Waterfront Marine Construction, Inc. v. North End 49ers Sandbridge Bulkhead Groups A, B and C

468 S.E.2d 894, 251 Va. 417, 1996 Va. LEXIS 52
CourtSupreme Court of Virginia
DecidedApril 19, 1996
DocketRecord 951218
StatusPublished
Cited by64 cases

This text of 468 S.E.2d 894 (Waterfront Marine Construction, Inc. v. North End 49ers Sandbridge Bulkhead Groups A, B and C) is published on Counsel Stack Legal Research, covering Supreme Court of Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Waterfront Marine Construction, Inc. v. North End 49ers Sandbridge Bulkhead Groups A, B and C, 468 S.E.2d 894, 251 Va. 417, 1996 Va. LEXIS 52 (Va. 1996).

Opinion

JUSTICE LACY

delivered the opinion of the Court.

In this appeal we consider whether the trial court’s confirmation of an arbitration award was erroneous because the claims in the demand for arbitration either were not arbitrable or were barred by the doctrine of res judicata.

North End 49ers Sandbridge Bulkhead Groups A, B, and C (49ers) is an unincorporated association of 22 landowners in the Sandbridge section of Virginia Beach. In 1988, the 49ers sought bids for the construction of a bulkhead along their property. Waterfront Marine Construction, Inc. (WMC) presented a bid to construct sheet steel bulkheads with tiebacks rather than the wooden bulkheads previously used in the Sandbridge area. The 49ers accepted WMC’s bid and entered into an agreement with WMC for the construction of the bulkhead at a price of $850,740.00. 1 The construction contract included a provision providing for arbitration of any controversy or claim “arising out of or relating to the Contract or the breach thereof.”

In 1989, the 49ers hired an engineering firm to inspect the bulkhead WMC had installed after a bulkhead of similar design had failed during a storm. At that point, the 49ers’ bulkhead had not been completely backfilled. The inspection report concluded *422 that the bulkhead design and construction were defective. Following the receipt of this report, the 49ers filed a demand for arbitration with the American Arbitration Association (AAA). The 49ers sought damages of $1,212,282.00, based on bids they received for work they contended was necessary to correct deficiencies in the bulkhead. WMC also filed a demand with the AAA seeking to recover $127,382.44 — the unpaid balance of the construction price, plus interest and arbitration costs.

An arbitration panel comprised of three engineers was appointed by the AAA. Following a hearing, the panel entered an award on March 7, 1991, denying the 49ers’ claim and granting WMC’s claim. The arbitrators also ordered WMC to perform certain work relating to the tie rod connections and anchor piles within 60 days. According to the terms of the award, the work had to be performed to the satisfaction of an independent engineer jointly hired and paid by the 49ers and WMC. The award required WMC to guarantee the work done for one year from the date the independent engineer determined that the work was completed.

Despite numerous attempts, WMC and the 49ers could not agree on the independent engineer and, consequently, WMC did not perform the work required under the first arbitration award. During this time, the spring and summer of 1991, the parties engaged in settlement discussions. On October 31, 1991, an unusually strong northeaster hit the 49ers’ property, but the bulkhead did not collapse. A second storm hit five days later, damaging approximately 600 feet of the 2,340-foot bulkhead.

On January 16, 1992, the 49ers filed a second demand for arbitration with the AAA, characterizing it as “a continuation” of the previous arbitration case, and requesting that the same panel be assembled to hear the demand. They also sought punitive damages, The AAA determined, however, that the matter was “filed as a new matter” and that reconvening the members of the original arbitration panel required agreement of the parties. The AAA also noted that WMC had raised an issue of “arbitrability” and stated “[a]s a nonjudicial body, the Association cannot determine whether or not an issue is arbitrable. Therefore, we will proceed with further administration of this case, unless otherwise requested by both parties, or unless the moving party is stayed by court order.”

*423 WMC filed a motion in the trial court seeking a temporary injunction to stay the pending arbitration proceeding. In its pleadings, WMC also sought a declaratory judgment that the 49ers’ second arbitration demand was barred by collateral estoppel and res judicata. The trial court entered an ex parte order on September 4, 1992, enjoining the arbitration proceedings. Following a hearing on March 18, 1993, the trial court ruled from the bench that the first arbitration award was final, that it could be “recognized in the form of a judgment,” and that it could be enforced. The court found that there was no agreement to “arbitrate the arbitration award.”

The 49ers filed a motion to reconsider and, after further consideration of memoranda and argument of counsel, the trial court reversed its prior position and vacated its September 4 order enjoining further arbitration proceedings. The court entered an order on September 30, 1993, referring the following matters to arbitration: 1) whether the dispute involving the first arbitration award was arbitrable; 2) whether res judicata was applicable to the claim; and 3) whether the 49ers were entitled to punitive damages.

The arbitration panel determined that the dispute centering on enforcement of the first arbitration award was arbitrable. After a two-day hearing, the panel issued a second arbitration award on July 8, 1994. That award required the 49ers to pay WMC the balance due from the first arbitration award and required WMC to pay a total of $491,795.00 to the 49ers for repair and replacement of the bulkhead and tie-back system, pre-arbitration costs, and property damage.

Pursuant to Code § 8.01-581.09, the 49ers filed a motion in the trial court to confirm the second arbitration award. WMC filed a motion seeking to vacate the award pursuant to Code § 8.01-581.10 based on allegations, inter alia, that the arbitrators exceeded their authority by addressing issues that should have been resolved by the court and resolving issues that were not arbitrable. WMC also sought a modification of the award pursuant to Code § 8.01-581.011. After considering memoranda and argument of counsel, the trial court entered an order on March 30, 1995, denying WMC’s motion to vacate, granting WMC’s motion to modify by removing approximately $17,000 in pre-arbitration costs from the amount owed to the 49ers, and confirming the award as modified. We awarded WMC an appeal.

*424 WMC raises a number of issues in its challenge to the trial court’s action confirming the second arbitration award. These issues include whether the trial court’s reference of the second demand for arbitration to the arbitration panel was erroneous because the claims in the demand either were not arbitrable or were barred by the doctrine of res judicata, whether the trial court used the proper standard of review in confirming the second arbitration award, and whether compulsory arbitration is available to current members of the 49ers who were not signatories to the 1988 contract which contained the arbitration agreement. We begin by considering a threshold issue raised by WMC: whether the trial court erred in its determination that the arbitration panel should decide the arbitrability of the claims contained in the 49ers’ second demand for arbitration.

I. DECIDING ARBITRABILITY

WMC argues that the court, not the arbitrators, should determine whether a dispute is arbitrable.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Reza Hajiha v. Colleen Leyrer
Court of Appeals of Virginia, 2025
Canaan Homes LLC v. Perchuhy Kazhoyan Cummings
Court of Appeals of Virginia, 2023
Dale A. Happe v. Kathryn Zimmerman
Court of Appeals of Virginia, 2023
Buckmire v. Lasership Inc.
E.D. Virginia, 2022
CACI, Inc. -- FEDERAL v. Ngo
E.D. Virginia, 2021
Brush Arbor Home Construction v. Alexander
823 S.E.2d 249 (Supreme Court of Virginia, 2019)
Reed v. Beverly Hills Porsche
307 F. Supp. 3d 494 (W.D. Virginia, 2018)
Schuiling v. Harris
Supreme Court of Virginia, 2013
Sabo v. Dennis
948 N.E.2d 121 (Appellate Court of Illinois, 2011)
Storey Construction Inc. v. Hanks
224 P.3d 468 (Idaho Supreme Court, 2009)
Cimerring v. Orix Capital Markets, LLC
323 F. App'x 306 (Fifth Circuit, 2009)
McMillan v. Com.
671 S.E.2d 396 (Supreme Court of Virginia, 2009)
Samuel Dinnitt East v. Beth Bailey East
Court of Appeals of Virginia, 2008
Michael Anthony Dizon v. Commonwealth of Virginia
Court of Appeals of Virginia, 2008
Caperton v. AT Massey Coal Co., Inc.
679 S.E.2d 223 (West Virginia Supreme Court, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
468 S.E.2d 894, 251 Va. 417, 1996 Va. LEXIS 52, Counsel Stack Legal Research, https://law.counselstack.com/opinion/waterfront-marine-construction-inc-v-north-end-49ers-sandbridge-bulkhead-va-1996.