Exton Drive-In, Inc. v. Home Indemnity Co.

261 A.2d 319, 436 Pa. 480, 1969 Pa. LEXIS 671
CourtSupreme Court of Pennsylvania
DecidedNovember 28, 1969
DocketAppeal, 466
StatusPublished
Cited by79 cases

This text of 261 A.2d 319 (Exton Drive-In, Inc. v. Home Indemnity Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Exton Drive-In, Inc. v. Home Indemnity Co., 261 A.2d 319, 436 Pa. 480, 1969 Pa. LEXIS 671 (Pa. 1969).

Opinions

Opinion by

Mr. Justice Pomeroy,

This action was commenced in 1956 when Exton Drive-In, Inc. (Exton) filed a complaint in assumpsit against The Home Indemnity Co. (Home) seeking damages under a performance bond in which Home and W. Arnold Blythe (Blythe) had bound themselves jointly and severally to Exton in the sum of $52,000. The bond was conditioned on the full and prompt per[484]*484formance by Blytbe of a contract between him and Ex-ton for the grading and paving of a site for an outdoor motion picture theater. Exton alleged that this contract had not been fully and promptly performed and claimed damages in the amount of $42,500, being the profits allegedly lost because of delay in performance plus the estimated cost of remedying the defects in performance. Because the bond was a joint undertaking of Blythe as principal and Home as surety, Home impleaded Blythe as an additional defendant asserting joint and several liability. In his answer to the third party complaint, Blythe denied that he had breached the contract and brought a counterclaim against Exton for the unpaid balance of the contract price and for payment for certain additional work he had performed, allegedly at the request of Exton.

The case came on for trial before a judge sitting without a jury in May, 1960. Not until June, 1967, over seven years after the trial was completed did the judge enter his decision in this case. This decision was in the form of a verdict in favor of defendants Home and Blythe on plaintiff’s original complaint and a verdict for Blythe on his counterclaim against Exton in the sum of $13,692.49; there were no findings of fact or conclusions of law. Exton filed numerous exceptions to this decision, which were overruled by the court en banc in June, 1968. This appeal followed. Not until April 18, 1969, seventeen days before this appeal was argued, did the trial judge file an opinion explaining the overruling of Exton’s exceptions.

Judicial Delay

Appellant contends that the lower court’s failure to order a new trial sua sponte because of the inordinate delay between trial and decision was an abuse of discretion.

[485]*485Appellant is correct that the court below had the power to grant a new trial sua sponte, if in its opinion justice so required. Getz v. Balliet, 431 Pa. 441, 446, 246 A. 2d 108 (1968); Fisher v. Brick, 358 Pa. 260, 262, 56 A. 2d 213 (1948). The question, then, is whether the court abused its discretion by failing to do so.

Nothing in the record indicates that any party was responsible for this delay; the fault appears to have been that of the trial judge. Such dereliction flouts the proud promise of the Magna Carta: “to none will we . . . deny, to none delay, either right or justice.” It contravenes the guarantee of the Constitution of this Commonwealth that “. . . Every man . . . shall have . . . right and justice administered without sale, denial or delay.” Article I, Section 11. It flies in the teeth of the statutory standard that the decision of a court sitting without a jury “. . . shall be filed ... as early as practicable, not exceeding sixty days from the termination of the trial . . .1 The right to have justice administered without delay is a fundamental right which should not be infringed unless no other course is reasonably possible. Kelly v. Brenner, 317 Pa. 55, 59, 175 Atl. 845 (1934).

We said in General Foods Corp., 429 Pa. 266, 271, 239 A. 2d 359 (1968), that as a matter of judicial administration we would not condone an eighteen month delay but that we could understand it. A seven year delay we neither condone nor understand; we can only [486]*486deplore it. While there may have been extenuating circumstances of which we have no knowledge, we must express our sense of dismay and chagrin that a delay so protracted could occur in the courts of this Commonwealth in the 1960’s.

Our unhappiness with this delay is not, however, a sufficient ground for ordering a new trial, for such an order would still further defer the end to this litigation. If the facts of this case support the decision as rendered, we would compound the injustice by requiring the parties to return to their pre-1960 positions and begin anew the trial of this case. Accordingly, we hold that the lower court’s failure to grant a new trial solely because of the long-delayed decision was not an abuse of discretion.

Standard of Review

Appellant further contends that a new trial is necessary because the evidence contradicts rather than supports the decision of the court below. That decision, as mentioned above, is in the form of a naked verdict for Blythe and Home on the original complaint and for Blythe on his counterclaim; there are no findings.2 In such a case we must make an independent review of the. record. Idell v. Falcone, 427 Pa. 472, 473-4, 235 A. 2d 394 (1967); Ballinger v. Howell Mfg. Co., 407 Pa. 319, 180 A. 2d 555 (1962). Cf. Yoo Hoo Bottling Co. of Pa. v. Leibowitz, 432 Pa. 117, 119, 247 A. 2d 469 (1968).

In reviewing this record we must evaluate the contentions of Exton that there were four material breaches of the contract by Blythe and that the verdict [487]*487was against the evidence. The material breaches alleged by Exton are: (1) failure to complete the contract work within the time period specified in the contract; (2) failure to make the paved surface impervious to water as required by the contract; (3) failure to use the required minimum quantities of materials; and (4) failure to grade and pave the area to allow proper drainage.

Timely Performance

The contract between Blythe and Exton specified that time was of the essence and required Blythe to complete the grading and paving of the drive-in theater site within thirty-eight working days of the contract date. This provision as to timely performance gave Blythe notice that a delay in completion of the contract would delay the opening of the theater and result in losses for Exton. Losses caused by Blythe’s failure to make timely performance were accordingly foreseeable. The Restatement of Contracts, §346 (1932) provides as follows: “(1) For a breach by one who has contracted to construct a specified product, the other party can get judgment for compensatory damages for all unavoidable harm that the builder had reason to foresee when the contract was made, less such part of the contract price as has not been paid and is not still payable, determined as follows ... (b) For any delay in completion fairly chargeable to the builder, the plaintiff can get judgment for the value of the use of the product, if it was being constructed for use.” We believe this rule is proper and sound. Cf. Lever v. Lagomarsino, 282 Pa. 110, 114, 127 Atl. 452 (1925). Its application in the present case would permit Exton to recover damages from Blythe for the difference between the losses caused by delay in the use of the theater and the unpaid balance of the contract price, provided only that [488]*488Exton proved (a) a failure of timely performance, and (b) resulting damages which were sufficiently certain to permit recovery.

From the evidence adduced at trial, we believe Ex-ton did establish a failure of timely performance. Even adopting arguendo

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Janice Leaman v. Gregg Wolfe
629 F. App'x 280 (Third Circuit, 2015)
SVNE Pharma, Inc. v. N.E. Philadelphia Pharmacy, Inc.
46 Pa. D. & C.5th 438 (Philadelphia County Court of Common Pleas, 2015)
Board of Trustees v. International Fidelity Insurance
63 F. Supp. 3d 459 (E.D. Pennsylvania, 2014)
Corrections U.S.A. v. McNany
892 F. Supp. 2d 626 (M.D. Pennsylvania, 2012)
Continental Casualty Co. v. Fleming Steel Co.
439 F. App'x 134 (Third Circuit, 2011)
MUNICIPAL REVENUE SERVICE, INC. v. Xspand, Inc.
700 F. Supp. 2d 692 (M.D. Pennsylvania, 2010)
State v. HESS CORP.
982 A.2d 388 (Supreme Court of New Hampshire, 2009)
Burtch v. Ganz (In Re Mushroom Transportation Co.)
366 B.R. 414 (E.D. Pennsylvania, 2007)
Zeno v. Ford Motor Co., Inc.
480 F. Supp. 2d 825 (W.D. Pennsylvania, 2007)
Brisbin v. Superior Valve Co.
398 F.3d 279 (Third Circuit, 2005)
Amco Prompriladamco v. American Meter Co.
312 F. Supp. 2d 681 (E.D. Pennsylvania, 2004)
ID Security Systems Canada, Inc. v. Checkpoint Systems, Inc.
249 F. Supp. 2d 622 (E.D. Pennsylvania, 2003)
Mahmood v. Ross
1999 UT 104 (Utah Supreme Court, 1999)
Wujcik v. Yorktowne Dental Associates, Inc.
701 A.2d 581 (Superior Court of Pennsylvania, 1997)
Allied Fire & Safety Equipment Co. v. Dick Enterprises, Inc.
972 F. Supp. 922 (E.D. Pennsylvania, 1997)
Trans Penn Wax Corp. v. McCandless
50 F.3d 217 (Third Circuit, 1995)
Trans Penn Wax Corporation v. Michael Mccandless
50 F.3d 217 (Third Circuit, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
261 A.2d 319, 436 Pa. 480, 1969 Pa. LEXIS 671, Counsel Stack Legal Research, https://law.counselstack.com/opinion/exton-drive-in-inc-v-home-indemnity-co-pa-1969.