Ireland's Lumber Yard v. Progressive Contractors, Inc.

122 N.W.2d 554, 1963 N.D. LEXIS 95
CourtNorth Dakota Supreme Court
DecidedJune 14, 1963
Docket8048
StatusPublished
Cited by24 cases

This text of 122 N.W.2d 554 (Ireland's Lumber Yard v. Progressive Contractors, Inc.) is published on Counsel Stack Legal Research, covering North Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ireland's Lumber Yard v. Progressive Contractors, Inc., 122 N.W.2d 554, 1963 N.D. LEXIS 95 (N.D. 1963).

Opinion

TEIGEN, Judge.

Plaintiff, Ireland’s Lumber Yard, Inc., a materialman, instituted this suit against the prime contractor, Progressive Contractors, Inc., and its two payment and performance bond sureties for materials furnished. The bonds were executed to secure payment for all labor and materials furnished in the prosecution of the work covered by the principal contract calling for the construction of 744 housing units for military personnel at the United States Air Force Base at Grand Forks, North Dakota.

The complaint alleges the supplying of material to the prime contractor and some of its subcontractors and their failure to pay for them. The prime contractor, Progressive Contractors, failed to answer and judgment was entered against it by default. The sureties, Continental Casualty Company and Fidelity and Casualty Company of New York, answered. In their answer they admit construction contracts were entered into for the construction of the housing units, the execution of the payment and performance bonds and that the plaintiff gave the notices of claims. However, they placed the plaintiff on its proof as to the material supplied, the value thereof, the claim of nonpayment, and denied the other averments of the complaint.

Further answering the sureties allege the complaint does not state a cause of action. The defendant sureties also moved the court to dismiss the action for lack of jurisdiction.

It is undisputed that on or about August 1, 1958, Progressive Contractors, as prime contractor, entered into contracts with the Department of the Air Force and seven housing corporations for the construction of 744 housing units at the Grand Forks Air Base; that to secure the faithful performance of these contracts the prime contractor, as principal, and the defendant sureties executed 100% payment and performance bonds and delivered them to the seven housing corporations. These bonds were in the aggregate amount of over twelve million dollars.

The district court tried the case without a jury. It found in favor of the plaintiff and awarded judgment against the prime contractor and the defendant sureties in the amount of $9,723.03, plus interest at 4% per annum from May 21, 1960. The sureties have appealed and demand trial de novo.

The defendant sureties specify it was error for the court to hold it had jurisdiction as the project was a “public works” and jurisdiction was limited to the federal court pursuant to 40 U.S.C.A. §§ 270a and 270b (Miller Act); that the trial judge erred in failing to disqualify himself for having prematurely ruled in the case and, lastly, if the court had jurisdiction that it erred in holding the plaintiff was entitled *557 to recover the additional sum of $8,045.69 as it had failed to comply with the terms of the bond with respect to timeliness in giving notice of claim.

The situation presented arises as a result of the construction of housing for military •personnel stationed at the Grand Forks Air Force Base at Grand Forks, North Dakota, under the housing program authorized by what is commonly known as the Capehart .Housing Act, as amended, 42 U.S.C.A. § 1594. Its purposes and objects are succinctly stated in Continental Casualty Company v. United States, 8 Cir., 305 F.2d 794, as follows:

“The purpose of the Capehart Act was to provide urgently needed housing for military personnel on Government property, and while Capehart housing is undoubtedly ‘Government housing,’ Capehart construction differs from conventional Government construction in certain significant respects.
“Ordinarily, federal public works are paid for both initially and finally with federal funds. Capehart housing, on the other hand, initially is built and financed by private capital, although loans made by financial institutions to finance the construction are fully insured by the Federal Housing Administration. Both the Department of Defense and the Federal Housing Administration are concerned with the administration of the Capehart program, and the Federal Housing Commissioner has been authorized to promulgate regulations concerning the program, 12 U.S. ■C.A. § 1748f, which authority has been •exercised, see 24 C.F.R. Part 292a.
“The Capehart Act now requires both ■payment and performance bonds, and standard forms of those bonds have 'been worked out by the Department of Defense and the Federal Housing Administration, and all Capehart housing •contracts call for the giving of those particular bonds, as was done in this ■case.
“With some allowance for possible oversimplification, a typical Capehart project may be described substantially as follows:
“A building contractor desiring to build Capehart housing and who has been the successful bidder for such housing, and who has made satisfactory arrangements to secure private financing, forms a corporation to take a long term lease on the Government property on which the housing is to be constructed and to execute a mortgage on the leasehold estate to the financial institution which is to lend the money required for construction purposes. This corporation, which is at all times under complete Government control, does not do the actual building of the housing units. That is done by the contractor under contract with the Government and with the corporation. The functions of the corporation are limited and to some extent nominal. It takes the lease and executes the mortgage and is a party to the construction contract. Further, it is one of the obligees named in the contractor’s performance and payment bonds. In the statute, regulations, and contract documents the contractor is called the ‘eligible bidder,’ the corporation is called the ‘mortgagor-builder,’ and the lending agency is called the ‘mortgagee.’
“As the project is completed, the housing units are turned over to and operated by the Government and are occupied by military personnel. Quarters allowances previously paid to such personnel are retained by the Government and used to pay off the mortgage. When the mortgage is finally retired, the lease to the ‘mortgagor-builder’ is terminated, and that corporation is dissolved, leaving title to the housing in the Government.
“The contractor derives his profit from doing the actual building of the housing. From the Government’s *558 standpoint, advantages are seen in that federal funds are not expended for initial construction and, while the housing will be paid for eventually with federal money, that money would have been expended in any event as quarters allowances for the affected service personnel. In addition, the program may be supposed to provide a stimulus for private industry and capital.”

The bond in this suit was executed on a form specifically described by the contract for the construction of the housing, which form had been adopted by the Department of Defense and by the Federal Housing Commissioner. The bonds contained certain provisions for notice to be given by laborers or materialmen as a condition precedent to commencing action on the bond.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rath v. Rath
2016 ND 105 (North Dakota Supreme Court, 2016)
Datz v. Dosch
2014 ND 102 (North Dakota Supreme Court, 2014)
Alerus Financial, N.A. v. Marcil Group Inc.
2011 ND 205 (North Dakota Supreme Court, 2011)
Wong v. State
2011 ND 201 (North Dakota Supreme Court, 2011)
Sargent County Bank v. Wentworth
500 N.W.2d 862 (North Dakota Supreme Court, 1993)
Red River Commodities, Inc. v. Eidsness
459 N.W.2d 805 (North Dakota Supreme Court, 1990)
Szarkowski v. Reliance Insurance Co.
404 N.W.2d 502 (North Dakota Supreme Court, 1987)
State v. Safeco Insurance Companies
396 N.E.2d 794 (Ohio Court of Appeals, 1978)
Permann v. Knife River Coal Mining Co.
180 N.W.2d 146 (North Dakota Supreme Court, 1970)
Giese v. Engelhardt
175 N.W.2d 578 (North Dakota Supreme Court, 1970)
Robertson Lumber Co. v. Progressive Contractors, Inc.
160 N.W.2d 61 (North Dakota Supreme Court, 1968)
Tropicair Manufacturing Corp. v. Coite Somers Co.
96 P.R. 140 (Supreme Court of Puerto Rico, 1968)
Lillethun v. Tri-County Electric Cooperative, Inc.
152 N.W.2d 147 (North Dakota Supreme Court, 1967)
B. C. Richter Contracting Co. v. Continental Casualty Co.
230 Cal. App. 2d 491 (California Court of Appeal, 1964)

Cite This Page — Counsel Stack

Bluebook (online)
122 N.W.2d 554, 1963 N.D. LEXIS 95, Counsel Stack Legal Research, https://law.counselstack.com/opinion/irelands-lumber-yard-v-progressive-contractors-inc-nd-1963.