Gratech Co. v. North Dakota Department of Transportation

2004 ND 61, 676 N.W.2d 781, 2004 N.D. LEXIS 68, 2004 WL 560608
CourtNorth Dakota Supreme Court
DecidedMarch 23, 2004
Docket20030203
StatusPublished
Cited by2 cases

This text of 2004 ND 61 (Gratech Co. v. North Dakota Department of Transportation) is published on Counsel Stack Legal Research, covering North Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gratech Co. v. North Dakota Department of Transportation, 2004 ND 61, 676 N.W.2d 781, 2004 N.D. LEXIS 68, 2004 WL 560608 (N.D. 2004).

Opinion

MARING, Justice.

[¶ 1] Gratech Company, Ltd. appeals from a judgment dismissing its application to vacate the decision of the arbitration panel in Gratech’s arbitration action against the North Dakota Department of Transportation (“DOT”). We affirm, concluding the arbitration panel did not err in concluding that Gratech’s failure to file a written notice of claim precluded arbitration of all but one of Gratech’s claims against DOT.

I

[¶ 2] In the fall of 1998, DOT awarded two separate road construction contracts to Flickertail Paving and Supply, LLC (“Flickertail”) to tear out, regrade, and repave portions of U.S. Highway 281. The projects were labeled the Belcourt project and the Rolla project. Flickertail subcontracted the grading portions of the projects to Gratech.

*782 [¶ 3] Gratech encountered poor soil conditions on both projects, resulting in additional subcutting, plowing, discing, and drying of the soil. The parties dispute the extent of the poor soil conditions and its impact upon the projects.

[¶ 4] Gratech concedes it did not give a contemporaneous notice of intent to seek additional compensation under N.D.C.C. § 24-02-26.1 or under the contract provisions requiring such notice. Flickertail, however, did give a contemporaneous written notice of claim for alleged increased compensation it claimed it was owed.

[¶ 5] Upon completion of the projects, Flickertail requested additional compensation on the Rolla project and Gratech sought additional compensation on both projects from DOT. DOT denied these claims, and Flickertail and Gratech filed separate demands for arbitration. DOT counterclaimed for indemnity against Flickertail, and all claims of the parties were consolidated into a single arbitration proceeding.

[¶ 6] A hearing was conducted, and the arbitrators issued a written decision. Flickertail was awarded $411,408 on its claim for additional compensation on the Rolla project. That claim is not before this Court on appeal.

[¶ 7] On Gratech’s claims, the arbitrators initially determined that Gratech’s failure to file a notice of claim under N.D.C.C. § 24-02-26.1 and the provisions of the contract precluded arbitration of all but one of Gratech’s claims. The arbitrators also, in the alternative, concluded that on the merits Gratech was not entitled to additional compensation on the barred claims. On the one claim properly before the arbitrators, they awarded Gratech an additional $55,651 for “muck excavation” on the Belcourt project.

[¶ 8] Gratech filed an application in district court to vacate the arbitration award. The district court affirmed the arbitration award and dismissed Gratech’s application to vacate the award. Gratech appealed to this Court.

II

[¶ 9] The dispositive issue on appeal is whether Gratech was required to file a written notice of claim as a prerequisite to arbitrating its claims against DOT.

A

[¶ 10] Gratech initially asks this Court to adopt a heightened standard of review for questions of law in a statutorily mandated arbitration.

[¶ 11] We have generally held that arbitrators are the judges of both the law and the facts, and a court will vacate an arbitration award on its merits only if the award is completely irrational. See, e.g., John T. Jones Constr. Co. v. City of Grand Forks, 2003 ND 109, ¶¶ 9-10, 665 N.W.2d 698; Superpumper, Inc. v. Norland Oil, Inc., 2003 ND 33, ¶ 13, 657 N.W.2d 250; State v. Gratech Co., 2003 ND 7, ¶ 12, 655 N.W.2d 417. Under the completely irrational standard, an arbitrator’s mistake in determining the facts or interpreting the law is not a sufficient ground for overturning the award. John T. Jones, at ¶ 9; Superpumper, at ¶¶ 13-14.

[¶ 12] Gratech invites us to modify that standard and to apply a de novo standard allowing full review by a reviewing court of questions of law in statutorily mandated arbitrations. In support of its argument, Gratech relies upon this Court’s comments in a footnote in Allstate Ins. Co. v. Nodak Mut. Ins. Co., 540 N.W.2d 614 (N.D.1995). In Allstate, the Court noted that some courts had adopted a minority view and applied a heightened standard of review to *783 questions of law when the arbitration is compelled by statute. Id. at 620 n. 2; see American Universal Ins. Co. v. DelGreco, 205 Conn. 178, 530 A.2d 171, 179 (1987); Allstate Ins. Co. v. Caltabiano, 74 Conn. App. 49, 809 A.2d 1153, 1156 (2002); Detroit Auto. Inter-Ins. Exch. v. Gavin, 416 Mich. 407, 331 N.W.2d 418, 434-35 (1982); Johnson v. American Family Mut. Ins. Co., 426 N.W.2d 419, 421 (Minn.1988) (automobile no-fault arbitration); Gilder v. Auto-Owners Ins. Co., 659 N.W.2d 804, 807 (Minn.Ct.App.2003) (same); Racine v. AMCO Ins. Co., 605 N.W.2d 773, 775 (Minn.Ct.App.2000) (same).

[¶ 13] We find it unnecessary to resolve this issue in this case because we conclude that, applying either standard, the arbitrators correctly determined that Gratech waived its right to arbitrate its claims by failing to file a notice of claim in compliance with N.D.C.C. § 24-02-26.1 and the provisions of the contract.

B

[¶ 14] All disputes arising out of any contract entered into by DOT for the construction or repair of highways must be submitted to arbitration. N.D.C.C. § 24-02-26; Gratech Co. v. Wold Eng’g, P.C., 2003 ND 200, ¶ 16, 672 N.W.2d 672; State v. Gratech Co., 2003 ND 7, ¶¶ 10, 19, 655 N.W.2d 417. By voluntarily entering into a highway construction contract, the parties are deemed to have agreed to arbitration of all disputes arising out of the contract. N.D.C.C. § 24-02-26; Gratech, 2003 ND 7, ¶ 19, 655 N.W.2d 417.

[¶ 15] Section 24-02-26.1, N.D.C.C., provides that, as a condition precedent to arbitration, any person seeking additional compensation for work not covered in the contract must file a written notice of claim:

Condition precedent to contractor demand for arbitration — Claims for extra compensation. In addition to the provisions of section 24-02-30, full compliance by a contractor with the provisions of this section is a condition precedent to the contractor’s right to demand arbitration.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gratech Co., Ltd. v. Wold Engineering, PC
2007 ND 46 (North Dakota Supreme Court, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
2004 ND 61, 676 N.W.2d 781, 2004 N.D. LEXIS 68, 2004 WL 560608, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gratech-co-v-north-dakota-department-of-transportation-nd-2004.