United States v. Western Surety Company

CourtDistrict Court, D. North Dakota
DecidedFebruary 7, 2020
Docket1:18-cv-00174
StatusUnknown

This text of United States v. Western Surety Company (United States v. Western Surety Company) is published on Counsel Stack Legal Research, covering District Court, D. North Dakota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. Western Surety Company, (D.N.D. 2020).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF NORTH DAKOTA

United States for the Use and Benefit of ) Thomas Industrial Coatings; and ) Thomas Industrial Coatings, ) ) ORDER DENYING MOTION Plaintiffs, ) FOR SUMMARY JUDGMENT ) vs. ) ) Western Surety Company, ) Case No. 1:18-cv-00174 ) Defendant. ) ______________________________________________________________________________

This case arises from a disagreement regarding payment for sandblasting and painting work performed on the Garrison Dam. The Plaintiffs, United States for the Use and Benefit of Thomas Industrial Coatings and Thomas Industrial Coatings (“TIC”), claim that the Defendant, Western Surety Company (“Western”), breached an obligation to pay TIC for that work under a subcontract payment bond. Western counters with this motion for summary judgment, filed on November 9, 2018, contending that TIC failed to tender notice of its claim, as the bond’s terms require, before filing suit. Doc. Nos. 23-24. TIC responded in opposition to the motion on November 30, 2018, and Western filed a reply brief on December 14, 2018. Doc. Nos. 28, 32-33. For the reasons below, Western’s motion for summary judgment is denied. I. BACKGROUND The controversy began to form in 2012, when the U.S. Army Corps of Engineers (“Corps”) designated S&S Coatings, Inc. (“S&S”) to act as the general contractor for a project on the Garrison Dam. Doc. No. 1, ¶ 3. Upon receiving the contract, S&S obtained a Miller Act1 payment bond from Western (“S&S Bond”). Id. ¶ 4. That bond obligated Western to pay subcontractors S&S hired for the labor and materials they contributed to the project if S&S failed to do so. Id. With the bond in hand, S&S subcontracted part of the project to Dix Corporation (“Dix”). Id. ¶ 6. Western issued a separate subcontract payment bond to Dix (“Dix Bond”), similarly promising to

cover labor and material costs, this time for second-tier subcontractors, if Dix did not. Id. ¶ 8. Dix then subcontracted gate sandblasting and painting work to TIC. Id. ¶ 6. TIC furnished labor and materials in furtherance of the project, completing its work on August 22, 2017.2 Id. ¶¶ 14-15. Two distinct, but related, series of events prompted TIC to file the present action against Western. First, TIC had instituted a separate lawsuit against Dix regarding the Garrison Dam project in Washington state court on August 7, 2017, asserting breach of contract, fraud, and breach of warranty claims. See Doc. No. 30-25. On August 23, 2017, Dix informed TIC that it intended to withhold $525,0003 in funds owed to TIC to cover litigation expenses in the Washington lawsuit. Doc. No. 30-5. On September 5, 2017, TIC sent a letter to representatives of both Dix and S&S

challenging Dix’s decision to withhold the funds. Doc. No. 30-6. In the letter, TIC referenced the $525,000 amount withheld and stated, “Dix’[s] action . . . will, unless immediate action is taken to prevent it, give rise to TIC taking legal action involving not only Dix, but also [S&S] . . . and

1 The Miller Act mandates that general contractors on federal government projects furnish both a performance bond (insuring that the work will be completed satisfactorily) and a payment bond (insuring that the general contractor will pay its subcontractors for their work). 40 U.S.C. § 3131. The Act authorizes subcontractors and, in more limited circumstances, second-tier subcontractors to bring a civil action on the general contractor’s payment bond. 40 U.S.C. § 3133(b). 2 Western contests this date, but not for purposes of the current motion. Doc. No. 24, p. 3. 3 This sum had apparently diminished to $323,317.95 by November 16, 2017. Doc. No. 30-21. The record does not clarify this discrepancy. the sureties on this project.” Id. at 2. TIC also requested that S&S and Dix “notify the sureties on this project of TIC’s claim.” Id. at 3. Second, due to unforeseen delays and cost overruns associated with the project, S&S, in conjunction with Dix and TIC, submitted three claims to the Corps for equitable adjustment – in other words, claims for more money than what the original contract allowed for to compensate the

contractors for the extra work required to finish the project. Doc. No. 30-3. The three claims totaled $3,124,056: $1,077,826 for “Paint Thickness”; $1,349,783 for “Stoplog Design Review/Delay”; and $696,447 for “Out of Scope Dewatering.” Id. On August 21, 2017, the Corps “found partial merit” to the claims and proposed to settle them. Id. S&S accepted the Corps’ offer and received $1,410,000. Doc. No. 30, ¶ 16. Divvying up the $1.41 million the Corps paid to S&S, Dix sent an email on September 6, 2017—the day after TIC sent the letter regarding the Washington litigation—that proposed to pay TIC $419,089. Doc. No. 30-4. The payment breakdown earmarked TIC to receive $328,947 for the “Paint Thickness” claim; $90,142 for the “Out of Scope Dewatering” claim; and nothing for

the “Stoplog Design Review/Delay” claim. Id. On October 5, 2017, Dix sent TIC a proposed change order to effectuate the $419,089 payment. Doc. No. 30-13. TIC then objected to the change order in a letter sent to representatives of both Dix and S&S dated October 9, 2017. Doc. No. 30-14. In an email sent two days later, TIC detailed its objections. Doc. No. 30-16, p. 1. TIC contended that it was owed a total of $659,534 for the “Paint Thickness” and “Out of Scope Dewatering” claims, not the proposed $419,089. Id. As support, TIC pointed to previous statements Dix and S&S had made that represented TIC would receive a larger percentage of the Corps’ equitable adjustment payment. Id. TIC also argued that S&S and Dix had improperly refused to allocate any funds to TIC for the “Stoplog Design Review/Delay” claim. Id. The email did not specify what TIC believed it was owed on this final claim. Because of the dispute, TIC requested that S&S and Dix withhold the $419,089 payment and again notify their sureties. Doc. No. 30-14. Western, as the surety on both the S&S Bond and the Dix Bond, sent two substantively

identical letters to TIC in November 2017 confirming receipt of TIC’s September 5, 2017 letter. Doc. Nos. 30-20, 30-23. In particular, a November 29, 2017 letter regarding the Dix Bond stated, “Western Surety Company is in receipt of your correspondence dated September 5, 2017 claiming that Thomas Industrial Coatings, Inc., is due payment for labor and material provided to the [Garrison Dam] Project.” Doc. No. 30-23. Both letters sought additional documentation from TIC regarding its claims, noting the letters were sent for investigative purposes and did not confirm compliance with the bonds’ requirements. Doc. Nos. 30-20, 30-23. TIC did not further respond to Western’s letters. The Plaintiffs filed this action on August 15, 2018, seeking “in excess of $2,244,817.46”

in damages. Doc. No. 1, ¶ 18. Count I alleges that TIC is entitled to payment from the S&S Bond under the Miller Act, and Count II alleges a state-law claim for breach of Western’s obligation on the Dix Bond. Id. ¶¶ 19-31. On January 2, 2019, the Plaintiffs moved to voluntarily dismiss Count I after resolving their claim against S&S. Doc. No. 34. The Court entered an order to that effect on January 17, 2019. Doc. No. 35. Remaining for disposition is Western’s motion for summary judgment on Count II. II. DISCUSSION A brief word on jurisdiction is necessary at the outset. With the dismissal of Count I, federal question jurisdiction pursuant to 28 U.S.C. § 1331 is no longer available.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Torgerson v. City of Rochester
643 F.3d 1031 (Eighth Circuit, 2011)
Nunn v. Noodles & Co.
674 F.3d 910 (Eighth Circuit, 2012)
Paul Schilf v. Eli Lilly & Company
687 F.3d 947 (Eighth Circuit, 2012)
Peoples State Bank of Truman, Inc. v. Molstad Excavating, Inc.
2006 ND 183 (North Dakota Supreme Court, 2006)
Larson v. Granite Re, Inc.
532 F.3d 724 (Eighth Circuit, 2008)
Robertson Lumber Co. v. Progressive Contractors, Inc.
160 N.W.2d 61 (North Dakota Supreme Court, 1968)
Ireland's Lumber Yard v. Progressive Contractors, Inc.
122 N.W.2d 554 (North Dakota Supreme Court, 1963)
Johnson v. Securitas Security Services USA, Inc.
769 F.3d 605 (Eighth Circuit, 2014)
Chornuk v. Nelson
2014 ND 238 (North Dakota Supreme Court, 2014)
Stuart C. Irby Company, Inc. v. Brandon Tipton
796 F.3d 918 (Eighth Circuit, 2015)
TCF National Bank v. Market Intelligence, Inc.
812 F.3d 701 (Eighth Circuit, 2016)
Bonnie Dick v. Dickinson State University
826 F.3d 1054 (Eighth Circuit, 2016)
Minard v. Moore (In Re Estate of Moore )
2018 ND 221 (North Dakota Supreme Court, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
United States v. Western Surety Company, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-western-surety-company-ndd-2020.