LaSalla v. Doctor's Associates, Inc.

898 A.2d 803, 278 Conn. 578, 2006 Conn. LEXIS 198
CourtSupreme Court of Connecticut
DecidedJune 13, 2006
DocketSC 17483
StatusPublished
Cited by27 cases

This text of 898 A.2d 803 (LaSalla v. Doctor's Associates, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Connecticut primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
LaSalla v. Doctor's Associates, Inc., 898 A.2d 803, 278 Conn. 578, 2006 Conn. LEXIS 198 (Colo. 2006).

Opinion

Opinion

BORDEN, J.

The principal issue in this appeal is whether a voluntary arbitration panel is bound to apply the doctrine of claim preclusion to a second arbitration claim involving the interpretation of the same provision of a contract between the same parties. The defendant, Doctor’s Associates, Inc., appeals1 from the judgment of the trial court confirming an arbitration award in favor of the plaintiff, Michael J. LaSalla, and denying the defendant’s application to vacate the award. The defendant claims that the award: (1) violated public policy; and (2) was issued in manifest disregard of the law. We disagree and, accordingly, we affirm the judgment of the trial court.

The parties entered into a voluntary, unrestricted arbitration proceeding. The arbitration panel ruled in favor of the plaintiff. The plaintiff applied to the trial court to confirm the award, and the defendant applied to vacate the award. The trial court rendered judgment granting the plaintiffs application to confirm and denying the defendant’s application to vacate the award. This appeal followed.

Certain of the facts, and the following procedural history, are undisputed. The defendant is a franchiser of Subway sandwich shops that contracts with development agents, who, in turn, develop and support Subway stores in particular areas. On February 1, 1986, the plaintiff and the defendant entered into a development [581]*581agent agreement pursuant to which the plaintiff became a development agent for northwestern Florida (plaintiffs territory), and the defendant agreed to pay to the plaintiff one third of the royalties and transfer fees that it receives from the Subway stores located in the plaintiffs territory, subject, however, to a reduction based on a modifier. Because, prior to the execution of the agreement, there were already twenty-nine Subway stores in the plaintiffs territory, the modifier was designed to reduce the payments from the defendant to the plaintiff to reflect those previously established stores.2

The agreement has a broad, unrestricted arbitration clause, requiring that “any controversy or claim arising out of or relating to this Agreement or the breach thereof shall be settled by arbitration in accordance with the Commercial Rules of the American Arbitration Association . . . .” In 1998, the plaintiff filed a claim for arbitration before the American Arbitration Association (1998 arbitration) regarding several matters in dispute between the parties under the agreement. Among the items in dispute was the interpretation of the modifier as applied to stores that were in existence at the time of the execution of the agreement, but that subsequently [582]*582were “ ‘permanently closed’ . . . .”3 The plaintiff presented the arbitrators in that proceeding with an exhibit indicating that, of the twenty-nine stores in existence on February 1, 1986, six had been permanently closed and nine had been relocated. On the basis of this exhibit, the plaintiff claimed that the denominator of the modifier should be reduced by the six permanently closed stores4 and, therefore, the calculation of the modifier that the defendant had been using should be changed to reflect the larger figure claimed by the plaintiff. In this connection, moreover, although the plaintiff sought money damages with respect to his other claims in the arbitration, as to the modifier issue he sought only a declaration of the modifier’s proper interpretation and application, not money damages.

The panel in the 1998 arbitration agreed with the plaintiff, and, in an award dated June 14,2000, declared: “The denominator of the modifier . . . shall be reduced for each store that was in place when the [agreement] was signed and thereafter permanently closed, so that the modifier will be determined in the manner suggested by [the plaintiff], reflected on [his exhibit, which chose a measurement date of January 30, 1999], that produces a modifier of 0.8642857, rather than in the manner suggested by [the defendant], that produces a modifier of 0.8214286.” The plaintiff then applied to the Superior Court to vacate the panel’s award, based upon two other issues in the arbitration upon which he had not prevailed. The defendant correspondingly applied to the court to confirm the award in [583]*583its entirety. In June, 2002, the trial court, Alander, J., denied the plaintiffs application to vacate and granted the defendant’s application to confirm the award. The plaintiff did not appeal further.

In November, 2002, the plaintiff filed the arbitration claim that is involved in the present case before the American Dispute Resolution Center.5 In his prayer for relief, the plaintiff sought “the enforcement of’ the agreement and of the award in the 1998 arbitration. He stated that the award in the 1998 arbitration “provided relief to [him] in the form of a declaration of certain rights that arise under the [agreement]. Based on that declaration, [the plaintiff] now seeks an award of money damages, legal fees, interest and cost of this arbitration.” He quoted the award in the 1998 arbitration regarding the modifier. He claimed that, since February 1, 1986, when the agreement was executed, until the award in the 1998 arbitration, the defendant had underpaid the plaintiff in breach of the agreement. He stated that, “[b]ased on the [award in the 1998 arbitration], it is now clear that the [m]odifier clause should have been interpreted to be flexible and subject to adjustment, taking into consideration the criteria set forth in the [agreement],” and that as a result of the defendant’s “misapplication of the [m]odifier, [the plaintiff] has been underpaid for [fourteen] years.” He stated, further, that, even after the 1998 arbitration, the defendant “has refused to make good on the unpaid balance in conformity with the [a]ward [in the 1998 arbitration],” and that the defendant had taken the position that “the panel’s interpretation of the [m]odifier only applies prospectively, from the date of the [a]ward forward.” Finally, the plaintiff sought “an appropriate award of money damages,” and “a declaration that the determina[584]*584tion of the net number of units added to the [t]erritory is governed by the contractual definition of the term ‘unit’ so that in the future, the parties will be able to conduct business without further disputes on the application of this clause. For this purpose, a ‘unit’ should be taken out of the [mjodifier calculation when it closes at one location and ceases operations at that location, as described in the [agreement].”

The defendant moved the arbitration panel to dismiss the arbitration demand on the grounds of, among other things,6 res judicata, or claim preclusion. The defendant presented a brief to the panel, fully explaining the factual background of the dispute between the parties, the ruling in the 1998 arbitration, the ruling of the court confirming that award, and the legal bases for its motion. In response, the plaintiff filed an objection to the motion, presenting his factual and legal arguments in favor of continuing the arbitration. The panel denied the motion to dismiss.

Ultimately, the panel issued two interim awards and a final award. The substance of the awards was as follows: (1) the award in the 1998 arbitration was retroactive to the execution of the agreement, but damages would be recoverable by the plaintiff “only from June 15, 1992”;7

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Reclaimant Corp. v. Deutsch
211 A.3d 976 (Supreme Court of Connecticut, 2019)
Cimmino v. Marcoccia
211 A.3d 1013 (Supreme Court of Connecticut, 2019)
A1Z7, LLC v. Dombek
205 A.3d 740 (Connecticut Appellate Court, 2019)
Russo v. GMAC Mortgage, LLC
Second Circuit, 2013
Bristol Heights Associates, LLC v. Chicago Title Insurance
950 F. Supp. 2d 408 (D. Connecticut, 2013)
Marques v. Allstate Insurance
58 A.3d 393 (Connecticut Appellate Court, 2013)
Bruno v. Geller
46 A.3d 974 (Connecticut Appellate Court, 2012)
Perez-Dickson v. City of Bridgeport
43 A.3d 69 (Supreme Court of Connecticut, 2012)
Close, Jensen & Miller, P.C. v. Fidelity National Title Insurance
21 A.3d 952 (Connecticut Appellate Court, 2011)
Ventres v. Goodspeed Airport, LLC
21 A.3d 709 (Supreme Court of Connecticut, 2011)
U.K. Construction & Management, LLC v. Gore
20 A.3d 163 (Court of Special Appeals of Maryland, 2011)
Sosin v. Sosin
14 A.3d 307 (Supreme Court of Connecticut, 2011)
Weiss v. Weiss
998 A.2d 766 (Supreme Court of Connecticut, 2010)
Burton v. City of Stamford
17 A.3d 543 (Connecticut Superior Court, 2010)
Marandino v. Prometheus Pharmacy
986 A.2d 1023 (Supreme Court of Connecticut, 2010)
Sullivan v. Hyland
647 F. Supp. 2d 143 (D. Connecticut, 2009)
Dougan v. Dougan
970 A.2d 131 (Connecticut Appellate Court, 2009)
Hogan v. Department of Children & Families
964 A.2d 1213 (Supreme Court of Connecticut, 2009)
HH East Parcel, LLC v. Handy & Harman, Inc.
947 A.2d 916 (Supreme Court of Connecticut, 2008)
Department of Transportation v. White Oak Corp.
946 A.2d 1219 (Supreme Court of Connecticut, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
898 A.2d 803, 278 Conn. 578, 2006 Conn. LEXIS 198, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lasalla-v-doctors-associates-inc-conn-2006.