Thomas M. Durkin & Sons, Inc. v. Department of Transportation

742 A.2d 233, 1999 Pa. Commw. LEXIS 880
CourtCommonwealth Court of Pennsylvania
DecidedNovember 24, 1999
StatusPublished
Cited by3 cases

This text of 742 A.2d 233 (Thomas M. Durkin & Sons, Inc. v. Department of Transportation) is published on Counsel Stack Legal Research, covering Commonwealth Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Thomas M. Durkin & Sons, Inc. v. Department of Transportation, 742 A.2d 233, 1999 Pa. Commw. LEXIS 880 (Pa. Ct. App. 1999).

Opinion

SMITH, Judge.

Thomas M. Durkin & Sons, Inc. (Dur-kin) petitions for review of a decision of the Pennsylvania Board of Claims (Board) which resolved claims arising from a highway construction contract between Durkin and the Department of Transportation *235 (DOT). Durkin appeals from the Board’s partial award of “standby costs” for equipment used to construct two retaining walls (Claim C) and the Board’s denial of costs for temporary concrete barrier and temporary impact attenuators used on the highway construction project during its final year (Claim J). DOT appeals from the Board’s award of compensation to Durkin for the removal of rock during the construction of a retaining wall (Claim G).

I.

On April 6, 1987, Durkin and DOT entered into a contract for $53,897,182.97 for the construction of “Section 600” of Interstate 78 (Project), a section of highway located south and west of the city of Allentown, in Lehigh County, Pennsylvania. The Project provided for the construction of approximately 3.375 miles of highway, reconstruction and rehabilitation of local roads and construction of bridge structures and retaining walls. DOT issued a notice to proceed on April 10, 1987 and set a completion date of December 17, 1988. After the work began, multiple problems arose which delayed Durkin’s performance and prevented completion of the Project within the specified time. To resolve Dur-kin’s potential contract claims against DOT, to provide an additional year for performance and to provide compensation to Durkin for work completed during the additional year, the parties executed an interim settlement agreement dated November 10,1988 (Agreement). The Agreement provided a $2.25 million lump-sum payment to resolve Durkin’s claims; provided smaller lump-sum payments for specified construction tasks; provided for the construction of two retaining walls on a force account basis; and provided revised unit prices for certain contract items.

The Project was completed within the extended year, but during that time additional disputes arose between Durkin and DOT. On December 15, 1992, Durkin forwarded a letter to DOT identifying thirteen claims requiring additional compensation. A resolution could not be reached, and on June 16, 1993, Durkin filed a complaint with the Board. On March 4, 1999, the Board issued an order that awarded Durkin $416,208.73 of the $1,534,075.48 claimed. Of the thirteen claims heard by the Board (Claims A-M), only Durkin’s appeal of the Board’s order as to Claims C and J and DOT’s appeal as to Claim G are before the Court.

Claim C involved DOT’s refusal to pay Durkin force account, equipment standby costs of $140,314.61 incurred when Durkin chose not to work, i.e., rain days, weekends and holidays. In refusing payment, DOT relied on its Project Office Manual, an internal publication pertaining to the administration of highway contracts, which specifies: “[D]ay[s] on which the contractor elects not to work, standby time will not be paid.” Durkin argued that the manual was never made part of the contract. The Board found that the manual was “in effect” during the Project and awarded Durkin $25,662.40 of the $140,-314.61 claimed.

Claim J involved DOT’s refusal to pay $444,583.25 claimed by Durkin for the full escalated contract price for each linear foot of temporary concrete barrier and temporary impact attenuator already on site at the time the parties executed the Agreement and used during the extended year. DOT states that the barrier was used to separate roadway traffic from the construction work and that the attenuators were used to guard traffic from collisions with objects such as guardrails. Durkin argued that DOT was required to pay the revised unit prices for the temporary concrete barrier at $15.25 per linear foot (for 29,153 linear feet) and for the temporary impact attenuators at $15,750 per unit (for 12 units) as specified in paragraph 5C of the Agreement. DOT argued that payment was covered by paragraph 5B of the Agreement, which provided a $150,000 lump-sum payment for the “extended maintenance and protection of traffic.” The Board determined that paragraph 5B *236 governed, and it denied Durkin any other sums for these items over and above the $150,000 lump-sum payment.

Claim G involved DOT’s refusal to pay $152,083.29 to Durkin for the removal of rock in the construction of the “Ramp B” retaining wall. The contract required Durkin to construct a combination proprietary and tieback retaining wall at Ramp B. 1 DOT’s design plans noted the precise location of the interface point between the proprietary and retaining portions of the wall. DOT’s Ramp B drawings, however, noted the interface point as “approximate” and stated that it would be determined “after the rock surface is exposed during construction.” Actual field conditions revealed that the interface point varied from what the design plans indicated. To construct the wall as required, Durkin incurred additional expense in removing significant quantities of rock. DOT’s stated position was that removal of the rock was covered by the contract because the interface point was labeled on the Ramp B drawings as “approximate.” By contrast Durkin maintained that the work was unanticipated and outside the scope of the contract. The Board agreed with Durkin and concluded that the work was beyond the scope of the contract and warranted additional compensation. 2

II.

Durkin initially argues its appeal of the Board’s order concerning Claim J. Durkin contends that the Board erred by failing to award Durkin costs for temporary concrete barrier and temporary impact attenuators already on site when the Agreement was executed. Durkin explained that these “time-related items” are not permanently incorporated into a project but instead are rented for use during the period of a project, and the extension of the contract with DOT for another year increased Durkin’s costs for retaining these items at the site. Durkin urges the Court to consider another essential factor overlooked by the Board, i.e., that the equipment represented contract items which were separate and apart from the general contract item for maintenance and protection of traffic, and pursuant to paragraph 5C of the Agreement DOT was liable for these items separately. Thus, Dur-kin contends, the parties intended that the revised unit prices would be paid for this equipment to compensate Durkin for its rental value for the extended period of the contract.

Durkin asserts that the Board erroneously relied on paragraph 5B of the Agreement, which provides that DOT “shall pay Durkin for extended maintenance and protection of traffic (Contract Item No. 0901-0001) the additional sum of One Hundred Fifty Thousand Dollars ($150,000.00).” Durkin argues that paragraph 5B does not apply because it makes no reference to the barrier or attenuators or to their item numbers. Instead, Durkin maintains that payment is governed solely by paragraph 5C of the Agreement, which provides that “items listed on Exhibit ‘B’ shall be paid to Durkin for the prices set forth therein. Any items not listed in Exhibit ‘B’, paragraphs 5A and B of this Agreement ...

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mar-Paul Co. v. Jim Thorpe Area School District
7 Pa. D. & C.5th 387 (Carbon County Court of Common Pleas, 2008)
A. G. Cullen Construction, Inc. v. State System of Higher Education
898 A.2d 1145 (Commonwealth Court of Pennsylvania, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
742 A.2d 233, 1999 Pa. Commw. LEXIS 880, Counsel Stack Legal Research, https://law.counselstack.com/opinion/thomas-m-durkin-sons-inc-v-department-of-transportation-pacommwct-1999.