Thalle Construction Co. v. Whiting-Turner Contracting Co.

39 F.3d 412
CourtCourt of Appeals for the Second Circuit
DecidedNovember 10, 1994
DocketNos. 234, 369, Dockets 94-7108L, 94-7126XAP
StatusPublished
Cited by1 cases

This text of 39 F.3d 412 (Thalle Construction Co. v. Whiting-Turner Contracting Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Second Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Thalle Construction Co. v. Whiting-Turner Contracting Co., 39 F.3d 412 (2d Cir. 1994).

Opinion

WALKER, Circuit Judge:

This diversity action is brought by Thalle Construction Company (“Thalle”), a citizen of New York and a subcontractor on a project to build an office complex for IBM, against the general contractor Whiting-Turner Contracting Company (“Whiting-Turner”), a citizen of Maryland, to recover damages for delays suffered by Thalle. Plaintiff appeals from a judgment of the United States District Court for the Southern District of New York (Gerard L. Goettel, District Judge) finding Whiting-Turner hable for three months of delay damages totaling approximately $600,000 and holding Thalle hable for $339,147 in counterclaims. Plaintiff challenges (1) the district court’s findings of fact as to the length of delay; (2) the measure of damages for its delay; and (3) Thahe’s liability for defendant’s counterclaims. Whiting-Turner cross-appeals, contending that 1) the district court erred in holding Whiting-Turner hable for any delay; 2) the measure of damages was inaccurate; and 3) plaintiff waived its claims.

For the reasons that follow, we reverse the judgment below in part and remand.

BACKGROUND

In March, 1986, the Whiting-Turner Contracting Company entered into a general contract with IBM to construct IBM’s “Customer Executive Education Center.” The six-building, $68.9 million complex was designed to house IBM’s most important customers while they received demonstrations of and training in the company’s newest products. Three months later, Thalle signed a subcontract with Whiting-Turner in which Thalle agreed to perform the site work on the project for shghtly over $5 million. The site work entailed several distinct tasks, including clearing, excavation, paving, and installation of site utihties and drainage systems.

When Thalle first submitted its bid, the entire project was scheduled to begin in October, 1985 and conclude by December, 1987, a total of 27 months. If selected, Thalle would be the first subcontractor to arrive at the site. In November, 1985, however, IBM [414]*414informed Whiting-Turner, and Whiting-Turner in turn informed Thalle, that construction would not begin until at least the spring of 1986. Thalle agreed to maintain its current bid until March 1, 1986. Thalle’s bid was eventually accepted, and Thalle arrived at the site to begin its work on April 1.

Thalle’s work did not proceed as planned. From nearly its first day, the project was fraught with delays. Perhaps most seriously, Whiting-Turner experienced a number of problems with Prim-Mar, its concrete subcontractor. After beginning work in June, 1986, Prim-Mar refused to execute its subcontract and operated with a reduced workforce, demanding that Whiting-Turner raise the subcontract price to compensate for supposed delays and increased costs. Even though Whiting-Turner eventually paid Prim-Mar an additional $643,000 beyond its subcontract price, Prim-Mar failed to meet the deadlines listed in the concrete subcontract. Prim-Mar was also unable to meet a second, more relaxed schedule. Whiting-Turner eventually terminated Prim-Mar after it abandoned the project in February, 1988. The delays caused by Prim-Mar’s intransigence slowed some of Thalle’s excavation and backfilling, which was dependent upon the completion of Prim-Mar’s concrete work.

Other project participants also delayed Thalle’s work. IBM, the site owner, failed to obtain permits from the State of New York to commence work along two roads. The electrical and waterproofing subcontractors also performed more slowly than required. Because of these problems and Whiting-Turner’s difficulties in coordinating the work of the various subcontractors, several of the project areas were not released to Thalle when needed.

Thalle also suffered numerous setbacks itself. Thalle failed to perform “sheeting and shoring” in one location, prompting a design adjustment and at least a mild delay. Thalle also experienced labor union unrest leading to a one-day strike and a “sick out” of up to one and a half days. To add to its problems, Thalle encountered ground water near one dam and rock at various building sites, both unanticipated. These obstructions required design changes and slowed Thalle’s progress.

As a result of the myriad delays, Thalle’s activities took substantially longer than expected. Bulk excavation and preliminary backfill, scheduled to be essentially completed by the end of 1986, stretched through the winter months of 1987. Additional backfill work was then pushed into the spring. Although Thalle’s major responsibilities were originally to end by May 31, 1987, Thalle worked steadily through the end of 1987. Thalle did not leave the site until August 1988, returning in October and November to complete final tasks. Because of these delays, Thalle refused to release Whiting-Turner from liability on the subcontract. Wdiit-ing-Turner initially held up payment of the balance remaining on the subcontract pending that release, but finally settled its account with Thalle in July, 1989 despite Thalle’s refusal. Wdfiting-Turner then signed a general release in favor of IBM in October of 1990.

Thalle filed suit against Whiting-Turner in February, 1991. Thalle claimed, among other allegations, that the delays it suffered resulted in over $4 million of additional costs. It arrived at this figure using the “total cost” approach, which measures the total cost of the subcontract, including profit and office overhead, and subtracts amounts received by the subcontractor. Whiting-Turner counterclaimed, asking for damages for delays prompted by Thalle and indemnification for damage that Thalle caused to adjacent property through its blasting and failure to control erosion, as well- as for stump burial fees Whiting-Turner paid on Thalle’s behalf.

Following a non-jury trial, the district court found that Thalle suffered three months of delay due to Whiting-Turner’s poor coordination of its subcontractors. The court rejected Thalle’s “total cost” measure of damages, and instead held Whiting-Turner liable for three months worth of additional revenue, or $600,000. The court also allowed counterclaims in the amount of $339,-147. Both parties appealed.

[415]*415DISCUSSION

I. The District Court’s Findings of Fact

Both parties contest the district court’s findings of fact regarding the length and cause of delays suffered by Thalle. Thalle argues that it experienced far more than three months of delay. It offers two prongs to this argument: First, it challenges Judge Goettel’s conclusion that Thalle either contributed to or “drifted along with” six months of delay in 1986. Second, Thalle takes issue with the district court’s finding that Thalle’s duties continued through the end of the project. Because its subcontract was to be fully completed on May 31, 1987, Thalle contends, the amount of delay should be measured from that date. Whiting-Turner argues that Thalle itself delayed the project by six months and should thus be held liable.

Amid this welter of contentions, all presented to the court below, we are guided by the principle that a district court’s findings of fact should not be set aside on appeal unless they are “clearly erroneous.” Fed. R.Civ.P. 52(a). This stringent standard is only met if “‘the reviewing court on the entire evidence is left with the definite and firm conviction that a mistake has been committed.’” Anderson v. City of Bessemer City,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
39 F.3d 412, Counsel Stack Legal Research, https://law.counselstack.com/opinion/thalle-construction-co-v-whiting-turner-contracting-co-ca2-1994.