT’s submittals. (Kostinden Aff. at par. 15.) 84 days elapsed from the contractually required 15 days in preparing the room finish schedule. (Kostinden Aff. at par. 17.) Tappe issued various change orders to correct discrepancies and omissions in his drawings and specifications at times which substantially disrupted TLT’s work and its subcontractors work. (Kostinden Aff. at par. 18.) The contract plans were deficient in providing for insulation of duct work in violation of the Massachusetts Building Code. (Kostinden Aff. at par. 19a.) Tappe issued a change order to correct this violation which most notably interrupted the drywall installation for 16 days. (Kostinden Aff. at par. 19a.) Even before the bidding, the mechanical engineer advised Tappe of this problem. (Kostinden Aff. at par. 19a.) Tappe made assurances to the Library Committee that no additional plaster work would be required in addition to the plaster work provided for in the architectural contract. (Kostinden Aff. at par. 19b.) At the end of the project Tappe requested additional plaster repairs which interrupted the painting subcontractor’s work and added some $23,000 in cost. (Kostinden Aff. at par.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cathey v. Fallon Clinic, Inc.
13 Mass. L. Rptr. 325 (Massachusetts Superior Court, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
6 Mass. L. Rptr. 202, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tlt-construction-corp-v-anthony-tappe-associates-inc-masssuperct-1996.