Ure v. Wangler Const. Co., Inc.

597 N.E.2d 759, 232 Ill. App. 3d 492, 173 Ill. Dec. 785, 1992 Ill. App. LEXIS 1178
CourtAppellate Court of Illinois
DecidedJuly 21, 1992
Docket1-91-2053
StatusPublished
Cited by22 cases

This text of 597 N.E.2d 759 (Ure v. Wangler Const. Co., Inc.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ure v. Wangler Const. Co., Inc., 597 N.E.2d 759, 232 Ill. App. 3d 492, 173 Ill. Dec. 785, 1992 Ill. App. LEXIS 1178 (Ill. Ct. App. 1992).

Opinion

PRESIDING JUSTICE HARTMAN

delivered the opinion of the court:

A contractor, Wangler Construction Company, Inc. (Wangler), seeks reversal of a judgment on the pleadings, which confirmed an arbitration award. The issues presented on appeal are whether (1) the arbitrator exceeded his authority by not following certain express contract terms; (2) Wangler waived this argument; and (3) judgment on the pleadings was properly entered by the circuit court against Wangler. We affirm.

David Ure and Estelle Ure (the Ures) entered into two written contracts, one with an architect, Reno J. Masini Associates (Masini), and one with Wangler, the former to design and the latter to construct a residence. After the residence was substantially built, disputes concerning design and construction arose between the Ures, Masini and Wangler, which the parties were unable to resolve.

On May 26, 1989, the Ures filed separate demands for arbitration. Each demand was entitled “Joint Demand for Arbitration.” One demand named Wangler as respondent and claimed, among other things, that Wangler “negligently, improperly and in an un-workmanlike manner constructed the home which caused over-stressing and deflection of the beams in the house and did not complete all contract items properly[,] causing the owner great sums of money to remedy the defects and to complete the home.” The other demand asserted that Masini negligently and improperly designed the home which caused overstressing and deflection of beams in the house which had to be repaired and remedied at great cost to the owner. By letter dated June 15, 1989, the Ures’ attorney notified Wangler that he had filed “a Joint Demand for Arbitration *** against you and Reno J. Masini Associates,” and enclosed a copy thereof.

On June 21, 1989, the American Arbitration Association (AAA) notified Wangler and Masini of the “[djemand requesting that arbitration be initiated between the parties whose names are set forth in the caption.” In the caption, Wangler was listed as “Respondent #1” and Masini was listed as “Respondent #2.” The AAA assigned to the demands a single case number and treated them as consolidated. A list of names selected from the “National Panel” was provided to the parties, from which an arbitrator was to be appointed, with instructions to strike any names not acceptable. On July 25, 1989, Wangler’s attorneys sent a letter to the AAA indicating their representation of Wangler and enclosing a list showing Wangler’s preferences in the selection of an arbitrator. No objection to consolidation was then raised by any party.

On August 7, 1989, AAA sent a letter to all parties requesting that they respond to the AAA by August 17, 1989, “as to whether this arbitration will continue with the above captioned parties, or with Trus-Joist Corporation included as an additional [Respondent,” adding that Trus-Joist Corporation will be added only if all parties agree. Wangler’s counsel, on August 10, 1989, asserted in a letter that Wangler “has no objection to the addition of Trus-Joist Corporation as an additional respondent in this case.” (Emphasis added.) Trus-Joist declined to be a part of the arbitration, however, and on August 16, 1989, AAA sent written notice that it would proceed with the above-captioned parties, again listing Wangler as respondent No. 1 and Masini as respondent No. 2, without Wangler’s objection. On August 28, 1989, Wangler’s counsel sent a letter to the AAA, memorializing a telephone conversation involving a dispute as to the chosen arbitrator. On August 30, 1989, AAA sent a letter to the attorneys for the parties, acknowledging receipt of the letter from Wangler’s attorney, again listing Wangler as respondent No. 1 and Masini as respondent No. 2 under a single case number. On September 15, 1989, AAA advised the parties that the arbitrator resigned from the matter, indicating again that Wangler was respondent No. 1 and Masini respondent No. 2. In five subsequent letters sent to the parties’ attorneys, the respondents always were identified in the same way, without objection to consolidation.

The hearing convened on January 30, 1990. All parties were then present. All exhibits to be considered were marked. Witnesses were ready to testify. When counsel were asked to make opening statements, the attorneys for Wangler objected to a joint arbitration for the first time, in part as follows:

“[Wangler’s Attorney]: I would point out that the language in Article 6 [of the contract] is mirrored in Article 7.9, in the general conditions of the contracts between the owner and contractor, which also provides, and I quote, *** [reading the contract language quoted under part I of this opinion].
To my knowledge, there is no such signed written consent that pertains in this case.
And we would submit that the claimant in this case has to proceed separately on his claim against the architect and separately on his claim against the contractor.
And we would object to the consolidations in this matter.
[Ures’ Attorney]: If I may respond, we filed the proceedings, two proceedings, and asked the matter be consolidated in order to conserve time and effort and, of course, cost.
This is the first instance where this point has been raised at this late stage. I believe there’s been a waiver here of this provision.
I don’t see what jeopardy they possibly could have to go through two proceedings at the same facts.”

The arbitrator responded as follows:

"I’m just curious as to why with the arbitration structured as David Ure versus Wangler Construction Company, Inc., and Reno J. Masini, there was an agreement to the appointment of an arbitrator and to the scheduling of the hearing.
I’m just curious as to why this has never been raised with the tribunal, with the association, prior to our sitting down here today with witnesses present. And I wonder why this wasn’t raised with the tribunal administrator, Laura Brown, when she scheduled this as it was.
This was all scheduled, as I can see it, as a consolidated matter. And, apparently, no one has determined to raise this objection until this time when we’re all scheduled to sit here.
I’m inclined to deny that request and proceed with it the way it is, but I do want to check with the tribunal administrator to see whether or not there have been what would be, I guess, a waiver or an estoppel to the bringing of the motion at this time.
*** I believe the challenges to the procedure are raised first with the tribunal administrator and that the arbitrator then acts as a finder of fact.”

The arbitrator then consulted with the tribunal administrator and thereafter ruled as follows:

“I have consulted with the tribunal administrator.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Amerisure Mutual Insurance v. Global Reinsurance Corp. of America
927 N.E.2d 740 (Appellate Court of Illinois, 2010)
Woods v. Patterson Law Firm, P.C.
886 N.E.2d 1080 (Appellate Court of Illinois, 2008)
Salsitz v. Kreiss
761 N.E.2d 724 (Illinois Supreme Court, 2001)
7-Eleven, Inc. v. Dar
Appellate Court of Illinois, 2001
Bishop v. We Care Hair Development Corp.
738 N.E.2d 610 (Appellate Court of Illinois, 2000)
State Farm v. Hyman
Appellate Court of Illinois, 1999
State Farm Mutual Automobile Insurance v. George Hyman Construction Co.
715 N.E.2d 749 (Appellate Court of Illinois, 1999)
Ryan v. Kontrick
Appellate Court of Illinois, 1999
Christian Dior, Inc. v. Schaffner & Marx
637 N.E.2d 546 (Appellate Court of Illinois, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
597 N.E.2d 759, 232 Ill. App. 3d 492, 173 Ill. Dec. 785, 1992 Ill. App. LEXIS 1178, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ure-v-wangler-const-co-inc-illappct-1992.