Poirier & McLane Corp. v. United States

120 F. Supp. 209, 128 Ct. Cl. 117, 1954 U.S. Ct. Cl. LEXIS 124
CourtUnited States Court of Claims
DecidedApril 6, 1954
Docket49623
StatusPublished
Cited by11 cases

This text of 120 F. Supp. 209 (Poirier & McLane Corp. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Poirier & McLane Corp. v. United States, 120 F. Supp. 209, 128 Ct. Cl. 117, 1954 U.S. Ct. Cl. LEXIS 124 (cc 1954).

Opinion

LITTLETON, Judge.

In this action plaintiff seeks to recover $19,901.08, representing increased labor costs incurred by plaintiff, a New York corporation, in the performance of a contract with the defendant for the construction of a flight hangar in Buffalo, New York. The increased labor costs resulted from the payment by plaintiff of a higher wage rate to unskilled laborers working on the project than that contained in the contract specifications, as fixed and determined by the Secretary of Labor under the Davis-Bacon Act, 40 U.S.C.A. § 276a et seq.

The case is presently before the court on motions by plaintiff and defendant for summary judgment. From the allegations of the petition, several exhibits, and an agreed statement of facts not in dispute, it appears that defendant, on July 1, 1943, issued an invitation for bids for tne construction of a flight hangar. Plaintiff submitted the low bid, and on July 14, 1943, plaintiff and defendant acting through the United States Engineer Office entered into a contract whereby plaintiff agreed to furnish all labor, plant and material and perform all work required for the construction of a flight hangar at Buffalo Municipal Airport, Buffalo, New York, for an estimated consideration of $1,466,402. This figure was based in part upon lump sum prices and in part upon unit prices. Work was commenced within three days after July 15, 1943, and was to be completed not later than November 12, 1943. The contract work was completed by plaintiff and accepted by defendant within the contract performance period as subsequently extended.

As required by the Davis-Bacon Act, 1 the contract specifications which accompanied the bid and became a part of the contract contained a schedule of the minimum wages to be paid various classes of laborers and mechanics, based on wages determined by the Secretary of Labor to be prevailing on projects of a character similar in nature to the contract work in the contract locality. The minimum wage rate to be paid unskilled laborers on the contract work was fixed at 85 cents per hour. This was the minimum and also the maximum rate. Prior to submitting its bid, plaintiff made careful investigation for the purpose of determining the availability of labor, and the wages it would have to pay to obtain the required labor. Plaintiff found that the war wage stabilization program had been established in the Buffalo area, and that under this program the - United States Employment Service (hereinafter referred to as USES) was responsible for directing and regulating the hiring of workers in the Buffalo area. Plaintiff also found that the USES was predicting, in June and July, that an abundant supply of labor would be available in the Buffalo area during August, September, October, and November. 2 Plaintiff also consulted with labor unions and other sources in the Buffalo area, and found and determined that the unions expected to be able to provide all necessary unskilled labor at the specified wage rate of 85 cents per hour. In reliance upon its investigations and upon the decision of the Secretary of Labor and the wage provisions in the specifications, plaintiff made no allowance in the computation of its bid for any increase in wage rates in the performance of the contract.

Article 17 of the contract directed the contractor to pay to all mechanics and laborers employed directly upon the site of the work wages computed at “rates not less or more than those stated in the *211 specifications (subject to Executive Order No. 9250, 50 U.S.C.A.Appendix, § 901 note, and the General Orders and Regulations issued thereunder) regardless of any contractual relationship which may be alleged to exist between the contractor * * * and such laborers and mechanics * *

Section 1-27 ®f the specifications provided in part:

“(a) The minimum wages to be paid laborers and mechanics for work being performed for the United States Government as determined by the Secretary of Labor to be prevailing for the corresponding classes of laborers and mechanics employed on projects of a character similar to the contract work in the pertinent locality, are as follows:
“Title: Department of Labor Determination Dated September 15, 1942, as modified March 25, 1943, for Erie County, N. Y.
“Classification of Laborers and Mechanics:
****** Minimum rates of wages per hour
Laborers, unskilled.....$0.85
******
“(b) * * * The wages specified in this schedule shall be the maximum wages to be paid, subject, however, to Executive order No. 9250 and the General Orders and Regulations issued thereunder.
“(c) The contractor will be expected to make his own investigation and determine for himself both the availability of labor possessing the necessary skill and the rates of wages necessary to obtain the required quantity and quality thereof. Whenever the contractor, in pursuance of the foregoing, determines that he is unable to recruit the necessary labor with the necessary skills at the predetermined rates applicable to his contract, he will make request direct to the Wage Adjustment Board, for a wage adjustment, which shall contain a statement that the adjustment, if authorized, will be absorbed by the contractor and will not constitute a basis for a claim against the Government. * *

The contract also contained the standard Article 3, relating to changes in the drawings and specifications, and providing for an equitable adjustment for increase in price or time for performance.

The contract work was of importance to the war effort, and there was urgent need that it be completed within the contract performance period. Work was commenced within three days after July 15, 1943. In August of 1943, shortly after plaintiff had begun performance, it found that unskilled labor was being offered and paid $1.00 per hour or more on other construction projects in the Buffalo area, and that in order to procure a sufficient supply of unskilled laborers it would be necessary for plaintiff to pay a wage rate of $1.00 per hour.

Plaintiff thereupon requested that defendant change the 85 cents per hour wage rate contract specification to $1.00' per hour, retroactively to the date of execution of the contract, and to increase the contract price accordingly. Defendant was also notified that plaintiff would not make a request for a wage adjustment to the Wage Adjustment Board under paragraph 1-27(c) of the contract specifications, for the reasons that plaintiff believed the 85 cents per hour specification to be in error; that this error constituted a basis for a claim against the defendant for reimbursement, and that plaintiff accordingly would not agree that an adjustment, if authorized by the Wage Adjustment Board, would “be absorbed by the contractor.” Plaintiff made no request to the Wage Adjustment Board, and no order was issued by the Board authorizing a wage adjustment under the provisions of paragraph l-27(c) of the- specifications.

In September 1943, the Department of Labor reviewed data bearing upon wage rates prevailing for construction

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Emerald Maintenance, Inc. v. The United States
925 F.2d 1425 (Federal Circuit, 1991)
Morrison-Hardeman-Perini-Leavell v. The United States
392 F.2d 988 (Court of Claims, 1968)
Evans Reamer & MacHine Company v. The United States
386 F.2d 873 (Court of Claims, 1968)
Ross Engineering Co. v. United States
127 F. Supp. 580 (Court of Claims, 1955)
Hughes Transp., Inc. v. United States
121 F. Supp. 212 (Court of Claims, 1954)

Cite This Page — Counsel Stack

Bluebook (online)
120 F. Supp. 209, 128 Ct. Cl. 117, 1954 U.S. Ct. Cl. LEXIS 124, Counsel Stack Legal Research, https://law.counselstack.com/opinion/poirier-mclane-corp-v-united-states-cc-1954.