Elkins Manor Associates v. Eleanor Concrete Works, Inc.

396 S.E.2d 463, 183 W. Va. 501, 13 U.C.C. Rep. Serv. 2d (West) 75, 1990 W. Va. LEXIS 149
CourtWest Virginia Supreme Court
DecidedJuly 25, 1990
Docket19272
StatusPublished
Cited by9 cases

This text of 396 S.E.2d 463 (Elkins Manor Associates v. Eleanor Concrete Works, Inc.) is published on Counsel Stack Legal Research, covering West Virginia Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Elkins Manor Associates v. Eleanor Concrete Works, Inc., 396 S.E.2d 463, 183 W. Va. 501, 13 U.C.C. Rep. Serv. 2d (West) 75, 1990 W. Va. LEXIS 149 (W. Va. 1990).

Opinion

MILLER, Justice:

Elkins Manor Associates and Elkins Man- or, Inc., appeal from a final order of the Circuit Court of Randolph County, entered on January 17, 1989, which granted Eleanor Concrete Works, Inc., United States Fidelity and Guaranty Company, and Lawrence Butcher a directed verdict. We have reviewed the record, and we find that the trial court erred in directing a verdict. Accordingly, we reverse and remand the case for further proceedings consistent with this opinion.

I.

Elkins Manor Associates is a limited partnership which was formed to provide government subsidized housing for the elderly in Randolph County. Elkins Manor, Inc., is one of the general partners of the limited partnership. 1 After locating a site which complied with the Federal Housing Authority (FHA) requirements, Elkins Manor secured a twelve-month construction loan for $3,099,500 from the West Virginia Housing Development Fund (WVHDF). 2 In return, Elkins Manor agreed to comply with the guidelines of WVHDF and FHA. The controversy in this case involves Elkins Manor and one of the contractors on the housing project, Eleanor Concrete Works, Inc. (Eleanor).

*504 Elkins Manor’s evidence at trial revealed the following. On July 26, 1979, Elkins Manor and Eleanor entered into a contract in which Eleanor agreed to manufacture, deliver, and install pre-cast prestressed concrete planks for use as the floors and ceilings in the housing project. Eleanor was to provide the concrete for the first floor within eighteen days after the shop drawings had been approved and a one-half floor shipment of concrete every ten days thereafter. 3 Elkins Manor agreed to pay Eleanor a total of $159,400 for this service. The contract further required Eleanor to obtain a performance bond guaranteeing the completion of its work. Eleanor obtained a performance bond from United States Fidelity and Guaranty Company (USF & G).

The first floor of the project was installed by Eleanor in September, 1979. In October, 1979, inspectors from FHA discovered that the installed planks had not been anchored in accordance with the design specifications of the project. 4 Upon closer examination, the inspectors observed that several of the planks were cracked and warped. Believing that the planks were unsafe, the inspectors gave Elkins Manor two alternatives: (1) to remove all of the planks which had already been installed, or (2) to test the planks to assure that they complied with the standards prescribed by the American Concrete Institute (ACI). Both FHA and WVHDF require that all subsidized projects comply with these standards and this requirement was a part of Eleanor’s contract. 5 Eleanor decided to have the concrete tested.

Meanwhile, representatives from WVHDF inspected Eleanor’s plant in Putnam County and determined that the plant’s manufacturing process did not comply with the standards set by ACI or by the licensor of the product, Spiroll. WVHDF refused to allow any of Eleanor’s planks to be used on the Elkins Manor project until Eleanor obtained approval from both the ACI and Spiroll. Eleanor did not obtain the necessary approval until January, 1980.

During February, 1980, delivery and installation of the concrete planks proceeded relatively on time. In March, Eleanor experienced financial difficulties and did not have any trucks in which to make the deliveries to the Elkins Manor project. 6 Because of time limitations in its construction financing, Elkins Manor was forced to hire a trucking company to load and deliver the planks. Often, when a truck was sent down to pick up the concrete planks, the truck would return empty or half full. Eleanor also failed to provide either the manpower to install the planks or the crane necessary to remove them from the truck onto the construction site, as required by its contract. 7 Consequently, Elkins Manor had to rent its own crane and use its own personnel to install the planks. Installation of the planks required removing them *505 from the truck, leveling them, anchoring the slabs to the outside walls, and grouting between the planks.

Although Elkins Manor attempted to secure another company to make the pre-cast concrete, because of the time constraints of the construction loan, the estimates provided by the other companies were very uneconomical. According to Daniel Siegel, president of Elkins Manor, a decision was made to “limp along” with Eleanor even though it was not fulfilling its contractual obligations. Elkins Manor frequently notified USF & G of the difficulties they were experiencing with Eleanor. These notices included at least three phone calls to the insurance company and two responses to status inquiries, all of which informed USF & G that Eleanor was failing to comply with the terms of the contract. USF & G did not respond to any of these notices.

After the project was completed in December, 1980, Elkins Manor filed suit against Eleanor and USF & G for breach of the contract. Eleanor filed a counterclaim seeking payment for the remaining amount owed on the contract. 8 The trial commenced on June 21, 1988. At the close of Elkins Manor’s case, Eleanor and USF & G filed motions for directed verdict. The trial court granted these motions, finding that Elkins Manor provided insufficient evidence that Eleanor had breached the contract. Alternatively, the trial court found that if a breach had occurred, it was excused pursuant to Section 615(a) of the Uniform Commercial Code (UCC), W.Va. Code, 46-2-615(a).

Moreover, the trial court found that El-kins Manor failed to provide adequate or timely notice to USF & G of Eleanor’s default; therefore, it granted USF & G’s motion for directed verdict. Finally, the trial court ruled that Eleanor’s counterclaim for the remaining amount due under the contract should be offset by Elkins Manor’s cost in shipping, installing, anchoring, and grouting the concrete planks. El-kins Manor moved for a new trial, and, in an order entered on January 17, 1989, the trial court denied this motion.

II.

We have traditionally held that a verdict should not be directed against a plaintiff in a civil case unless he has failed to present a prima fade case. See Jividen v. Legg, 161 W.Va. 769, 245 S.E.2d 835 (1978). In determining whether a prima fade case has been established, it is incumbent upon the trial judge to weigh the evidence in the plaintiff’s favor. Blair v. Preece, 176 W.Va. 532, 346 S.E.2d 50 (1986), cert. denied, 492 U.S. 923, 109 S.Ct. 3253, 106 L.Ed.2d 599 (1989). We explained this more fully in the Syllabus of Nichols v. Raleigh-Wyoming Coal Co., 112 W.Va. 85, 163 S.E. 767 (1932):

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mid-State Surety Corp. v. Thrasher Engineering, Inc.
575 F. Supp. 2d 731 (S.D. West Virginia, 2008)
Waddy v. Riggleman
606 S.E.2d 222 (West Virginia Supreme Court, 2004)
Capitol Chrysler-Plymouth, Inc. v. Megginson
532 S.E.2d 43 (West Virginia Supreme Court, 2000)
Goldberg. Marchesano. Kohlman. Inc. v. Old Republic Surety Co.
727 A.2d 858 (District of Columbia Court of Appeals, 1999)
Adkins v. Chevron, USA, Inc.
485 S.E.2d 687 (West Virginia Supreme Court, 1997)
Lane Construction Corp. v. Trading Merchandising Co.
34 Va. Cir. 383 (Stafford County Circuit Court, 1994)
Bowling v. Ansted Chrysler-Plymouth-Dodge, Inc.
425 S.E.2d 144 (West Virginia Supreme Court, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
396 S.E.2d 463, 183 W. Va. 501, 13 U.C.C. Rep. Serv. 2d (West) 75, 1990 W. Va. LEXIS 149, Counsel Stack Legal Research, https://law.counselstack.com/opinion/elkins-manor-associates-v-eleanor-concrete-works-inc-wva-1990.