Black Top Paving Co. v. Commonwealth

466 A.2d 774, 77 Pa. Commw. 612, 1983 Pa. Commw. LEXIS 2028
CourtCommonwealth Court of Pennsylvania
DecidedOctober 19, 1983
DocketAppeal, No. 577 C.D. 1982
StatusPublished
Cited by9 cases

This text of 466 A.2d 774 (Black Top Paving Co. v. Commonwealth) is published on Counsel Stack Legal Research, covering Commonwealth Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Black Top Paving Co. v. Commonwealth, 466 A.2d 774, 77 Pa. Commw. 612, 1983 Pa. Commw. LEXIS 2028 (Pa. Ct. App. 1983).

Opinion

Opinion by

Judge Craig,

Black Top Paving Company appeals from an order by the Board of Claims (board) which dismissed the company’s claim against the Pennsylvania Department of Transportation (DOT) for $5,382.06, the amount withheld by DOT because of Black Top’s inability to meet compaction standards for the wearing (surface) course of an area, designated as Lot 1, under a contract to resurface a legislative route in Perry Township.

We must decide if, in interpreting the contract, the board committed an error of law1 by (1) holding Black Top to a minimum acceptable theoretical density compaction standard of ninety percent and by (2) concluding that neither constructive fraud nor a mutual mistake of fact existed to excuse Black Top from complying fully with DOT’s compaction requirements.

In June of 1977, Black Top and DOT entered into a contract for resurfacing 19,157 linear feet of existing roadway; the contract’s sketches and typical sections revealed that the roadway had widths varying from twenty to twenty-four feet between shoulders or between shoulders and existing curb.

Before DOT awarded the contract, Black Top’s vice-president, William Spencer, inspected the project site and observed that the highway was not uniformly at least twenty feet wide, and did not have two feet [614]*614of bituminous concrete base course widening on each side of the road, as he viewed the typical section drawings. Mr. Spencer did not bring these alleged discrepancies to DOT’s attention, however, believing that after the award of the contract but before the start of Black Top’s performance, DOT would perform work on the site so that road conditions conformed to the drawings. Hence, Black Top relied solely upon the drawings in preparing its bid.

Before Black Top commenced operations, DOT personnel placed cross drains at various locations along the project and removed unsuitable material from Lot 1, as well as from other portions of the roadway.

Sometime after commencement of the resurfacing project, Black Top constructed three control strips under DOT supervision for the purpose of establishing a standard against which DOT could measure compaction compliance in the field. Specifically, section 401.3(h) of the 1976 Form 408 Specifications (1976 specifications), incorporated by reference into the contract, called for construction of control strips “to obtain the maximum density attainable under the existing field conditions, and employ this target density value as the standard for measurement of compaction compliance for the work. ’ ’

Section 401.3(h) also provided that (1) upon completion of compaction, DOT would perform density tests at random locations to determine the average in-place density of the control strip, (2) the value of the average would serve as the reference density target for the course, and (3) the value “shall not be less than 92% of the theoretical maximum density2 [615]*615for the wearing course. ...” The contract also provided that if the 92% density target was not met, DOT’s engineer could “direct the use of more effective compaction procedures, or the redesign of the pavement mixture. ’ ’

DOT tested the control strips with a nuclear testing gauge; all three strips failed to meet the contract’s minimum acceptable theoretical density target of 92%. Black Top, however, achieved 91.8% of theoretical density in one control strip. Therefore, instead of directing the use of more effective compaction procedures or the redesign of the pavement mixture, as provided in section 401.3(h), DOT held Black Top to a 91.8% theoretical density target, which the company had shown it could produce under field conditions.

Upon completion of the project, several locations failed to meet the adjusted 91.8% target. According to the findings of fact, DOT then applied a conversion factor to all failed tests, reducing the acceptable degree of theoretical density to 90%, a reduction of 1.8%. The area designated as Lot 1 failed to meet this reduced standard. Accordingly, DOT adjusted the contract price, using the 90% density standard as the basis for measuring compliance.

Theoretical Density Standard

Finding that DOT held Black Top to the conversion standard, the board concluded that Black Top failed to prove DOT responsible for the contractor’s inability to compact Lot 1 to within 90% of theoretical density.

Black Top contends that it only agreed to have its compaction performance measured against a minimum theoretical density target of 92% and that the board therefore erred by holding Black Top to the [616]*61690% standard. Specifically, the company contends that the contract provides for only two remedies when a contractor fails to achieve the 92% target, the use of more effective compaction procedures or redesign of the pavement mixture, and that use of a different density standard by DOT was arbitrary and unreasonable. We disagree.

In their contract, the parties agreed that DOT could accept performance at less than contract specification standards, with a corresponding adjustment in compensation. Specifically, section 106.06(b) of the 1976 specifications provided:

(b) Restricted Performance Specifications
1. Acceptance or Rejection. Following the application of the appropriate acceptance plan, the decision of the engineer shall be final as to the acceptance, rejection, or acceptance at an adjusted price of sampled LOTS.
2. Disposition of LOTS. When practical to do so, LOTS not conforming to Specification requirements may be reworked and resubmitted for acceptance sampling. Non-conforming LOTS of materials, products, items of construction or completed construction that are not adaptable to correction by reworking shall be removed and replaced, accepted with payment, or accepted at an adjusted price as stated in the Specifications; or if not stated, as directed by the engineer. [Emphasis added.]

Apparently, the engineer decided that Lot 1 was not adaptable to correction by reworking and so, under the terms of section 106.06(b), waived the 92% threshold, lowered the minimum acceptable density target to 90%, and adjusted the price of the contract. Contractual provisions can be waived, expressly or impliedly. Chung v. Park, 377 F. Supp. 524, 529 (M.D. [617]*617Pa. 1974). Here the contract, by expressly authorizing adjustment, impliedly allowed DOT’S engineer to waive the 92% compaction requirement. This does not mean, however, that DOT waived all reasonable compaction standards. DOT’S decisions to forego the 92% target and the right of reconstruction did not extinguish its right to hold Black Top to a more lax theoretical density target of 90% and to adjust the contract price accordingly.

Constructive Fraud and Mutual Mistake

At least before the board, Black Top claimed that DOT had actual knowledge of unsuitable subsurface conditions and that failure to alert Black Top to such conditions amounted to constructive fraud.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Chester Community Charter School v. Com. of PA, Dept. of Ed
Commonwealth Court of Pennsylvania, 2024
BAIM v. DUKART
E.D. Pennsylvania, 2022
Electroplating Technologies Ltd. v. HH Sumco Inc.
11 Pa. D. & C.5th 160 (Lehigh County Court of Common Pleas, 2009)
McDermott v. Party City Corp.
11 F. Supp. 2d 612 (E.D. Pennsylvania, 1998)
Morningstar v. Department of Transportation
646 A.2d 666 (Commonwealth Court of Pennsylvania, 1994)
Commonwealth, Department of General Services v. Lhormer Real Estate Agency, Inc.
549 A.2d 1008 (Commonwealth Court of Pennsylvania, 1988)
Trumpp v. Trumpp
505 A.2d 601 (Supreme Court of Pennsylvania, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
466 A.2d 774, 77 Pa. Commw. 612, 1983 Pa. Commw. LEXIS 2028, Counsel Stack Legal Research, https://law.counselstack.com/opinion/black-top-paving-co-v-commonwealth-pacommwct-1983.