McNamara Construction of Manitoba, Ltd. v. United States

509 F.2d 1166, 20 Cont. Cas. Fed. 83,644, 206 Ct. Cl. 1, 1975 U.S. Ct. Cl. LEXIS 241
CourtUnited States Court of Claims
DecidedJanuary 22, 1975
DocketNo. 417-73
StatusPublished
Cited by28 cases

This text of 509 F.2d 1166 (McNamara Construction of Manitoba, Ltd. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McNamara Construction of Manitoba, Ltd. v. United States, 509 F.2d 1166, 20 Cont. Cas. Fed. 83,644, 206 Ct. Cl. 1, 1975 U.S. Ct. Cl. LEXIS 241 (cc 1975).

Opinions

Bennett, Judge,

delivered the opinion of the court:

By fixed-price contract dated June 30, 1964, plaintiff McNamara Construction of Manitoba, Ltd. (hereinafter McNamara) undertook to construct for the Army Corps of Engineers a canal lock and related structures (New Second Lock) at St. Mary’s Falls Canal, Sault Ste. Marie, Michigan.1 The original completion date of June 30,1967, was extended by a series of modifications to October 19,1968. The work was completed and accepted as of that latter date and the administrative claims under the contract have been settled.

[4]*4This claim arises out of unusually severe labor problems— strikes, delays, and harassment — which plagued McNamara throughout the performance of the contract and which resulted in additional labor (and labor-related) costs. The contracting officer freely granted plaintiff extensions of time for the delays resulting from those labor problems because the delays were not McNamara’s fault, but disclaimed any authority or obligation to make a financial adjustment.2 Plaintiff’s subsequent request to the Secretary of the Army for special, discretionary statutory relief pursuant to Public Law 85-804, 72 Stat. 972 (1958), 50 U.S.C. § 1431 et seq.,. was denied.

Plaintiff now seeks to recover those additional labor costs3 in this court on a theory of reformation of contract due to an alleged mutual mistake of fact. The mutual mistake of fact, states plaintiff, was that “neither the contractor nor the [Engineering] Corps was aware of or could possibly have anticipated the unreasonable and uncooperative attitude and conduct of the labor unions.” Plaintiff says both parties assumed labor would behave in a responsible fashion but they were mistaken in that assumption. As proof of the alleged mutual mistake, plaintiff notes that the Government’s estimate of the cost of the project, $22,189,692, was roughly equivalent to plaintiff’s bid of $21,471,690; yet, after accounting for modifications, the unanticipated labor costs swelled the ultimate cost of the project allegedly in excess of $6 million above those figures.

Plaintiff’s claim must fail. There was, simply, no mutual mistake of fact by the parties of the type for which judicial relief may be given. Both parties, at the time of executing the contract, were fully aware of the potential for labor difficulties. This awareness is reflected in clause 5 of the contract, which states in relevant part:

5. TERMINATION EOR DEFAULT — DAMAGES EOR DeLAV-Time Extensions
*_ * * # *
[5]*5(d) The Contractor’s right to proceed shall not be so terminated nor the Contractor charged with resulting damage if:
(1) The delay in the completion of the work arises from unforeseeable causes beyond the control and without the fault or negligence of the Contractor, including * * * strikes * * *.

Even were the above provision not in the contract, we could take judicial notice of the risk of strikes and other labor problems inherent in the vast.majority of construction contracts. This is a fact of modern commercial life. Neither the contractor nor the Government could be presumed ignorant of this risk. Defendant denies that it ever entered into the contract upon the assumption of labor peace and says that this was just plaintiff’s unilateral assumption.

What we have in the instant case, therefore, is a risk which is known to both parties and results from human inability to predict the future. The authorities are unanimous in distinguishing such risks from bona ffde mutual mistakes of fact. In 13 WillistoN, CoNteacts § 1543 (3d ed. 1970) at 75, it is said:

* * * there must be excluded from consideration mistakes as to matters which the contracting parties had in mind as possibilities and as to the existence of which they took the risk. * * *.

A similar statement is made in 3 CoebiN, Contracts § 598 (2ed. 1960) at 585-86:

* * * The same result obtains in any case where the risk of the existence of some factor or of the occurrence of an event is consciously considered in agreeing upon terms. There is no mistake; instead, there is awareness of the uncertainty, a conscious ignorance of the future. * * *.

The EestateMBNT, Contracts § 502, comment /, reinforces the distinction:

Where the parties know that there is doubt in regard to a certain matter and contract on that assumption, the contract is not rendered voidable because one is disappointed in the hope that the facts accord with his wishes. The risk of the existence of the doubtful fact is then assumed as one of the elements of the bargain.

[6]*6See also Leasco Corp. v. Taussig, 473 F. 2d 777 (2d Cir. 1972).

Plaintiff argues, however, that while both parties may have been aware of the risk of a “normal” strike, neither party anticipated the severe labor difficulties which eventuated. This attempted distinction based on the degree of the difficulties encountered is fallacious. First, there is no evidence whatsoever that defendant ever thought in terms of a “normal” as opposed to a “severe” strike. Secondly, the distinction is unworkable as a practical matter, because there is no such recognizable concept as a “normal” strike, and no clear line between “normal” and “severe” difficulties. Furthermore, it is unlikely that the parties to a contract of this type ever plan for the most unfavorable outcome, even though they are aware of the risk of such an outcome.4

In those circumstances, not present here, in which we are able to identify a mutual mistake of fact, we still cannot grant reformation if the contract puts the risk of the mistake upon the party asking reformation. National Presto Industries, Inc. v. United States, 167 Ct. Cl. 749, 764, 338 F. 2d 99, 108 (1964), cert. denied, 380 U.S. 962 (1965). In the instant case, the risk of labor strife was placed, both explicitly and implicitly by the contract, on McNamara.

Clause 13 of the contract places responsibility on the contractor to take steps “reasonably necessary to ascertain the nature and location of the work, and the general and local conditions which can affect the work or the cost thereof. Any failure by the Contractor to do so will not relieve him from responsibility for successfully performing the work without additional expense to the Government.” Plaintiff assures the court, and we see no reason to doubt the fact, that plaintiff visited the site prior to bidding, and investigated as best it could the availability and cost of labor in the area. Plaintiff’s effort to comply with clause 13 does not, however, alter the clear implication of the clause that the risk that local [7]*7conditions will turn out to be other than plaintiff expected falls on plaintiff. We have previously held, for example, that the presence of such a clause in a contract placed the risk of a mistake as to subsurface materials on the contractor. Flippin Materials Co. v. United States, 160 Ct. Cl. 357, 312 F. 2d 408 (1963). In Flippin the contractor did not make an adequate on-site investigation but did argue for reformation.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lakeshore Engineering Services, Inc. v. United States
110 Fed. Cl. 230 (Federal Claims, 2013)
PCL Construction Services, Inc. v. United States
47 Fed. Cl. 745 (Federal Claims, 2000)
Northrop Grumman Corp. v. United States
47 Fed. Cl. 20 (Federal Claims, 2000)
Olympus Corporation v. United States
98 F.3d 1314 (Federal Circuit, 1996)
Peterson Builders, Inc. v. United States
40 Cont. Cas. Fed. 76,853 (Federal Claims, 1995)
Mega Construction Co. v. United States
39 Cont. Cas. Fed. 76,564 (Federal Claims, 1993)
Denro, Inc. v. United States
36 Cont. Cas. Fed. 75,782 (Court of Claims, 1990)
Gould, Inc. v. United States
36 Cont. Cas. Fed. 75,781 (Court of Claims, 1990)
Design & Production, Inc. v. United States
35 Cont. Cas. Fed. 75,718 (Court of Claims, 1989)
Marathon Oil Co. v. United States
17 Cl. Ct. 116 (Court of Claims, 1989)
Atlas Corp. v. United States
35 Cont. Cas. Fed. 75,578 (Court of Claims, 1988)
Johns-Manville Corp. v. United States
34 Cont. Cas. Fed. 75,361 (Court of Claims, 1987)
Utility Contractors, Inc. v. United States
32 Cont. Cas. Fed. 73,446 (Court of Claims, 1985)
Passaro v. United States
4 Cl. Ct. 395 (Court of Claims, 1984)
Black Top Paving Co. v. Commonwealth
466 A.2d 774 (Commonwealth Court of Pennsylvania, 1983)
Gregory Lumber Co. v. United States
29 Cont. Cas. Fed. 82,637 (Court of Claims, 1982)
Haas v. Pittsburgh National Bank
495 F. Supp. 815 (W.D. Pennsylvania, 1980)
Aluminum Co. of America v. Essex Group, Inc.
499 F. Supp. 53 (W.D. Pennsylvania, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
509 F.2d 1166, 20 Cont. Cas. Fed. 83,644, 206 Ct. Cl. 1, 1975 U.S. Ct. Cl. LEXIS 241, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mcnamara-construction-of-manitoba-ltd-v-united-states-cc-1975.