Robertson Lumber Co. v. Progressive Contractors, Inc.

160 N.W.2d 61, 1968 N.D. LEXIS 65
CourtNorth Dakota Supreme Court
DecidedJuly 3, 1968
DocketCiv. 8462
StatusPublished
Cited by27 cases

This text of 160 N.W.2d 61 (Robertson Lumber Co. v. Progressive Contractors, Inc.) is published on Counsel Stack Legal Research, covering North Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Robertson Lumber Co. v. Progressive Contractors, Inc., 160 N.W.2d 61, 1968 N.D. LEXIS 65 (N.D. 1968).

Opinion

TEIGEN, Chief Justice.

The defendant sureties have appealed from the adverse judgment in a Capehart bond suit brought by a materialman who furnished materials on a housing project authorized under the Capehart Housing Act. The case was tried to the court and demand has been made ■ for trial de novo in this Court.

The plaintiff, Robertson Lumber Company, which is the materialman, instituted this suit against Progressive Contractors, Inc., the prime contractor, and its two payment and performance bond sureties, the Continental Casualty Company and the Fidelity and Casualty Company of New York, for materials furnished several subcontractors of the prime contractor, for *64 which it had not received payment. The defendant Progressive Contractors, Inc. was the prime contractor for the construction of 744 housing units at the United States Air Force Base, at Grand Forks, North Dakota, authorized under the Cape-hart Housing Act. The defendant sureties furnished payment and performance bonds as required under the Capehart Housing Act, as amended, 42 U.S.C.A. Sec. 1594 (a). The defendant Progressive Contractors, Inc. failed to answer the complaint and judgment has been entered against it by default. The defendant sureties answered setting out several defenses.

When the case came on for trial, the plaintiff and the defendant sureties stipulated the facts. The stipulation of facts admits that the plaintiff furnished the materials described in its complaint and that the value of the unpaid materials furnished was the sum of $13,780.08, and the stipulation provides that if judgment is entered for the plaintiff, it shall be entered for that amount.

It was also stipulated that the defendant Progressive Contractors, Inc. abandoned the building project on May 20, 1960, and notice as required by Sec. 4(a) of the payment and performance bond was sent to the principal alone [Progressive Contractors, Inc.] on July 22, 1960, which was within 90 days of the furnishing of the last materials but that no notice was given to the sureties. It was also stipulated that on April 20, 1961, (more than 90 days after the last materials were furnished) the plaintiff mailed notice as provided by Sec. 4(a) of the bond provisions to the required parties, and that such notices contained the proper information.

The defendant sureties in this appeal raise three principal issues which we must consider: first, jurisdiction over the subject matter; they contend the federal courts have exclusive jurisdiction in suits on Capehart bonds; second, the matter is res judicata; and, third, failure to give notice in accordance with the bond terms.

Thus, although the case is before us for trial de novo, there is no issue of fact for determination on this appeal. The issues raised are purely questions of law.

HISTORY

This case and a companion case commenced by the same plaintiff but against Wilshire Contractors, Inc., and Continental Casualty Company, have followed a parallel course through the federal and state courts before this appeal was taken.

The two companion actions were first brought under the Miller Act, as provided by 40 U.S.C.A. Sec. 270b, in the Federal District Court, Northeastern Division in December of 1960. At a pretrial conference, the facts being stipulated and the contractor having defaulted, the issue between the plaintiff and the defendant sureties was narrowed to a single question of law. The question presented was whether the plaintiff had a right to maintain the actions for recovery upon Capehart payment and performance bonds when the notice requirements of the Miller Act had been complied with, but the notice requirements of the bonds had not been met. The district court rendered its decision in favor of the plaintiff. It held that the plaintiff had a right to sue upon the payment bond if it had complied with the provisions of the Miller Act, 40 U.S.C.A. Secs. 270a-270d, which provides for a single notice. The Capehart bond provisions provided notice requirements as follows:

“4. No suit or action shall be commenced hereunder by any claimant,
(a) Unless claimant shall have given written notice to any two of the following: The Principal, any one of the Obligees, or the Sureties above named, * * * ”

United States for Use and Benefit of Robertson Lumber Company v. Progressive Contractors, Inc., 196 F.Supp. 171 (D.C.N.D.1961).

*65 The opinion of the district court was rendered on May 24, 1961. Prior to that time, to wit: on April 20, 1961, the plaintiff mailed notices, as required by Sec. 4(a) of the bond, to the required parties as provided by the bond provisions. The decision of the federal district court was appealed to the Court of Appeals of the Eighth Circuit, and that court rendered its decision on June 30, 1962. (See Continental Casualty Company v. United States for Use and Benefit of Robertson Lumber Company, 305 F.2d 794 (8th Cir. 1962. (Cert. denied, 371 U.S. 922, 83 S.Ct. 290, 9 L.Ed.2d 231.) It reversed the federal district court and held that the notice provisions of the Miller Act did not govern in a suit on a Capehart bond. The circuit court ordered the judgment appealed from reversed and the cause was remanded to the district court with directions to dismiss the complaint.

While the federal cases were pending and after due notices had been given on April 20, 1961, the plaintiff commenced separate actions on the claims in the state court. These actions were brought on the bonds under the provisions of 28 U.S.C.A. Sec. 1352, providing concurrent jurisdiction in the state and federal courts. On May 15, 1961, counsel for the plaintiff and counsel for the defendant sureties stipulated “ * * * that the above captioned matter shall be and hereby is removed * * * to United States Federal District Court for the District of North Dakota, Northeastern Division * * Pursuant to the stipulation, the Honorable Ronald N. Davies, Judge of the Federal District Court, ordered that the two cases be removed to the United States Federal Court for the District of North Dakota, Northeastern Division. This order was made on May 18, 1961. On the same date, the defendants Continental Casualty Company and Fidelity and Casualty Company filed their separate answers in federal court. No answer or other responsive pleading has ever been received, served, or filed by either of the defendants Progressive Contractors, Inc., or Wilshire Contractors,. Inc.

The defendant sureties filed motions for summary judgments on February 26, 1963. Following oral arguments on said motions- and the submission of briefs, Judge Davies,, on July 17, 1963, entered his orders denying both motions for summary judgments and directed that both actions be tried in the federal court on the merits.

The issues raised in the motions for summary judgments were the claims that the plaintiff had been non-suited in both cases commenced in federal court under the identical fact situation and therefore, the issues were res judicata. However, the federal district court found that the notice requirements contained in the bonds, as a condition precedent to an action on the bonds, were questions of fact for determination and that if the plaintiff can establish compliance, the actions may be decided on the merits.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hanneman v. Nygaard
2010 ND 113 (North Dakota Supreme Court, 2010)
Byron's Construction Co. v. North Dakota Department of Transportation
463 N.W.2d 660 (North Dakota Supreme Court, 1990)
Red River Commodities, Inc. v. Eidsness
459 N.W.2d 805 (North Dakota Supreme Court, 1990)
Elkins Manor Associates v. Eleanor Concrete Works, Inc.
396 S.E.2d 463 (West Virginia Supreme Court, 1990)
Harrison v. State
791 P.2d 359 (Court of Appeals of Alaska, 1990)
First State Bank of New Rockford v. Anderson
452 N.W.2d 90 (North Dakota Supreme Court, 1990)
Modern Supply Co. v. Federal Savings & Loan Insurance
748 P.2d 251 (Court of Appeals of Washington, 1987)
Schiele v. First National Bank of Linton
404 N.W.2d 479 (North Dakota Supreme Court, 1987)
Thoring v. LaCounte
733 P.2d 340 (Montana Supreme Court, 1987)
Peacock v. Sundre Township
372 N.W.2d 877 (North Dakota Supreme Court, 1985)
Farmers State Bank v. Slaubaugh
366 N.W.2d 804 (North Dakota Supreme Court, 1985)
Oakes Farming Ass'n v. Martinson Bros.
318 N.W.2d 897 (North Dakota Supreme Court, 1982)
Blackhawk Heating & Plumbing Co. v. Seaboard Surety Co.
534 F. Supp. 309 (N.D. Illinois, 1982)
Nodland v. Nokota Co.
314 N.W.2d 89 (North Dakota Supreme Court, 1981)
Becker Ex Rel. Becker v. Doubek
292 N.W.2d 72 (North Dakota Supreme Court, 1980)
State v. Safeco Insurance Companies
396 N.E.2d 794 (Ohio Court of Appeals, 1978)
Rugby Milling Co. v. Logosz
261 N.W.2d 662 (North Dakota Supreme Court, 1977)
Dolajak v. State Automobile & Casualty Underwriters
252 N.W.2d 180 (North Dakota Supreme Court, 1977)

Cite This Page — Counsel Stack

Bluebook (online)
160 N.W.2d 61, 1968 N.D. LEXIS 65, Counsel Stack Legal Research, https://law.counselstack.com/opinion/robertson-lumber-co-v-progressive-contractors-inc-nd-1968.