COURT OF APPEALS OF VIRGINIA UNPUBLISHED
Present: Judges Athey, Ortiz and Senior Judge Clements Argued at Leesburg, Virginia
CANAAN HOMES LLC, ET AL. MEMORANDUM OPINION* BY v. Record No. 1047-22-4 JUDGE DANIEL E. ORTIZ AUGUST 29, 2023 PERCHUHY KAZHOYAN CUMMINGS, ET AL.
FROM THE CIRCUIT COURT OF PRINCE WILLIAM COUNTY Tracy C. Hudson, Judge
Sean Patrick Roche (William E. Evans; Richard G. Cole III; Cameron/McEvoy PLLC, on briefs), for appellants.
Matthew A. Crist (Matthew A. Crist, PLLC, on brief), for appellees.
When an expansive arbitration clause incorporates a set of rules that require that the
arbitrator determine arbitrability issues, a trial court may not separately decide these issues. This
appeal arises from an arbitration clause in a construction contract between Canaan Homes LLC
and its owner, Wei Lu (collectively “Canaan Homes”), on one side, and Perchuhy and Aaron
Cummings (collectively “the Cummingses”), on the other side. Canaan Homes appeals the trial
court’s denial of its motion for arbitration, arguing that the arbitration clause is unambiguous and
enforceable and applies to both the underlying claims and questions of arbitrability. Because the
clause is unambiguous and incorporates the American Arbitration Association’s rules, which
provide that the arbitrator shall determine arbitrability, we reverse and remand.
* This opinion is not designated for publication. See Code § 17.1-413(A). BACKGROUND
In August 2020, the Cummingses contracted Canaan Homes to construct a new home for
$767,827. Clause H (“Default/Termination”) of the contract provides:
Upon default, the non[]-defaulting party will notify the other party in writing and this Agreement shall be considered null and void and of no further force or effect. However either party shall not be precluded from pursuing any remedies under applicable law for wrongful breach or cancellation of this Agreement.
In addition, Clause I (“Dispute Resolution/Arbitration”) provides:
You agree to have all claims, controversies, disputes, and other matters in question between you and us arising out of or relation [sic] to this Agreement (including any and all warranty documents, attachments or addenda hereto) or breach hereof or to any alleged defects relation [sic] to the condition decided by final and binding arbitration in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association or the Construction Arbitration Inc at our option, in effect on the date of any demand for arbitration hereunder. The demand for arbitration shall be filed in writing and shall be made within a reasonable time after the claim, controversy, dispute or other matter in question would be barred by the applicable statute of limitations. By agreeing to this, both parties acknowledge they are giving up rights they might process to have such claims disputes and other matters in question litigated in a court or jury trial. The foregoing agreement to arbitrate shall be enforceable under the prevailing Virginia arbitration law and the award rendered by the arbitrator shall be final and binding upon the parties.
In all circumstance[s], you shall not institute any adversarial proceedings against us unless you have given us prior written notice of and a reasonable opportunity to resolve such matter or cure any alleged breach. In the event that certain issues do not get resolved by arbitration, both parties waive their right to a jury trial.
From late 2020 to 2021, Canaan Homes allegedly breached the contract by “refus[ing] to
continue working, threaten[ing] to delay or cancel scheduled work after being paid for such work
and materials, and, when entreated to continue work, repl[ying] by cancelling subcontractors and
absconding with considerable sums of money.” On August 10, 2021, the Cummingses notified
Canaan Homes in writing that it was in default of the contract and that the contract was thus -2- “null and void and of no further force or effect.” In April 2022, the Cummingses filed a
complaint against Canaan Homes in Prince William County Circuit Court, arguing violation of
the Virginia Consumer Protection Act (Count I) and conversion (Count II) and requesting
invalidation of the mechanics lien on the Cummingses’ property (Count III). The Cummingses
argued that the arbitration clause was void and unenforceable because it unconscionably required
that the Cummingses “wait 5 years before they can bring a demand for arbitration.”
Canaan Homes filed a “Motion To Dismiss And/Or Application To Compel Arbitration
And Stay Proceedings,” arguing that the trial court could not determine the “[t]hreshold [i]ssue
of [a]rbitrability” because the agreement incorporated the “Construction Industry Arbitration
Rules of the American Arbitration Association,” which places this authority in the hands of the
arbitrator. Alternatively, Canaan Homes argued that the case was arbitrable because all three
counts were related to the contract. The Cummingses responded that Canaan Homes’ default
had already rendered the contract “[n]ull [a]nd [v]oid [o]r [u]nenforceable” under Clause H.
The trial court denied Canaan Homes’ motion for arbitration. It found that it could
decide arbitrability because the contract did not incorporate the American Arbitration
Association’s rules, but “simply refers to them as the manner of proceeding or the rules of
procedure once the case gets to arbitration.” The trial court noted that the issue was “further
confused by the reference to this other organization which defense counsel says doesn’t exist,
this thing called Construction Arbitration, Inc., at our option.” The trial court found that Clause
H terminates only “the obligation to perform further,” not the “parties’ rights to pursue
remedies,” and rejected the Cummingses’ argument that Canaan Homes’ default voided Clause I.
However, the trial court found Clause I unenforceable due to the ambiguity of the sentence: “The
demand for arbitration shall be filed in writing and shall be made within a reasonable time after
-3- the claim, controversy, dispute or other matter in question would be barred by the applicable
statute of limitations.”
Canaan Homes appeals, arguing that the trial court erred in denying its motion for
arbitration. It first argues that the trial court should not have addressed arbitrability because the
arbitration clause requires that the arbitrator determine that issue. Alternatively, it argues that the
Cummingses’ claims were arbitrable.
ANALYSIS
Because the contract contains an enforceable arbitration clause that covers both the
arbitrability question and the Cummingses’ substantive claims, the trial court erred in denying
Canaan Homes’ motion for arbitration.
I. Standard of Review
“We review a circuit court’s interpretation of contractual language, including language
governing arbitration, de novo.” Brush Arbor Home Constr., LLC v. Alexander, 297 Va. 151,
154 (2019).
II. The trial court erred in deciding arbitrability because the contract properly incorporated the Rules of the American Arbitration Association.
“[I]n the absence of a clear agreement showing that the parties intended that the arbitrator
decide questions of arbitrability, that question is to be resolved by the court.” Waterfront Marine
Constr., Inc. v. N. End 49ers Sandbridge Bulkhead Grps. A, B & C, 251 Va. 417, 427 (1996); see
also Code § 8.01-581.02(B). But “the parties by their contract can agree that [arbitrability]
Free access — add to your briefcase to read the full text and ask questions with AI
COURT OF APPEALS OF VIRGINIA UNPUBLISHED
Present: Judges Athey, Ortiz and Senior Judge Clements Argued at Leesburg, Virginia
CANAAN HOMES LLC, ET AL. MEMORANDUM OPINION* BY v. Record No. 1047-22-4 JUDGE DANIEL E. ORTIZ AUGUST 29, 2023 PERCHUHY KAZHOYAN CUMMINGS, ET AL.
FROM THE CIRCUIT COURT OF PRINCE WILLIAM COUNTY Tracy C. Hudson, Judge
Sean Patrick Roche (William E. Evans; Richard G. Cole III; Cameron/McEvoy PLLC, on briefs), for appellants.
Matthew A. Crist (Matthew A. Crist, PLLC, on brief), for appellees.
When an expansive arbitration clause incorporates a set of rules that require that the
arbitrator determine arbitrability issues, a trial court may not separately decide these issues. This
appeal arises from an arbitration clause in a construction contract between Canaan Homes LLC
and its owner, Wei Lu (collectively “Canaan Homes”), on one side, and Perchuhy and Aaron
Cummings (collectively “the Cummingses”), on the other side. Canaan Homes appeals the trial
court’s denial of its motion for arbitration, arguing that the arbitration clause is unambiguous and
enforceable and applies to both the underlying claims and questions of arbitrability. Because the
clause is unambiguous and incorporates the American Arbitration Association’s rules, which
provide that the arbitrator shall determine arbitrability, we reverse and remand.
* This opinion is not designated for publication. See Code § 17.1-413(A). BACKGROUND
In August 2020, the Cummingses contracted Canaan Homes to construct a new home for
$767,827. Clause H (“Default/Termination”) of the contract provides:
Upon default, the non[]-defaulting party will notify the other party in writing and this Agreement shall be considered null and void and of no further force or effect. However either party shall not be precluded from pursuing any remedies under applicable law for wrongful breach or cancellation of this Agreement.
In addition, Clause I (“Dispute Resolution/Arbitration”) provides:
You agree to have all claims, controversies, disputes, and other matters in question between you and us arising out of or relation [sic] to this Agreement (including any and all warranty documents, attachments or addenda hereto) or breach hereof or to any alleged defects relation [sic] to the condition decided by final and binding arbitration in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association or the Construction Arbitration Inc at our option, in effect on the date of any demand for arbitration hereunder. The demand for arbitration shall be filed in writing and shall be made within a reasonable time after the claim, controversy, dispute or other matter in question would be barred by the applicable statute of limitations. By agreeing to this, both parties acknowledge they are giving up rights they might process to have such claims disputes and other matters in question litigated in a court or jury trial. The foregoing agreement to arbitrate shall be enforceable under the prevailing Virginia arbitration law and the award rendered by the arbitrator shall be final and binding upon the parties.
In all circumstance[s], you shall not institute any adversarial proceedings against us unless you have given us prior written notice of and a reasonable opportunity to resolve such matter or cure any alleged breach. In the event that certain issues do not get resolved by arbitration, both parties waive their right to a jury trial.
From late 2020 to 2021, Canaan Homes allegedly breached the contract by “refus[ing] to
continue working, threaten[ing] to delay or cancel scheduled work after being paid for such work
and materials, and, when entreated to continue work, repl[ying] by cancelling subcontractors and
absconding with considerable sums of money.” On August 10, 2021, the Cummingses notified
Canaan Homes in writing that it was in default of the contract and that the contract was thus -2- “null and void and of no further force or effect.” In April 2022, the Cummingses filed a
complaint against Canaan Homes in Prince William County Circuit Court, arguing violation of
the Virginia Consumer Protection Act (Count I) and conversion (Count II) and requesting
invalidation of the mechanics lien on the Cummingses’ property (Count III). The Cummingses
argued that the arbitration clause was void and unenforceable because it unconscionably required
that the Cummingses “wait 5 years before they can bring a demand for arbitration.”
Canaan Homes filed a “Motion To Dismiss And/Or Application To Compel Arbitration
And Stay Proceedings,” arguing that the trial court could not determine the “[t]hreshold [i]ssue
of [a]rbitrability” because the agreement incorporated the “Construction Industry Arbitration
Rules of the American Arbitration Association,” which places this authority in the hands of the
arbitrator. Alternatively, Canaan Homes argued that the case was arbitrable because all three
counts were related to the contract. The Cummingses responded that Canaan Homes’ default
had already rendered the contract “[n]ull [a]nd [v]oid [o]r [u]nenforceable” under Clause H.
The trial court denied Canaan Homes’ motion for arbitration. It found that it could
decide arbitrability because the contract did not incorporate the American Arbitration
Association’s rules, but “simply refers to them as the manner of proceeding or the rules of
procedure once the case gets to arbitration.” The trial court noted that the issue was “further
confused by the reference to this other organization which defense counsel says doesn’t exist,
this thing called Construction Arbitration, Inc., at our option.” The trial court found that Clause
H terminates only “the obligation to perform further,” not the “parties’ rights to pursue
remedies,” and rejected the Cummingses’ argument that Canaan Homes’ default voided Clause I.
However, the trial court found Clause I unenforceable due to the ambiguity of the sentence: “The
demand for arbitration shall be filed in writing and shall be made within a reasonable time after
-3- the claim, controversy, dispute or other matter in question would be barred by the applicable
statute of limitations.”
Canaan Homes appeals, arguing that the trial court erred in denying its motion for
arbitration. It first argues that the trial court should not have addressed arbitrability because the
arbitration clause requires that the arbitrator determine that issue. Alternatively, it argues that the
Cummingses’ claims were arbitrable.
ANALYSIS
Because the contract contains an enforceable arbitration clause that covers both the
arbitrability question and the Cummingses’ substantive claims, the trial court erred in denying
Canaan Homes’ motion for arbitration.
I. Standard of Review
“We review a circuit court’s interpretation of contractual language, including language
governing arbitration, de novo.” Brush Arbor Home Constr., LLC v. Alexander, 297 Va. 151,
154 (2019).
II. The trial court erred in deciding arbitrability because the contract properly incorporated the Rules of the American Arbitration Association.
“[I]n the absence of a clear agreement showing that the parties intended that the arbitrator
decide questions of arbitrability, that question is to be resolved by the court.” Waterfront Marine
Constr., Inc. v. N. End 49ers Sandbridge Bulkhead Grps. A, B & C, 251 Va. 417, 427 (1996); see
also Code § 8.01-581.02(B). But “the parties by their contract can agree that [arbitrability]
issues be decided by the arbitrator.” Waterfront Marine Constr., 251 Va. at 425. When an
“arbitration clause includes expansive language and incorporates a specific set of rules requiring
that the arbitrator determine arbitrability,” it constitutes “clear and unmistakable” evidence that
the parties intended for the arbitrator to determine arbitrability. Brenco Enters., Inc. v.
Bitesquad.com, LLC, 297 F. Supp. 3d 608, 611-12 (E.D. Va. 2018). -4- 1. The parties’ agreement is expansive and evidences an intent to have the arbitrator decide issues of arbitrability.
Here, the arbitration clause is broad and expansive. It covers “all claims, controversies,
disputes, and other matters in question between [the parties] arising out of or relation [sic] to this
Agreement . . . or breach hereof or to any alleged defects relation [sic] to the condition.” And it
provides that any such dispute will be decided by arbitration “in accordance with the
Construction Industry Arbitration Rules of the American Arbitration Association or the
Construction Arbitration Inc at [Canaan Homes’] option.”
Because both parties agree that “Construction Arbitration Inc” is a non-existent entity,
the only arbitration rules available to the parties are the Construction Industry Arbitration Rules
of the American Arbitration Association (the “AAA Rules”). Under the AAA Rules, “[t]he
arbitrator shall have the power to rule on his or her own jurisdiction” and to “determine the
existence or validity of a contract of which an arbitration clause forms a part.” American
Arbitration Association, Construction Industry Arbitration Rules and Mediation Procedures,
Rule 9 (rev. May 1, 2022). The broad reference to the AAA Rules in the arbitration clause thus
evidences a “clear and unmistakable” intent by the parties to have the arbitrator determine
arbitrability.
2. The trial court erred in finding that the contract did not incorporate the Rules of the American Arbitration Association.
In denying Canaan Homes’ motion for arbitration, the trial court found that the arbitration
clause does not incorporate the AAA Rules, but “simply refers to them as the manner of
proceeding or the rules of procedure once the case gets to arbitration.” We disagree. In the
absence of Virginia precedent directly on point, we turn to federal case law for instructions.
Federal courts have generally considered rules incorporated when an arbitration clause requires
-5- dispute resolution to follow those rules. See, e.g., Simply Wireless, Inc. v. T-Mobile US, Inc.,
877 F.3d 522, 525, 528 (4th Cir. 2017); Brenco Enters., 297 F. Supp. 3d at 611-12.
In Simply Wireless, the Fourth Circuit found that an arbitration clause explicitly
incorporated the JAMS Rules when it stated: “arbitration shall be administered pursuant to the
JAMS Comprehensive Rules and Procedures then in effect.” 877 F.3d at 525. It found that the
language constituted an “explicit incorporation of JAMS Rules” and thus “‘clear and
unmistakable’ evidence of the parties’ intent to arbitrate arbitrability.” Id. at 528. Similarly, in
Brenco Enterprises, the United States District Court for the Eastern District of Virginia found
that the language “in accordance with the Commercial Arbitration Rules of the American
Arbitration Association” incorporated these rules and “manifest[ed] the parties’ clear intention to
commit the arbitrability determination to the arbitrator.” 297 F. Supp. 3d at 612. Thus,
contractual language requiring disputes be arbitrated in accordance with certain rules should be
interpreted as incorporating those rules. This interpretation is also consistent with persuasive
authorities from other states. See, e.g., TotalEnergies E&P USA, Inc. v. MP Gulf of Mexico,
LLC, 667 S.W.3d 694, 709 (Tex. 2023), reh’g denied (June 9, 2023) (holding that an agreement
to arbitrate disputes “in accordance with the rules of the AAA” thereby incorporates the AAA
Rules); Epic Games, Inc. v. Murphy-Johnson, 785 S.E.2d 137, 143-44 (N.C. Ct. App. 2016)
(finding that a clause that requires that arbitration be “conducted pursuant to” the AAA Rules
incorporates these rules).
Although the Cummingses correctly point out that none of this case law is binding upon
this Court, they fail to cite any case law to the contrary—that is, case law that draws a distinction
between incorporating certain arbitration rules and “simply refer[ing] to them as the manner of
proceeding or the rules of procedure once the case gets to arbitration.” And they do not cite any
cases suggesting that the word “incorporate” is required for an arbitration clause to incorporate a
-6- set of arbitration rules. Thus, reviewing de novo, we find the language of the arbitration clause
sufficient to incorporate the AAA Rules.
3. The trial court correctly found that Clause H did not void the arbitration clause.
While denying Canaan Homes’ motion for arbitration, the trial court correctly found that
Clause H simply “terminates the obligation to perform further” in case of a breach and “does not
impair the parties’ rights to pursue remedies.” Thus, Clause H did not terminate Clause I, which
only addresses “the manner of pursuing remedies.”
Assuming arguendo that the parties intended Clause H to terminate the entire contract,
the Cummingses’ argument still fails, as the triggering event of Clause H would be a “default,”
not an alleged default. Here, Canaan Homes’ default is in dispute. The contract’s dispute
resolution provisions would remain effective until a fact finder determines that a default
occurred.
4. The trial court erred in finding Clause I ambiguous and, therefore, unenforceable.
The trial court found that the second sentence in Clause I, “The demand for arbitration
shall be filed in writing and shall be made within a reasonable time after the claim, controversy,
dispute or other matter in question would be barred by the applicable statute of limitations,” was
ambiguous and renders the arbitration clause unenforceable. We disagree. While poorly drafted,
the sentence is not ambiguous when interpreted within context.
A contractual provision is ambiguous “when, in context, it is capable of more than one
reasonable meaning.” Res. Bankshares Corp. v. St. Paul Mercury Ins. Co., 407 F.3d 631, 636
(4th Cir. 2005) (emphasis added); see also Caldwell v. Transp. Ins. Co., 234 Va. 639 (1988).
Thus, if contractual language has two literal meanings, but one of them is unreasonable, the
language is not ambiguous. Cf. Dixon Lumber Co., Inc. v. Austinville Limestone Co., Inc., 256 F.
-7- Supp. 3d 658, 671 (W.D. Va. 2017) (“Contract language is ambiguous only when it is capable of
more than one reasonable meaning, so alternative but unreasonable interpretations of a contract
do not preclude summary judgment.” (internal quotation marks and citation omitted)). In
contractual interpretation, the “plain meaning of a word depends not merely on semantics and
syntax but also on the holistic context of the word within the instrument,” and “[c]onsequently,
every word, clause, and provision of the policy ‘should be considered and construed together and
seemingly conflicting provisions harmonized when that can be reasonably done.’” Erie Ins.
Exch. v. EPC MD 15, LLC, 297 Va. 21, 28 (2019) (quoting Floyd v. N. Neck Ins., 245 Va. 153,
158 (1993); see also Yarborough v. Atl. Life Ins. Co., 84 F.2d 319, 320 (4th Cir. 1936) (“It is . . .
an equally well-established rule of interpretation that all provisions of a contract should be
construed in harmony with one another, if it can be done reasonably, in order to avoid
repugnancy between the several parts of the instrument.”).
The trial court found that to enforce the provision, it would have to rewrite it, either by
replacing the word “shall” with “may” or replacing “after” to “before.” But the trial court need
not, and should not, rewrite the provision here. The provision has two literal meanings—first,
that the arbitration demand must be made within a reasonable time but after the statute of
limitations expires, or second, that the arbitration demand must be made before the end of a
reasonable time if made after the statute of limitations expires. The first interpretation is
unreasonable, as it would render meaningless the provision, “In the event that certain issues do
not get resolved by arbitration, both parties waive their right to a jury trial.” If a claim could not
be arbitrated until its statute of limitations expires, then the parties would no longer have an
opportunity to litigate any issues left unresolved by arbitration, whether with a jury or not. In
fact, even the Cummingses argue that it would be “unconscionable” to require “the parties to
wait five years before starting the arbitration process.” The second interpretation—that the
-8- language simply extends the statute of limitations for arbitration purposes for a reasonable
time—is the only reasonable interpretation. Thus, the provision is unambiguous and
enforceable.1
CONCLUSION
Because the parties’ arbitration clause explicitly incorporates the AAA Rules, which
authorize the arbitrator to determine arbitrability, the trial court erred in denying Canaan Homes’
motion for arbitration. We reverse and remand for the trial court to compel arbitration and stay
further proceedings.2
Reversed and remanded.
1 Even if the second sentence of Clause I were ambiguous, it would not automatically render the first sentence unenforceable, under which the arbitrator would still have the authority to determine arbitrability issues, including whether the request for arbitration was timely. 2 The Cummingses requested attorney fees associated with this appeal. The arbitrator will resolve this issue, as the prevailing party is entitled to attorney fees under Clause H. -9-