Wellons, Inc., a Corporation v. T.E. Ibberson Company and Ibberson Engineering, Inc., Formerly Known as Kibcor Engineering, Inc., Corporations

869 F.2d 1166
CourtCourt of Appeals for the Eighth Circuit
DecidedApril 24, 1989
Docket88-5026
StatusPublished
Cited by61 cases

This text of 869 F.2d 1166 (Wellons, Inc., a Corporation v. T.E. Ibberson Company and Ibberson Engineering, Inc., Formerly Known as Kibcor Engineering, Inc., Corporations) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wellons, Inc., a Corporation v. T.E. Ibberson Company and Ibberson Engineering, Inc., Formerly Known as Kibcor Engineering, Inc., Corporations, 869 F.2d 1166 (8th Cir. 1989).

Opinion

HEANEY, Circuit Judge.

Wellons, Inc. appeals from a district court order granting summary judgment in favor of T.E. Ibberson Company and Ibber-son Engineering, Inc., formerly known as Kibcor Engineering, Inc. We affirm.

BACKGROUND

National Sun Industries, Inc. (NSI) built a sunflower seed processing plant in End-erlin, North Dakota during the years of 1981 and 1982. The plant was designed to produce sunflower oil and meal for sale and to produce hulls which would be burned to produce steam to process the seeds and to generate electricity. NSI retained Ibberson Engineering as engineer on the project and T. E. Ibberson as construction manager.

T.E. Ibberson and Ibberson Engineering (collectively Ibberson) solicited a bid from Wellons for the construction of two steam boilers to burn the seed hulls. Sometime during the bidding process, Ibberson provided Wellons with certain test results from independent testing laboratories which detailed the burning characteristics of the hulls. Wellons apparently used these test results in calculating its bid. This bid was subsequently accepted by NSI.

In late 1982, construction of the boilers was finished. Soon thereafter, NSI began to encounter problems because ash from the sunflower seed hulls fused to the pipes and walls of the boilers. Apparently, the temperature at which the hulls melted was much lower than anticipated and the fused hulls clogged the pipes, reducing the production of steam. Wellons returned to the plant and modified the boilers in an attempt to eliminate this problem.

In January 1984, NSI commenced a lawsuit against Wellons in North Dakota state court, alleging that Wellons had improperly designed the boilers causing it to incur substantial losses. The court stayed the action after Wellons invoked the arbitration clause in its contract with NSI. In August 1985, an arbitration panel awarded NSI $3,623,006 against Wellons. NSI moved to confirm the award in the United States District Court for the District of Minnesota. Wellons cross-claimed, moving the court to vacate the award.

In September 1985, Wellons commenced this action against Ibberson in North Dako *1168 ta, alleging that Wellons suffered losses when Ibberson intentionally misrepresented or negligently led Wellons to believe that the burning hull test results were correct. It also sought contribution or indemnification for the arbitration award against it.

Shortly after this suit was filed, but before the Minnesota court had confirmed the arbitration award, NSI and Wellons settled their dispute. Wellons agreed to pay NSI the entire amount of the award. The settlement provided for a mutual release of all claims and for dismissal of the confirmation suit in Minnesota.

Ibberson then sought summary judgment against Wellons in this suit, alleging that the doctrine of collateral estoppel barred Wellons’ suit as the issue of Ibber-son’s liability for the boilers’ malfunctioning had been rejected by the arbitration panel. It also alleged that Wellons’ claims for contribution or indemnity were barred under North Dakota law.

After considering these arguments, a magistrate recommended that the motion for summary judgment as to the application of collateral estoppel be denied because the finality of the arbitration award was extinguished by the settlement. The district court refused to adopt the magistrate’s recommendation as to the application of collateral estoppel in this case because it found that the settlement agreement had adopted the arbitration award, making it “final” for collateral estoppel purposes. Thus, it granted the motion for summary judgment in favor of Ibberson.

DISCUSSION

Wellons argues on appeal that the district court erred in giving collateral estop-pel effect to the arbitration proceeding between Wellons and NSI because no final judgment occurred in that action and because the issues of law and fact involved were different than those presented in this case.

Collateral estoppel is appropriate when: (1) the issue sought to be precluded is identical to the issue previously decided; (2) the prior action resulted in a final adjudication on the merits; (3) the party sought to be estopped was either a party or in privity with a party to the prior action; and (4) the party sought to be estopped was given a full and fair opportunity to be heard on the issue in the prior action. Arkla Exploration Co. v. Texas Oil & Gas Corp., 734 F.2d 347, 356 (8th Cir.1984), cert. denied, 469 U.S. 1158, 105 S.Ct. 905, 83 L.Ed.2d 920 (1985). The present case focuses on the first two requirements, as Wellons was a party to the arbitration proceeding and does not allege that it did not receive a fair hearing before the arbitrators.

We agree with the district court that an arbitration award may constitute a final judgment for purposes of collateral estoppel. See City of Bismarck v. Toltz, King, Duvall, et al., 855 F.2d 580, 582-88, (8th Cir.1988); French v. Jinright & Ryan, P.C., 735 F.2d 433, 436 (11th Cir.1984); Jeffers v. Convoy Co., 636 F.Supp. 1337, 1339 (D.Minn.1986) (collateral estoppel may be applied to an arbitration decision); United Food, Etc. v. G. Bartusch Packing Co., 546 F.Supp. 852, 855 (D.Minn.1982) (arbitration decision counts as a prior adjudication when defendant seeks to use prior decision to bar plaintiff’s claim).

In City of Bismarck, supra, the city brought a suit for damages against a sewer project contractor and an engineering firm for the negligent design and construction of a sewage system. As required by their contract, the city and the contractor removed their suit to arbitration. The contractor alleged that the city failed to pay it for construction delays due to faulty plans and soil problems encountered on the job. The arbitration panel found that the contractor owed the city $612,500 for faulty construction and the city owed the contractor $885,000 for payments due under the contract. The city then amended its complaint against the engineering firm in federal district court, increasing its damage request. A panel of this Court held that the arbitration award operated as a final adjudication for collateral estoppel purposes. The panel found that the city was collaterally estopped from suing the engi *1169 neer for negligent inspection and supervision because the claim that the sewage system was defective had been presented to the arbitrators, the city had argued that the contractor was completely liable for this defect, and the city had received an award equal to the amount it had originally requested in its civil suit against both parties. 855 F.2d at 583. Thus, it is clear that an arbitration award may operate as a final adjudication for the purposes of collateral estoppel.

The fact that the award in the present case was not confirmed by a court and was modified by a subsequent settlement agreement does not vitiate the finality of the award.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bostick v. DST Systems Inc
W.D. Missouri, 2021
Carroll v. DST Systems Inc
W.D. Missouri, 2021
Campfield v. DST Systems Inc
W.D. Missouri, 2021
Sutton v. DST Systems Inc
W.D. Missouri, 2021
Rutkowski v. DST Systems Inc
W.D. Missouri, 2021
Dunbar v. DST Systems Inc
W.D. Missouri, 2021
Hursh v. DST Systems, Inc.
W.D. Missouri, 2021
Newger v. First Contact, LLC
E.D. Missouri, 2020
Portal Invs., LLC v. Johnson (In re Johnson)
584 B.R. 895 (D. North Dakota, 2018)
Dumont Telephone Co. v. Power & Telephone Supply Co.
962 F. Supp. 2d 1064 (N.D. Iowa, 2013)
Cody Farms, Inc. v. Deerman (In re Deerman)
482 B.R. 344 (D. New Mexico, 2012)
Ronald Byers v. Edina Couriers, LLC
475 F. App'x 638 (Eighth Circuit, 2012)
Rfms, Inc. v. United States
736 F. Supp. 2d 1222 (S.D. Iowa, 2010)
In Re Heaviside
433 B.R. 749 (E.D. Missouri, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
869 F.2d 1166, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wellons-inc-a-corporation-v-te-ibberson-company-and-ibberson-ca8-1989.