Kenco Construction, Inc., Resp v. Porter Brothers Construction, Inc., Et Ano, Apps

CourtCourt of Appeals of Washington
DecidedJune 11, 2018
Docket74069-5
StatusUnpublished

This text of Kenco Construction, Inc., Resp v. Porter Brothers Construction, Inc., Et Ano, Apps (Kenco Construction, Inc., Resp v. Porter Brothers Construction, Inc., Et Ano, Apps) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kenco Construction, Inc., Resp v. Porter Brothers Construction, Inc., Et Ano, Apps, (Wash. Ct. App. 2018).

Opinion

FILED CURT OF APPEALS, DIV I STATE OF WASHINGTON

2018 JUN 1 1 A1110: 30

IN THE COURT OF APPEALS OF THE STATE OF WASHINGTON

KENCO CONSTRUCTION, INC., a ) No. 74069-5-1 Washington Corporation, ) ) DIVISION ONE Respondents, ) ) UNPUBLISHED OPINION v. ) ) PORTER BROTHERS CONSTRUCTION, ) INC., a Washington Corporation; ) ) Appellant. ) FILED: June 11,2018 ) ) BEMO USA CORPORATION, ) ) Plaintiff, ) ) v. ) ) KENCO CONSTRUCTION, INC., a ) Washington Corporation; RLI ) INSURANCE COMPANY (Bond No. ) SSB397726), ) ) Respondents, ) ) PORTER BROTHERS CONSTRUCTION, ) INC., a Washington Corporation; ) HARTFORD FIRE INSURANCE ) COMPANY (Bond No. 52BCSD1578), a ) foreign corporation; ) ) Appellants, ) ) HIGHLINE PUBLIC SCHOOL DISTRICT ) NO. 401, a public school district; ) ) Defendant. ) ) No. 74069-5-1/2

) KENCO CONSTRUCTION, INC., a ) Washington Corporation, ) ) Respondent, ) ) v. ) ) HARTFORD FIRE INSURANCE ) COMPANY (Bond No. 52BCSD1578), a ) foreign corporation; ) ) Appellant, ) ) HIGHLINE PUBLIC SCHOOL DISTRICT ) NO. 401, a public school district; ) ) Defendant. )

) TOTEM ELECTRIC OF TACOMA, INC., a ) Washington Corporation, ) ) Respondent, ) ) v. ) ) PORTER BROTHERS CONSTRUCTION, ) INC., a Washington Corporation; ) HARTFORD FIRE INSURANCE ) COMPANY (Bond No. 52BCSD1578), a ) foreign corporation; ) ) Appellants, ) ) HIGHLINE PUBLIC SCHOOL DISTRICT ) 'NO. 401, a public school district; ) ) Defendant. ) ) APPELWICK, C.J. — General contractor, Porter, appeals from jury verdicts in

favor of subcontractors, Kenco and Totem, and from summary judgment

2 No. 74069-5-1/3

dismissing its claims against surety, RLI. We reverse the award of expert fees to

Kenco and Totem. We affirm in all other respects.

FACTS

The Highline School District No. 401 (District) entered into a contract (the

"prime contract") with Porter Brothers Construction Inc., to serve as the general

contractor to construct Raisbeck Aviation High School.

Porter entered into a subcontract agreement with Kenco Construction Inc.,

to perform roofing and paneling for $1,509,745.00. It entered into a second

subcontract with Kenco to perform window, door, and curtain installation for

$979,897.00. As part of these contracts, Kenco selected BEMO USA Corporation

as its supplier for the roofing system and related products for waterproofing. Kenco

also obtained surety bonds for each of these subcontracts from RLI Insurance

Company. The two surety bonds incorporated the subcontracts(which themselves

incorporated the prime contract).

Porter also entered into a subcontract with Totem Electric of Tacoma Inc.,

to perform electrical work for $2,862,980.00.

The project encountered numerous problems affecting both Kenco's and

Totem's work. At the start of the project, Totem discovered an undisclosed

underground power line. It needed to be rerouted to allow pilings to be inserted.

This required coordination with Seattle City Light. On October 6, 2011, the

architect provided supplemental instructions to address the issue. Rerouting of

the line was complete by December 23, 2011. This set the project back more than

60 days.

3 No. 74069-5-1/4

In an effort to accelerate the project, the steel erector's work was expedited,

and made up 31 days of time. But, after the expedited steel erection, the structural

steel was outside of the project's specifications. Kenco was asked to complete

extra work to rectify the steel issue. Kenco was required to adapt to the out-of-

tolerance substrates.

However, one of the problems associated with the project was the suitability

of a building product used by Kenco. That product, a roofing underlayment

supplied by BEMO, did not work as intended. It did not properly adhere to the

structure, and therefore caused leaks. The underlayment had to be installed three

successive times to seal the building.

As Kenco was completing its work, it submitted applications to Porter for

progress payments. Kenco's President testified that Porter began withholding

progress payment funds owed to Kenco, starting on August 12, 2012.1 Problems

also arose affecting Totem. Predecessor work was not ready, the job site was not

properly prepared, and Totem was frequently forced to start and stop its work.

Totem also did not receive scheduling updates that should have been provided.

Totem sent numerous letters to Porter expressing concern over predecessor work,

the project schedule, and impacts on cost. As a result, Totem sent a number of

change order requests(CORs)to Porter.

1 Under the billing arrangement, Kenco was to submit an application for progress payments to Porter, who would make application for payment for the calendar month from the project owner, Highline. Highline was then obligated to pay Porter within 30 days, and Porter was obligated to disburse those funds to Kenco within 10 days. Given this arrangement, any funds that Porter withheld on August 12, 2012, would necessarily have been for work performed in July or earlier.

4 No. 74069-5-1/5

As with Kenco, Porter made only limited progress payments to Totem. Both

subcontractors demanded arbitration as provided in the contract, but Porter

refused.

Kenco filed suit against Porter for breach of contract and to compel

arbitration, as provided for in the contract.2 Porter counterclaimed for breach of

contract, brought claims against RLI on the bond, and later amended its answer to

include bad faith claims against RLI. Totem filed a separate complaint for breach

of contract and quantum meruit, among other claims. The lawsuits were

consolidated.

A significant number of motions were heard prior to trial. Porter again

opposed arbitration, and the trial court found that arbitration was not proper due to

the presence of nonparties to the contract.3 .

The trial was bifurcated, with the contract dispute between Porter, Kenco,

and Totem, tried first. Porter's bad faith and Insurance Fair Conduct Act (IFCA),

RCW 48.30.010-.015, claims against RLI were to be tried separately.

Kenco and Totem's theory of the case was that they were not properly

compensated for work that they dutifully performed in response to problems with

the project that were attributable to Porter. Porter's theory was that it properly

withheld progress payments, that the subcontractors failed to give proper notice of

their claims for extra compensation as required by the subcontracts, and that

2 Porter's surety, Hartford Fire Insurance Company, was named in the suit as well. But, for the purposes of our analysis, the distinction between Porter and Hartford is immaterial. We refer to them collectively as "Porter." 3 Highline was also a named defendant, but not a party to the subcontract that required arbitration. The issues on appeal do not pertain to Highline.

5 No. 74069-5-1/6

Kenco caused delays. The trial court denied Porter's midtrial and posttrial motions

for judgment as a matter of law based on inadequate notice as to both Kenco and

Totem.

The jury found in favor of Kenco and Totem. It awarded $1,815,914.49 to

Kenco, and $1,124,095.06 to Totem. And, because the jury found Porter liable, it

dismissed Porter's claims against RLI on summary judgment. Therefore, no trial

on the bad faith and IFCA claims was held. The trial court awarded fees including

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jones v. Best
950 P.2d 1 (Washington Supreme Court, 1998)
Colonial Imports v. Carlton Northwest, Inc.
921 P.2d 575 (Court of Appeals of Washington, 1996)
First Interstate Bank v. Nelco Enterprises, Inc.
822 P.2d 1260 (Court of Appeals of Washington, 1992)
Olympic Steamship Co., Inc. v. Centennial Ins. Co.
811 P.2d 673 (Washington Supreme Court, 1991)
Sing v. John L. Scott, Inc.
948 P.2d 816 (Washington Supreme Court, 1997)
Safeco Insurance Co. of America v. Butler
823 P.2d 499 (Washington Supreme Court, 1992)
City of Seattle v. McCready
931 P.2d 156 (Washington Supreme Court, 1997)
Puget Sound Service Corp. v. Bush
724 P.2d 1127 (Court of Appeals of Washington, 1986)
Seattle Western Industries, Inc. v. David A. Mowat Co.
750 P.2d 245 (Washington Supreme Court, 1988)
Seattle-First National Bank v. Washington Insurance Guaranty Ass'n
972 P.2d 1282 (Court of Appeals of Washington, 1999)
Bignold v. King County
399 P.2d 611 (Washington Supreme Court, 1965)
Bulaich v. AT&T INFORMATION SYSTEMS
778 P.2d 1031 (Washington Supreme Court, 1989)
Refrigeration Engineering Co. v. McKay
486 P.2d 304 (Court of Appeals of Washington, 1971)
Tank v. State Farm Fire and Casualty Co.
715 P.2d 1133 (Washington Supreme Court, 1986)
Hayes v. City of Seattle
934 P.2d 1179 (Washington Supreme Court, 1997)
Washburn v. Beatt Equipment Co.
840 P.2d 860 (Washington Supreme Court, 1992)
Eagle Insurance v. Albright
474 P.2d 920 (Court of Appeals of Washington, 1970)
John F. Harkins Co. v. SCH. DIST. OF PHIL.
460 A.2d 260 (Superior Court of Pennsylvania, 1983)
Gregoire v. City of Oak Harbor
244 P.3d 924 (Washington Supreme Court, 2010)
Moratti Ex Rel. Tarutis v. Farmers Ins. Co.
254 P.3d 939 (Court of Appeals of Washington, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
Kenco Construction, Inc., Resp v. Porter Brothers Construction, Inc., Et Ano, Apps, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kenco-construction-inc-resp-v-porter-brothers-construction-inc-et-washctapp-2018.