Byron's Construction Co. v. North Dakota Department of Transportation

463 N.W.2d 660, 1990 N.D. LEXIS 248, 1990 WL 187770
North Dakota Supreme Court·Decided November 29, 1990·No. Civ. 900207·Published·Cited by 7 cases

Opinions

LEVINE, Justice.

Byron’s Construction Co. (Byron’s) appeals from a district court judgment dismissing its claims against the North Dakota Department of Transportation (the De[661] partment) in its October 6, 1988, demand for arbitration. We affirm.

Byron’s and the Department entered into a highway construction contract in 1985. On February 11, 1988, Byron’s submitted a five-claim demand for arbitration requesting additional compensation. Claims 1 through 4 dealt with delay, disruption, additional work, soil types, borrow quantities, and tolerance requirements for gravel spread on the roadbed. Claim 5 dealt with the Department’s imposition of sanctions for violation of a contract provision relating to participation by minority business enterprises.

After a hearing on April 25-26, 1988, the arbitrators dismissed all five claims. The arbitrators determined that for Claims 1 through 4, Byron’s failed to provide timely notice under § 24-02-26.1, N.D.C.C., of its intention to claim additional compensation. The arbitrators dismissed Claim 5 for lack of jurisdiction. The district court affirmed the arbitrators’ dismissal of all of Byron’s claims. On appeal, we concluded that the arbitrators erred in dismissing Claim 5 for lack of jurisdiction and affirmed the dismissal of Claims 1 through 4 except for a subissue under Claim 2 relating to “force account” work which was not subject to the notice requirement of § 24-02-26.1, N.D. C.C. Byron’s Constr. Co. v. North Dakota State Highway Dep’t, 448 N.W.2d 630 (N.D.1989).

On October 6, 1988, Byron’s again demanded arbitration, seeking compensation for claims relating to “Borrow Quantities” and “Gravel Laydown Due to Altered Specification.” An arbitration hearing was held on May 31, 1989. That hearing was limited to “deciding the issue of whether or not the claim presented in this matter is the same claim that previously was adjudicated in the earlier arbitration proceeding.” In its decision of June 14, 1989, the second arbitration panel determined:

“2.
“The final estimate for final quantities of materials involved in this construction project were received by the claimant’s attorney on or before April 4, 1988, ... and therefore these quantities were available to the claimant for submission in the first arbitration proceedings involving this project.
“3.
“The alleged claim of an altered specification by the claimant was based upon the testimony of Paul Regan at the first arbitration proceedings. Review of that testimony and the evidence presented at the hearing on May 31, 1989, shows conclusively that this issue was considered in the first arbitration proceedings.
“4.
“The claimant had the opportunity pri- or to the first arbitration proceedings to request a continuance for the purpose of further study and review of the final estimates of quantities involved in this project and the claimant chose not to ask for such continuance and instead chose to proceed with the scheduled arbitration hearing on April 26, 1988.
“5.
“The claimant at or prior to the previous arbitration proceedings could have amended their claim to include additional matters brought to their attention shortly before or at the first arbitration hearing and there was no evidence to show that any such amendment was requested by the claimant.”

The arbitrators concluded that “[a]ll of the issues presented by the claimant in the second demand for arbitration were previously litigated and determined in the first arbitration proceedings” and ordered that “the second arbitration demand and claim is in all things dismissed.”

The Department filed a motion in district court for entry of a judgment implementing the decision of the arbitrators. Byron’s filed a motion for an order vacating the arbitrators’ decision and ordering a rehearing. The district court denied Byron’s motion and granted the Department’s motion. A judgment dismissing Byron’s claims in its October 6, 1988, demand for arbitration [662] was entered and Byron’s appealed, raising one issue:

“Was the arbitrator’s determination that the doctrine of ‘res judicata’ precluded appellant’s right to arbitrate completely irrational?”

An arbitration decision will be vacated only if it is completely irrational. Byron’s Constr. Co. v. North Dakota State Highway Dep't, supra; Scherbenske Excavating, Inc. v. North Dakota State Highway Dep’t., 365 N.W.2d 485 (N.D.1985). Although there is no precise definition of a clearly irrational decision, Scherbenske Excavating, Inc. v. North Dakota State Highway Dep’t, supra, generally, a decision is completely irrational if it is either mistaken on its face or so mistaken as to result in real injustice or constructive fraud. Nelson Paving Co., Inc. v. Hjelle, 207 N.W.2d 225 (N.D.1973). The doctrine of res judicata applies to arbitration proceedings as well as judicial proceedings. Wellons, Inc. v. T.E. Ibberson Co., 869 F.2d 1166, 1168 (8th Cir.1989); B.O.W. Cleaning Corp. v. Doe, 84 A.D.2d 527, 443 N.Y.S.2d 614 (App.Div.1981); Restatement (2d) of Judgments § 84 (1982); 6 C.J.S. Arbitration § 128 (1975). The doctrine of res judicata may be used “to protect successful parties from unnecessary, duplica-tive proceedings which cause drains on the resources of both the parties and the judiciary.” Berdahl v. North Dakota State Personnel Board, 447 N.W.2d 300, 307 (N.D.1989).

Byron’s argues that the doctrine of res judicata does not bar its claims because its claims in the first arbitration proceeding were not decided on the merits:

“Res judicata is ‘... a thing or matter that has been definitely or finally settled and determined on its merits by a court of competent jurisdiction.’ (emphasis added) Robertson Lumber Company v. Progressive Contractors, Inc., 160 NW2d 61, 76 (N.D.1968). Nothing in the first arbitration hearing was determined on its merits since the entire demand was dismissed summarily on ‘notice’ and ‘jurisdictional’ issues.”

The reach of res judicata is not necessarily limited to matters that have actually been decided “on the merits.” See, e.g., Comment a to Restatement (2d) of Judgments § 19:

Free access — add to your briefcase to read the full text and ask questions with AI

Byron's Construction Co. v. North Dakota Department of Transportation, 463 N.W.2d 660, 1990 N.D. LEXIS 248, 1990 WL 187770 (N.D. 1990).

463 N.W.2d 660 (Byron's Construction Co. v. North Dakota Department of Transportation) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

LaSalla v. Doctor's Associates, Inc.
898 A.2d 803 (Supreme Court of Connecticut, 2006)
Superpumper, Inc. v. Nerland Oil, Inc.
2003 ND 33 (North Dakota Supreme Court, 2003)
O&K Glass Co. v. Innes Const. Co., Inc.
2000 ND 56 (North Dakota Supreme Court, 2000)
McKibben v. Grigg
1998 ND App 5 (North Dakota Court of Appeals, 1998)
Hofsommer v. Hofsommer Excavating, Inc.
488 N.W.2d 380 (North Dakota Supreme Court, 1992)
Byron's Construction Co. v. North Dakota Department of Transportation
463 N.W.2d 660 (North Dakota Supreme Court, 1990)