Text

If after the making of an award which requires the contractor to do further work, any controversies arise between the parties as to the doing of such work, the controversies may be submitted to the same arbitrators on five days' notice for further determination.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Byron's Construction Co. v. North Dakota Department of Transportation
463 N.W.2d 660 (North Dakota Supreme Court, 1990)
7 case citations